All Exams Test series for 1 year @ ₹349 only
Question

A and B can do a work together in 18 days. A is three times as efficient as B. In how many days can B alone complete the work?

This question was previously asked in
SSC CGL 2019 (Tier 2) GS Finance & Economics Previous Year Paper (17-Nov-2020)
The correct answer is

72 days

Understanding the Problem: Time, Work, and Efficiency

This problem involves the concept of time and work, specifically focusing on the relationship between efficiency and the time taken to complete a task. We are given the combined time taken by two individuals, A and B, to complete a work, and a relationship between their efficiencies. We need to find the time taken by one individual, B, to complete the same work alone.

Key Concepts: Efficiency and Work

  • Efficiency: Efficiency is defined as the amount of work done per unit of time. Higher efficiency means less time is required to complete a given amount of work.
  • Work: The total amount of task to be completed. It is often considered as a fixed unit (e.g., 1 unit of work) or calculated based on efficiency and time (Work = Efficiency × Time).

Setting up the Problem

We are given two main pieces of information:

  1. A and B together can complete the work in 18 days.
  2. A is three times as efficient as B.

Step-by-Step Solution

Step 1: Define Efficiency Ratio

Let the efficiency of B be represented by $E_B$.

According to the problem, A is three times as efficient as B. So, the efficiency of A ($E_A$) is:

$$E_A = 3 \times E_B$$

We can assume a unit of efficiency for B for simplicity. Let $E_B = 1$ unit of work per day.

Then, $E_A = 3 \times 1 = 3$ units of work per day.

Step 2: Calculate Combined Efficiency

When A and B work together, their efficiencies add up. The combined efficiency ($E_{A+B}$) is:

$$E_{A+B} = E_A + E_B$$
$$E_{A+B} = 3 \text{ units/day} + 1 \text{ unit/day} = 4 \text{ units/day}$$

So, A and B together complete 4 units of work each day.

Step 3: Calculate Total Work

We know that Work = Efficiency × Time. A and B together complete the work in 18 days with a combined efficiency of 4 units/day.

The total work (W) is:

$$W = E_{A+B} \times \text{Time taken by A and B together}$$
$$W = 4 \text{ units/day} \times 18 \text{ days}$$
$$W = 72 \text{ units}$$

The total amount of work to be done is 72 units.

Step 4: Calculate Time Taken by B Alone

To find the time taken by B alone to complete the work, we use the formula:

$$\text{Time} = \frac{\text{Total Work}}{\text{Efficiency}}$$

The total work is 72 units, and B's efficiency ($E_B$) is 1 unit/day.

$$\text{Time taken by B alone} = \frac{W}{E_B}$$
$$\text{Time taken by B alone} = \frac{72 \text{ units}}{1 \text{ unit/day}}$$
$$\text{Time taken by B alone} = 72 \text{ days}$$

Therefore, B alone can complete the work in 72 days.

Verification

Let's check the result:

  • B's efficiency = 1 unit/day. Time for B alone = 72 days. Total Work = 1 × 72 = 72 units.
  • A's efficiency = 3 units/day. Time for A alone = Total Work / EA = 72 / 3 = 24 days.
  • Combined Work Rate = 1/72 (by B) + 1/24 (by A) = 1/72 + 3/72 = 4/72 = 1/18.
  • Time taken together = 1 / (Combined Work Rate) = 1 / (1/18) = 18 days.

This matches the information given in the question, confirming our calculation is correct.

Individual/Group Efficiency (units/day) Time Taken (days) Total Work (units)
B 1 72 $1 \times 72 = 72$
A 3 24 $3 \times 24 = 72$
A and B together $1 + 3 = 4$ 18 $4 \times 18 = 72$

Revision Table: Time and Work Formulas

Concept Formula Explanation
Work Done Work = Efficiency × Time Total work completed is the product of the rate of work (efficiency) and the time spent.
Efficiency Efficiency = $\frac{\text{Work}}{\text{Time}}$ Efficiency is the amount of work done per unit of time.
Time Taken Time = $\frac{\text{Work}}{\text{Efficiency}}$ The time needed to complete a task is the total work divided by the efficiency.
Combined Efficiency (A and B) $E_{A+B} = E_A + E_B$ When multiple people work together, their efficiencies are added.
Individual Time from Combined (for 2 people A & B) If A takes 'a' days and B takes 'b' days, then time together = $\frac{ab}{a+b}$ Useful for relating individual times to combined time.

Additional Information: Solving Time and Work Problems

Time and work problems are common in quantitative aptitude. Understanding the inverse relationship between efficiency and time is crucial. If a person is more efficient, they take less time to complete the same amount of work. Conversely, if someone is less efficient, they take more time.

  • Always define a unit of work or efficiency based on the given information. Assuming a variable or a simple number (like 1 or the LCM of time periods) can make calculations easier.
  • Remember that when people work together, their rates of work (efficiencies) are combined, usually by adding them.
  • The total work remains constant regardless of who does it or how many people are involved.

This problem used the efficiency approach. Another common approach involves calculating the fraction of work done per day. If B takes 'x' days, B does 1/x of the work per day. If A takes 'y' days, A does 1/y per day. Since A is 3 times as efficient as B, A takes 1/3 the time B takes, so $y = x/3$. Together they do $1/x + 1/(x/3) = 1/x + 3/x = 4/x$ of the work per day. Since they finish in 18 days, they do 1/18 of the work per day. Thus, $4/x = 1/18$, which gives $x = 4 \times 18 = 72$ days. Both methods yield the same correct answer.

Was this answer helpful?

Similar Questions

  1. A and Btogether can do a piece of work in 12 days. Aalone can do it in 18 days. In how many days can Balone can do the work?
  2. A can complete a certain piece of work in 40 days. B is 25% more efficient than A and C is 28% more efficient than B. They work together for 5 days. The remaining work will be complete by B alone, in:

  3. 45 men or 60 boys can do a piece of work in 20 days. How many days will 15 men and 20 boys take to complete the work?

  4. A, B and C can finish a job working alone in 20, 30 and 60 days respectively. They all work together for 1 day, then A and B quit. How many days C working alone will take to finish the remaining part of the job?

  5. A can do a piece of work in 6 days, B can do it in 9 days. With the assistance of C they completed the work in 3 days. In how many days can C alone do the work?

  6. A piece of work was finished by A, B and C together. A and B together finished 60% of the work and B and C together finished 70% of the work. Who among the three is most efficient?

  7. A, B and C can individually complete a task in 24 days, 20 days and 18 days, respectively. B and C start the task, and they work for 6 days and leave. The number of days required by A alone to finish the remaining task is:

  8. Amar can complete a work in 30 days and Raman can complete the same work in 15 days. If both of them work together, then in 4 days what percent of the total work will be completed?

  9. The ratio of the efficiencies of A, B and C is 7 ∶ 5 ∶ 4. Working together, they can finish a work in 35 days. A and B work together for 28 days. The remaining work will be completed (in days) by C alone∶

  10. 3 men, 4 women and 6 boys together can complete a work in 6 days. A woman does triple the work a man does and a boy does half the work a man does. How many women alone will be able to complete this work in 4 days?


Important Questions from Work Efficiency

  1. M is thrice as efficient as workman as N and therefore is able to finish a job in 264 days less than N. Then in how many days can N finish the entire work?
  2. A can do a piece of work in $1455$ days. B is $25\%$ more efficient than A. Find the number of days taken by B to do the same piece of work.
  3. 45 people take 18 days to dig a pond. If the pond would have to be dug in 15 days, then the number of people to be employed will be
  4. A stock of food is enough for 240 men for 48 days. How long will the same stock last for 160 men?
  5. One contractor had undertaken a construction work. To complete the given job, he sought labour comprising 24 men for 12 days for working 10 hours a day. But due to festival season, as the labour had gone to their respective hometowns, he could get only 15 men and they too were willing to work 8 hours a day. With this much labour, in how many days would he be able to complete the same job?

Need Expert Advice?
Upcoming Exams
SSC CPO
November 23, 2026
SSC CHSL
November 30, 2026
SSC JE
November 30, 2026
Test Series
SSC CGL img
SSC
SSC CGL (Tier I + Tier II) 2026 Mock Test Series - Latest Pattern
2509 Tests 6 Tests Free
9134 Attempts
4.2(952)
English, Hindi
More Questions from SSC CGL

Start Your Preparation with Prepp Mobile App

Download the app from Google Play & App Store
Download the app from Google Play & App Store
Prepp Mobile App