All Exams Test series for 1 year @ ₹349 only
Question

A and B can do a work together in 18 days. A is three times as efficient as B. In how many days can B alone complete the work?

This question was previously asked in
SSC CGL 2019 (Tier 2) GS Finance & Economics Previous Year Paper (17-Nov-2020)
The correct answer is

72 days

Understanding the Problem: Time, Work, and Efficiency

This problem involves the concept of time and work, specifically focusing on the relationship between efficiency and the time taken to complete a task. We are given the combined time taken by two individuals, A and B, to complete a work, and a relationship between their efficiencies. We need to find the time taken by one individual, B, to complete the same work alone.

Key Concepts: Efficiency and Work

  • Efficiency: Efficiency is defined as the amount of work done per unit of time. Higher efficiency means less time is required to complete a given amount of work.
  • Work: The total amount of task to be completed. It is often considered as a fixed unit (e.g., 1 unit of work) or calculated based on efficiency and time (Work = Efficiency × Time).

Setting up the Problem

We are given two main pieces of information:

  1. A and B together can complete the work in 18 days.
  2. A is three times as efficient as B.

Step-by-Step Solution

Step 1: Define Efficiency Ratio

Let the efficiency of B be represented by $E_B$.

According to the problem, A is three times as efficient as B. So, the efficiency of A ($E_A$) is:

$$E_A = 3 \times E_B$$

We can assume a unit of efficiency for B for simplicity. Let $E_B = 1$ unit of work per day.

Then, $E_A = 3 \times 1 = 3$ units of work per day.

Step 2: Calculate Combined Efficiency

When A and B work together, their efficiencies add up. The combined efficiency ($E_{A+B}$) is:

$$E_{A+B} = E_A + E_B$$
$$E_{A+B} = 3 \text{ units/day} + 1 \text{ unit/day} = 4 \text{ units/day}$$

So, A and B together complete 4 units of work each day.

Step 3: Calculate Total Work

We know that Work = Efficiency × Time. A and B together complete the work in 18 days with a combined efficiency of 4 units/day.

The total work (W) is:

$$W = E_{A+B} \times \text{Time taken by A and B together}$$
$$W = 4 \text{ units/day} \times 18 \text{ days}$$
$$W = 72 \text{ units}$$

The total amount of work to be done is 72 units.

Step 4: Calculate Time Taken by B Alone

To find the time taken by B alone to complete the work, we use the formula:

$$\text{Time} = \frac{\text{Total Work}}{\text{Efficiency}}$$

The total work is 72 units, and B's efficiency ($E_B$) is 1 unit/day.

$$\text{Time taken by B alone} = \frac{W}{E_B}$$
$$\text{Time taken by B alone} = \frac{72 \text{ units}}{1 \text{ unit/day}}$$
$$\text{Time taken by B alone} = 72 \text{ days}$$

Therefore, B alone can complete the work in 72 days.

Verification

Let's check the result:

  • B's efficiency = 1 unit/day. Time for B alone = 72 days. Total Work = 1 × 72 = 72 units.
  • A's efficiency = 3 units/day. Time for A alone = Total Work / EA = 72 / 3 = 24 days.
  • Combined Work Rate = 1/72 (by B) + 1/24 (by A) = 1/72 + 3/72 = 4/72 = 1/18.
  • Time taken together = 1 / (Combined Work Rate) = 1 / (1/18) = 18 days.

This matches the information given in the question, confirming our calculation is correct.

Individual/Group Efficiency (units/day) Time Taken (days) Total Work (units)
B 1 72 $1 \times 72 = 72$
A 3 24 $3 \times 24 = 72$
A and B together $1 + 3 = 4$ 18 $4 \times 18 = 72$

Revision Table: Time and Work Formulas

Concept Formula Explanation
Work Done Work = Efficiency × Time Total work completed is the product of the rate of work (efficiency) and the time spent.
Efficiency Efficiency = $\frac{\text{Work}}{\text{Time}}$ Efficiency is the amount of work done per unit of time.
Time Taken Time = $\frac{\text{Work}}{\text{Efficiency}}$ The time needed to complete a task is the total work divided by the efficiency.
Combined Efficiency (A and B) $E_{A+B} = E_A + E_B$ When multiple people work together, their efficiencies are added.
Individual Time from Combined (for 2 people A & B) If A takes 'a' days and B takes 'b' days, then time together = $\frac{ab}{a+b}$ Useful for relating individual times to combined time.

Additional Information: Solving Time and Work Problems

Time and work problems are common in quantitative aptitude. Understanding the inverse relationship between efficiency and time is crucial. If a person is more efficient, they take less time to complete the same amount of work. Conversely, if someone is less efficient, they take more time.

  • Always define a unit of work or efficiency based on the given information. Assuming a variable or a simple number (like 1 or the LCM of time periods) can make calculations easier.
  • Remember that when people work together, their rates of work (efficiencies) are combined, usually by adding them.
  • The total work remains constant regardless of who does it or how many people are involved.

This problem used the efficiency approach. Another common approach involves calculating the fraction of work done per day. If B takes 'x' days, B does 1/x of the work per day. If A takes 'y' days, A does 1/y per day. Since A is 3 times as efficient as B, A takes 1/3 the time B takes, so $y = x/3$. Together they do $1/x + 1/(x/3) = 1/x + 3/x = 4/x$ of the work per day. Since they finish in 18 days, they do 1/18 of the work per day. Thus, $4/x = 1/18$, which gives $x = 4 \times 18 = 72$ days. Both methods yield the same correct answer.

Was this answer helpful?

Similar Questions

  1. Five men and 2 boys can do in 30 days as much work as 7 men and 10 boys can do in 15 days. How many boys should join 40 men to do the same work in 4 days?

  2. To do a certain work, A and B work on alternate days with B beginning the work on the first day. A alone can complete the same work in 24 days. If the work gets completed in  \(11 \frac{1}{3}\)  days, then B alone can complete  \(\rm \frac{7}{9}^{th}\)  part of the original work in:

  3. 20 women and 15 men together can complete a work in 6 days. It takes 150 days for a single woman to complete the work. In how many days can a single man complete the work?

  4. 15 men and 25 women can complete a piece of work in 9.6 days. If 16 women can complete the same work in 27 days, find the number of days in which 16 men can complete the same work.  

  5. Ram can complete a piece work in 15 days, Rohan in 25 days, and Rohit in 30 days. Rohan and Rohit worked together for 2 days and then Rohit was replaced by Ram. In how many days altogether was the work completed?

  6. R, S and T can finish a work in 20, 15 and 10 days, respectively. R works on all days and S and T work on alternate days with T starting the work on the first day. In how many days is the work finished?

  7. A can do \(1 \over 3\) of a piece of work in 32 days, B can do \(37{1 \over 2}\)% of the same work in 24 days, while C can do 60% of the same work in 48 days. B and C together started and worked for x days. After x days, B left the work and A joined C and both completed the remaining work in (x + 8) days. If the ratio of the work done by (B + C) together to the work done by (A + C) together is 9 ∶ 11, then what fraction of the same work can be completed by C alone in 3.5x days?

  8. A group of college students had decided to complete a project in 10 days. As 2 students dropped out every day, the project got completed at the end of the 15th day. The number of students at the beginning of the project was:

  9. Aarif, Arun and Abraham can do a work in 12, 20 and 24 days, respectively. They all begin together. Arun leaves the work 3 days and Abraham 6 days before its completion. In how many days is the work finished?

  10. A,B and C can do a piece of work in 30 days, 40 days and 50 days, respectively. Beginning with A, if A, B and C do the work alternatively then in how many days will the work be finished?


Important Questions from Work Efficiency

  1. Five men and 2 boys can do in 30 days as much work as 7 men and 10 boys can do in 15 days. How many boys should join 40 men to do the same work in 4 days?

  2. A man completes 7/8 of a job in 21 days. How many more days will it take him to finish the job if quantum of work further increased by 50%?

  3. 24 men and 12 women can do a piece of work in 30 days. In how many days can 12 men and 24 women do the same piece of work?

  4. A and B together can do a piece of work in 4 days, B and C can do it in 6 days, A and C can do it in 8 days. Then A, B and C together can do the same work in :-

  5. A can complete 50% of a work in 9 days and B can do 25% of the work in 9 days, if they work alone. If they work together then how much work (in percentage) can be completed in 6 days?

Need Expert Advice?
Upcoming Exams
SSC CGL
September 30, 2026
UPSSSC PET
October 23, 2026
Test Series
SSC CGL img
SSC
SSC CGL (Tier I + Tier II) 2026 Mock Test Series - Latest Pattern
2503 Tests 6 Tests Free
5322 Attempts
4.2(864)
English, Hindi

Start Your Preparation with Prepp Mobile App

Download the app from Google Play & App Store
Download the app from Google Play & App Store
Prepp Mobile App