All Exams Test series for 1 year @ ₹349 only
Question

A and B can do a work together in 18 days. A is three times as efficient as B. In how many days can B alone complete the work?

This question was previously asked in
SSC CGL 2019 (Tier 2) GS Finance & Economics Previous Year Paper (17-Nov-2020)
The correct answer is

72 days

Understanding the Problem: Time, Work, and Efficiency

This problem involves the concept of time and work, specifically focusing on the relationship between efficiency and the time taken to complete a task. We are given the combined time taken by two individuals, A and B, to complete a work, and a relationship between their efficiencies. We need to find the time taken by one individual, B, to complete the same work alone.

Key Concepts: Efficiency and Work

  • Efficiency: Efficiency is defined as the amount of work done per unit of time. Higher efficiency means less time is required to complete a given amount of work.
  • Work: The total amount of task to be completed. It is often considered as a fixed unit (e.g., 1 unit of work) or calculated based on efficiency and time (Work = Efficiency × Time).

Setting up the Problem

We are given two main pieces of information:

  1. A and B together can complete the work in 18 days.
  2. A is three times as efficient as B.

Step-by-Step Solution

Step 1: Define Efficiency Ratio

Let the efficiency of B be represented by $E_B$.

According to the problem, A is three times as efficient as B. So, the efficiency of A ($E_A$) is:

$$E_A = 3 \times E_B$$

We can assume a unit of efficiency for B for simplicity. Let $E_B = 1$ unit of work per day.

Then, $E_A = 3 \times 1 = 3$ units of work per day.

Step 2: Calculate Combined Efficiency

When A and B work together, their efficiencies add up. The combined efficiency ($E_{A+B}$) is:

$$E_{A+B} = E_A + E_B$$
$$E_{A+B} = 3 \text{ units/day} + 1 \text{ unit/day} = 4 \text{ units/day}$$

So, A and B together complete 4 units of work each day.

Step 3: Calculate Total Work

We know that Work = Efficiency × Time. A and B together complete the work in 18 days with a combined efficiency of 4 units/day.

The total work (W) is:

$$W = E_{A+B} \times \text{Time taken by A and B together}$$
$$W = 4 \text{ units/day} \times 18 \text{ days}$$
$$W = 72 \text{ units}$$

The total amount of work to be done is 72 units.

Step 4: Calculate Time Taken by B Alone

To find the time taken by B alone to complete the work, we use the formula:

$$\text{Time} = \frac{\text{Total Work}}{\text{Efficiency}}$$

The total work is 72 units, and B's efficiency ($E_B$) is 1 unit/day.

$$\text{Time taken by B alone} = \frac{W}{E_B}$$
$$\text{Time taken by B alone} = \frac{72 \text{ units}}{1 \text{ unit/day}}$$
$$\text{Time taken by B alone} = 72 \text{ days}$$

Therefore, B alone can complete the work in 72 days.

Verification

Let's check the result:

  • B's efficiency = 1 unit/day. Time for B alone = 72 days. Total Work = 1 × 72 = 72 units.
  • A's efficiency = 3 units/day. Time for A alone = Total Work / EA = 72 / 3 = 24 days.
  • Combined Work Rate = 1/72 (by B) + 1/24 (by A) = 1/72 + 3/72 = 4/72 = 1/18.
  • Time taken together = 1 / (Combined Work Rate) = 1 / (1/18) = 18 days.

This matches the information given in the question, confirming our calculation is correct.

Individual/Group Efficiency (units/day) Time Taken (days) Total Work (units)
B 1 72 $1 \times 72 = 72$
A 3 24 $3 \times 24 = 72$
A and B together $1 + 3 = 4$ 18 $4 \times 18 = 72$

Revision Table: Time and Work Formulas

Concept Formula Explanation
Work Done Work = Efficiency × Time Total work completed is the product of the rate of work (efficiency) and the time spent.
Efficiency Efficiency = $\frac{\text{Work}}{\text{Time}}$ Efficiency is the amount of work done per unit of time.
Time Taken Time = $\frac{\text{Work}}{\text{Efficiency}}$ The time needed to complete a task is the total work divided by the efficiency.
Combined Efficiency (A and B) $E_{A+B} = E_A + E_B$ When multiple people work together, their efficiencies are added.
Individual Time from Combined (for 2 people A & B) If A takes 'a' days and B takes 'b' days, then time together = $\frac{ab}{a+b}$ Useful for relating individual times to combined time.

Additional Information: Solving Time and Work Problems

Time and work problems are common in quantitative aptitude. Understanding the inverse relationship between efficiency and time is crucial. If a person is more efficient, they take less time to complete the same amount of work. Conversely, if someone is less efficient, they take more time.

  • Always define a unit of work or efficiency based on the given information. Assuming a variable or a simple number (like 1 or the LCM of time periods) can make calculations easier.
  • Remember that when people work together, their rates of work (efficiencies) are combined, usually by adding them.
  • The total work remains constant regardless of who does it or how many people are involved.

This problem used the efficiency approach. Another common approach involves calculating the fraction of work done per day. If B takes 'x' days, B does 1/x of the work per day. If A takes 'y' days, A does 1/y per day. Since A is 3 times as efficient as B, A takes 1/3 the time B takes, so $y = x/3$. Together they do $1/x + 1/(x/3) = 1/x + 3/x = 4/x$ of the work per day. Since they finish in 18 days, they do 1/18 of the work per day. Thus, $4/x = 1/18$, which gives $x = 4 \times 18 = 72$ days. Both methods yield the same correct answer.

Was this answer helpful?

Similar Questions

  1. X and Y can complete a work in 9 days and 36 days, respectively. X begins to do the work and they work alternately one at a time for one day each. The whole work will be complete in:

  2. P is two times as efficient as Q. P is able to complete a piece of work in 40 days less than Q. Working together, the whole number of days taken by them to complete the work is:

    (Round off to the nearest integer)

  3. 4 women or 6 boys can finish a work in the same number of days. A boy can finish it in 60 days. In how many days can 5 women finish the work, working together every day?

  4. To do a certain work, Ajay and Bharat work on alternate days, with Bharat starting the work on the first day. Ajay can finish the work alone in 32 days. If the work gets completed in exactly 8 days, then Bharat alone can finish 7 times the same work in ____________ days.

  5. A, B and C can separately complete a work in 12, 15 and 20 days, respectively. They worked together 4 days. What will be the remaining work?

  6. A, B and C, working alone, can complete a job in 16, 24 and 36 days, respectively. In how many days can they complete the job if they work together?

  7. Rakshit, Ajay, and Satish are sanitation workers in a Municipal Corporation. Rakshit alone takes 20 hours to clean a drain while Ajay takes 12 hours when working alone to do the same. All three together take only 5 hours to clean the drain. In how many hours, can Satish complete the work alone?

  8. 15 men and 25 women can complete a piece of work in 9.6 days. If 16 women can complete the same work in 27 days, find the number of days in which 16 men can complete the same work.  

  9. A,B and C can do a piece of work in 30 days, 40 days and 50 days, respectively. Beginning with A, if A, B and C do the work alternatively then in how many days will the work be finished?

  10. Ravi can do a piece of work in 40 days and Sudha can do the same piece of work in 60 days. If they work on alternative days starting with Sudha on the first day, then in how many days will the work be completed?


Important Questions from Work Efficiency

  1. A and B working together can complete a job in 30 days. The ratio of their efficiencies is 3 : 2. In how many days can the faster person complete the job?

  2. A takes 15 days to complete \(\frac{5}{7} \)  of a work. With the help of B, they finish the whole work in 12 days. In how many days, B alone will complete the same work

  3. A alone can complete a work in 14 days and B alone can complete the same work in 21 days. A and B start the work together but A leaves the work after 4 days of the starting of work. In how many days B will complete the remaining work?

  4. For completing a certain work, A is 50% less efficient than B and B is 50% more efficient than C. Working together A, B and C can complete the work in 48 days. A alone can complete the same work in:

  5. 30 persons can do a piece of work in 24 days. How many more persons are required to complete the work in 20 days?

Need Expert Advice?
Upcoming Exams
SSC JHT
September 08, 2026
SSC Stenographer
September 09, 2026
SSC Selection Post
September 16, 2026
Test Series
SSC CGL img
SSC
SSC CGL (Tier I + Tier II) 2026 Mock Test Series - Latest Pattern
2500 Tests 6 Tests Free
3990 Attempts
4.2(838)
English, Hindi

Start Your Preparation with Prepp Mobile App

Download the app from Google Play & App Store
Download the app from Google Play & App Store
Prepp Mobile App