A and B can do a work together in 18 days. A is three times as efficient as B. In how many days can B alone complete the work?
72 days
This problem involves the concept of time and work, specifically focusing on the relationship between efficiency and the time taken to complete a task. We are given the combined time taken by two individuals, A and B, to complete a work, and a relationship between their efficiencies. We need to find the time taken by one individual, B, to complete the same work alone.
We are given two main pieces of information:
Let the efficiency of B be represented by $E_B$.
According to the problem, A is three times as efficient as B. So, the efficiency of A ($E_A$) is:
We can assume a unit of efficiency for B for simplicity. Let $E_B = 1$ unit of work per day.
Then, $E_A = 3 \times 1 = 3$ units of work per day.
When A and B work together, their efficiencies add up. The combined efficiency ($E_{A+B}$) is:
So, A and B together complete 4 units of work each day.
We know that Work = Efficiency × Time. A and B together complete the work in 18 days with a combined efficiency of 4 units/day.
The total work (W) is:
The total amount of work to be done is 72 units.
To find the time taken by B alone to complete the work, we use the formula:
The total work is 72 units, and B's efficiency ($E_B$) is 1 unit/day.
Therefore, B alone can complete the work in 72 days.
Let's check the result:
This matches the information given in the question, confirming our calculation is correct.
| Individual/Group | Efficiency (units/day) | Time Taken (days) | Total Work (units) |
|---|---|---|---|
| B | 1 | 72 | $1 \times 72 = 72$ |
| A | 3 | 24 | $3 \times 24 = 72$ |
| A and B together | $1 + 3 = 4$ | 18 | $4 \times 18 = 72$ |
| Concept | Formula | Explanation |
|---|---|---|
| Work Done | Work = Efficiency × Time | Total work completed is the product of the rate of work (efficiency) and the time spent. |
| Efficiency | Efficiency = $\frac{\text{Work}}{\text{Time}}$ | Efficiency is the amount of work done per unit of time. |
| Time Taken | Time = $\frac{\text{Work}}{\text{Efficiency}}$ | The time needed to complete a task is the total work divided by the efficiency. |
| Combined Efficiency (A and B) | $E_{A+B} = E_A + E_B$ | When multiple people work together, their efficiencies are added. |
| Individual Time from Combined (for 2 people A & B) | If A takes 'a' days and B takes 'b' days, then time together = $\frac{ab}{a+b}$ | Useful for relating individual times to combined time. |
Time and work problems are common in quantitative aptitude. Understanding the inverse relationship between efficiency and time is crucial. If a person is more efficient, they take less time to complete the same amount of work. Conversely, if someone is less efficient, they take more time.
This problem used the efficiency approach. Another common approach involves calculating the fraction of work done per day. If B takes 'x' days, B does 1/x of the work per day. If A takes 'y' days, A does 1/y per day. Since A is 3 times as efficient as B, A takes 1/3 the time B takes, so $y = x/3$. Together they do $1/x + 1/(x/3) = 1/x + 3/x = 4/x$ of the work per day. Since they finish in 18 days, they do 1/18 of the work per day. Thus, $4/x = 1/18$, which gives $x = 4 \times 18 = 72$ days. Both methods yield the same correct answer.
A can complete a certain piece of work in 40 days. B is 25% more efficient than A and C is 28% more efficient than B. They work together for 5 days. The remaining work will be complete by B alone, in:
45 men or 60 boys can do a piece of work in 20 days. How many days will 15 men and 20 boys take to complete the work?
A, B and C can finish a job working alone in 20, 30 and 60 days respectively. They all work together for 1 day, then A and B quit. How many days C working alone will take to finish the remaining part of the job?
A can do a piece of work in 6 days, B can do it in 9 days. With the assistance of C they completed the work in 3 days. In how many days can C alone do the work?
A piece of work was finished by A, B and C together. A and B together finished 60% of the work and B and C together finished 70% of the work. Who among the three is most efficient?
A, B and C can individually complete a task in 24 days, 20 days and 18 days, respectively. B and C start the task, and they work for 6 days and leave. The number of days required by A alone to finish the remaining task is:
Amar can complete a work in 30 days and Raman can complete the same work in 15 days. If both of them work together, then in 4 days what percent of the total work will be completed?
The ratio of the efficiencies of A, B and C is 7 ∶ 5 ∶ 4. Working together, they can finish a work in 35 days. A and B work together for 28 days. The remaining work will be completed (in days) by C alone∶
3 men, 4 women and 6 boys together can complete a work in 6 days. A woman does triple the work a man does and a boy does half the work a man does. How many women alone will be able to complete this work in 4 days?
One contractor had undertaken a construction work. To complete the given job, he sought labour comprising 24 men for 12 days for working 10 hours a day. But due to festival season, as the labour had gone to their respective hometowns, he could get only 15 men and they too were willing to work 8 hours a day. With this much labour, in how many days would he be able to complete the same job?