40 persons begin to work together on a job. But after some days 10 persons left the work. As a result, the job which should have been completed in 50 days is completed in 60 days. How many days after the commencement of the work did the 10 persons leave?
20
Total work \(= 40 \times 50 = 2000\) person-days.
Let the 10 persons leave after \(x\) days. For the first \(x\) days all 40 persons work, and for the remaining \(60 - x\) days only \(40 - 10 = 30\) persons work.
So the work done is \(40x + 30(60 - x) = 2000\).
Expand: \(40x + 1800 - 30x = 2000\), which gives \(10x = 200\).
Therefore \(x = 20\).
Hence, the 10 persons left 20 days after the commencement of the work.
Mohan can do a piece of work in 10 days and Sohan in 15 days. They started working together, but after 3 days Mohan left the work . What time will Sohan take to finish the work?
A tank is filled in 8 hours by three taps A, B and C. The tap C is thrice as fast as B and B is twice as fast as A. How much time will pipe B alone take to fill the tank?
Had been one menless, then the number of days required to do a piece of work would have been one more. If the number of Man. Days required to complete the work is 56, how many workers were there?
A can do a piece of work in 16 hours, B and C can do it in 8 hours while A and C can do it 12 hours. How long will B alone take to do it?