This problem requires calculating the total time to complete a task considering different work efficiencies and a condition where one person leaves before the task finishes.
The approach involves determining individual work rates, calculating total work, and then analyzing the work done during different phases.
Let's define the work rate of person A. We'll assume A's work rate is 1 unit per day.
A completes the work in 45 days. The total amount of work ($W$) can be calculated as:
$W = R_A \times 45 \text{ days} = 1 \text{ unit/day} \times 45 \text{ days} = 45 \text{ units}$
When A, B, and C work together, their combined work rate ($R_{ABC}$) is:
$R_{ABC} = R_A + R_B + R_C = 1 + 1.5 + 3 = 5.5 \text{ units/day}$
When only A and B work together, their combined work rate ($R_{AB}$) is:
$R_{AB} = R_A + R_B = 1 + 1.5 = 2.5 \text{ units/day}$
C left 7 days before the work was completed. This implies that A and B worked together for the final 7 days.
Calculate the work done by A and B during these last 7 days ($W_{last7}$):
$W_{last7} = R_{AB} \times 7 \text{ days} = 2.5 \text{ units/day} \times 7 \text{ days} = 17.5 \text{ units}$
The work done by all three (A, B, and C) before C left ($W_{ABC}$) is the total work minus the work done in the last 7 days:
$W_{ABC} = W - W_{last7} = 45 \text{ units} - 17.5 \text{ units} = 27.5 \text{ units}$
The number of days A, B, and C worked together ($Days_{ABC}$) is found by dividing the work they did together by their combined rate:
$Days_{ABC} = \frac{W_{ABC}}{R_{ABC}} = \frac{27.5 \text{ units}}{5.5 \text{ units/day}} = 5 \text{ days}$
The total time taken to complete the entire work is the sum of the days A, B, and C worked together and the final 7 days when only A and B worked.
Total Days = Days A, B, C worked + Days A, B worked alone
Total Days = 5 days + 7 days = 12 days
Therefore, the entire work was completed in 12 days.
Manoj is twice as efficient a fisherman as Anuraj, and together they complete a piece of work in 22 days. In how many days can Anuraj alone complete the same work?
Sumi can complete a job working 5 hours per day in 2 days. If she doubles her working hours per day, then in how many days will she complete the work?
Five men and 2 boys can do in 30 days as much work as 7 men and 10 boys can do in 15 days. How many boys should join 40 men to do the same work in 4 days?
A man completes 7/8 of a job in 21 days. How many more days will it take him to finish the job if quantum of work further increased by 50%?
24 men and 12 women can do a piece of work in 30 days. In how many days can 12 men and 24 women do the same piece of work?
3 men working 7 hours a day can complete a piece of work in 45 days. In how many days will 9 men working 6 hours a day complete the same work?