All Exams Test series for 1 year @ ₹349 only
Question

John is only 40% as efficient as Jesse. If John alone can do a piece of work in 35 days, how many days will it take the duo to complete the work, if they work together?

This question was previously asked in
RRB NTPC 2019 CBT 1 Question Paper PDF (31-Jan-2021) (Shift 1)
The correct answer is
10 days

Duo Work Time Calculation: John & Jesse Efficiency

This problem involves calculating the time required for two individuals, John and Jesse, to complete a task together, considering their differing efficiencies.

John's efficiency is given as 40% of Jesse's efficiency. Let $E_J$ represent John's efficiency and $E_{Je}$ represent Jesse's efficiency.

The relationship is mathematically expressed as: $E_J = 0.40 \times E_{Je}$

Calculate Total Work and Individual Efficiencies

To solve this efficiently, we can assign unit values to their efficiencies:

  • Assume Jesse's efficiency $E_{Je} = 100$ units.
  • Consequently, John's efficiency $E_J = 0.40 \times 100 = 40$ units.
  • We know John completes the entire work alone in 35 days.
  • The total amount of work can be calculated using the formula: Total Work = Efficiency $\times$ Time.
  • Calculating the total work: $ \text{Total Work} = E_J \times \text{Time}_J = 40 \text{ units} \times 35 \text{ days} = 1400 \text{ units} $.

Determine Combined Efficiency and Time Taken Together

When John and Jesse work together, their individual efficiencies add up to give a combined efficiency.

  • Combined Efficiency $E_{J+Je} = E_J + E_{Je}$.
  • $E_{J+Je} = 40 \text{ units} + 100 \text{ units} = 140 \text{ units}$.
  • The time needed for them to complete the work together is found by dividing the total work by their combined efficiency: $ \text{Time Together} = \frac{\text{Total Work}}{E_{J+Je}} $.
  • Substituting the values: $ \text{Time Together} = \frac{1400 \text{ units}}{140 \text{ units/day}} = 10 \text{ days} $.

Thus, the duo will take 10 days to complete the work when collaborating.

Was this answer helpful?

Similar Questions

  1. A can do $\frac{1}{5}^{\text{th}}$ of some work in 12 days, B can do $20\%$ of the same work in 10 days, C can do $\frac{1}{6}^{\text{th}}$ of the work in 8 days and D can do $\frac{1}{5}^{\text{th}}$ of the work in 12 days. Who will complete the work first if all four started to work at the same time?
  2. A can do a certain work in 45 days. B is 50% more efficient than A, and C is 3 times as fast as A. They started the work together but C left 7 days before completion of the work. In how many days was the entire work completed?
  3. Manoj is twice as efficient a fisherman as Anuraj, and together they complete a piece of work in 22 days. In how many days can Anuraj alone complete the same work?

  4. Five women can do a work in thirty six days. If the ratio between the capacity of a man and a woman is 3:1, then find how many days it will take 5 men to complete the same work?
  5. If 15 persons can do a job in 30 days, then 30 persons with twice the efficiency can do the same job in how many days?
  6. Raju is thrice as good as a workman as Vinod and together they can finish a task in 21 days. In how many days can Vinod alone complete the work?
  7. If Raju is thrice as good workman as Ravi and takes 20 days less than him to complete a piece of work, then find the time taken by Ravi to complete the work.
  8. Kamal can complete a work in 14 days. Vimal is 40% more efficient than Kamal. The number of days Vimal will take to complete the same piece of work is:
  9. Raj is 60% more efficient than Sundar and Sundar can finish a certain task in 16 days. How many days will Raj alone take to complete the same task?
  10. 21 women can complete a task in 40 days. 30 men can complete the task in 21 days. What is the ratio of the number of days a man will take to complete the task alone to the number of days a woman will need to do that task?

Important Questions from Work Efficiency

  1. A man completes 7/8 of a job in 21 days. How many more days will it take him to finish the job if quantum of work further increased by 50%?

  2. 24 men and 12 women can do a piece of work in 30 days. In how many days can 12 men and 24 women do the same piece of work?

  3. A and B together can do a piece of work in 4 days, B and C can do it in 6 days, A and C can do it in 8 days. Then A, B and C together can do the same work in :-

  4. A can complete 50% of a work in 9 days and B can do 25% of the work in 9 days, if they work alone. If they work together then how much work (in percentage) can be completed in 6 days?

  5. A is thrice as good a workman as B. C alone takes 48 days to paint a house. All three A, B and C working together take 16 days to paint the house. It will take how many days for A alone to paint the house?

Need Expert Advice?
Upcoming Exams
RRB JE
November 02, 2026
RRB ALP
November 03, 2026
Test Series
RRB NTPC img
Railways
RRB NTPC Under Graduate 2026 New Mock Test Series
1612 Tests 1 Tests Free
1009 Attempts
4.3(515)
English, Hindi, Telugu +7 More
More Questions from RRB NTPC

Start Your Preparation with Prepp Mobile App

Download the app from Google Play & App Store
Download the app from Google Play & App Store
Prepp Mobile App