14 persons can construct a wall in 12 days. In how many days can another group of 7 persons, each being only one-fourth as skilled compared to the persons in the first group, complete the construction work of this wall?
96 days
96 days is correct.
Total work = \(14 \times 12 = 168\) person-days of the first group.
Each person of the second group does one-fourth of that work per day, so 7 of them equal \(7 \times \dfrac{1}{4} = \dfrac{7}{4}\) persons of the first group.
Days needed = \(168 \div \dfrac{7}{4} = 168 \times \dfrac{4}{7} = 96\).
So the second group completes the wall in 96 days.
Manoj is twice as efficient a fisherman as Anuraj, and together they complete a piece of work in 22 days. In how many days can Anuraj alone complete the same work?
A man completes 7/8 of a job in 21 days. How many more days will it take him to finish the job if quantum of work further increased by 50%?
24 men and 12 women can do a piece of work in 30 days. In how many days can 12 men and 24 women do the same piece of work?
A and B together can do a piece of work in 4 days, B and C can do it in 6 days, A and C can do it in 8 days. Then A, B and C together can do the same work in :-
A can complete 50% of a work in 9 days and B can do 25% of the work in 9 days, if they work alone. If they work together then how much work (in percentage) can be completed in 6 days?
A is thrice as good a workman as B. C alone takes 48 days to paint a house. All three A, B and C working together take 16 days to paint the house. It will take how many days for A alone to paint the house?