The question asks to determine which individual among A, B, C, and D will complete a given piece of work first, assuming they start simultaneously. To find this, we need to calculate the total time each person requires to finish the entire work.
We are given the fraction of work each person completes in a specific number of days. We can use this information to find the time needed for each to complete 1 whole unit of work.
Completes $\frac{1}{5}$ of the work in 12 days.
Time for A to complete the whole work = $12 \times 5 = 60$ days.
Completes $20\%$ of the work in 10 days. Since $20\% = \frac{20}{100} = \frac{1}{5}$, B completes $\frac{1}{5}$ of the work in 10 days.
Time for B to complete the whole work = $10 \times 5 = 50$ days.
Completes $\frac{1}{6}$ of the work in 8 days.
Time for C to complete the whole work = $8 \times 6 = 48$ days.
Completes $\frac{1}{5}$ of the work in 12 days.
Time for D to complete the whole work = $12 \times 5 = 60$ days.
Now, let's compare the total time each person needs to complete the work:
The individual who requires the minimum time to complete the work will finish first. Comparing the times, C requires the least time (48 days).
Therefore, C will complete the work first if all four started to work at the same time.
Manoj is twice as efficient a fisherman as Anuraj, and together they complete a piece of work in 22 days. In how many days can Anuraj alone complete the same work?
A man completes 7/8 of a job in 21 days. How many more days will it take him to finish the job if quantum of work further increased by 50%?
24 men and 12 women can do a piece of work in 30 days. In how many days can 12 men and 24 women do the same piece of work?
A and B together can do a piece of work in 4 days, B and C can do it in 6 days, A and C can do it in 8 days. Then A, B and C together can do the same work in :-
A can complete 50% of a work in 9 days and B can do 25% of the work in 9 days, if they work alone. If they work together then how much work (in percentage) can be completed in 6 days?
A is thrice as good a workman as B. C alone takes 48 days to paint a house. All three A, B and C working together take 16 days to paint the house. It will take how many days for A alone to paint the house?