A, B, and C together can complete a piece of work in 10 days. A alone can do it in 20 days, and B in 30 days. How many days will C alone take to complete the work?
60
One day's work: A + B + C = \(\frac{1}{10}\), A = \(\frac{1}{20}\), B = \(\frac{1}{30}\).
C's one day's work = \(\frac{1}{10} - \frac{1}{20} - \frac{1}{30} = \frac{6 - 3 - 2}{60} = \frac{1}{60}\).
So C alone needs 60 days.
Hence, the answer is 60.
A and B can complete a task together in 12 days, while B and C can finish it in 16 days. After A works on it for 5 days and B for 7 days, C takes the remaining 13 days to finish the work. How many days would it take for C to complete the work alone?
A is three times more efficient as a worker than B, which allows A to complete a job in 60 days less than B. If they work together, they can finish the job in:
If 6 machines complete a task in 10 days, how many days for 15 machines at the same rate?
A can do a work in 8 days and B in 12 days. They work together for 3 days. What part of the work is left?
A and B together can complete a work in 12 days. B and C together can complete the same work in 15 days. C and A together can do it in 20 days. In how many days can A alone complete the job?
A, B, and C are capable of completing a job in 30, 45, and 90 days, respectively. A works every day, while B and C join A every fifth day. How long will it take to finish the task?