The question asks to determine which individual among A, B, C, and D will complete a given piece of work first, assuming they start simultaneously. To find this, we need to calculate the total time each person requires to finish the entire work.
We are given the fraction of work each person completes in a specific number of days. We can use this information to find the time needed for each to complete 1 whole unit of work.
Completes $\frac{1}{5}$ of the work in 12 days.
Time for A to complete the whole work = $12 \times 5 = 60$ days.
Completes $20\%$ of the work in 10 days. Since $20\% = \frac{20}{100} = \frac{1}{5}$, B completes $\frac{1}{5}$ of the work in 10 days.
Time for B to complete the whole work = $10 \times 5 = 50$ days.
Completes $\frac{1}{6}$ of the work in 8 days.
Time for C to complete the whole work = $8 \times 6 = 48$ days.
Completes $\frac{1}{5}$ of the work in 12 days.
Time for D to complete the whole work = $12 \times 5 = 60$ days.
Now, let's compare the total time each person needs to complete the work:
The individual who requires the minimum time to complete the work will finish first. Comparing the times, C requires the least time (48 days).
Therefore, C will complete the work first if all four started to work at the same time.
Manoj is twice as efficient a fisherman as Anuraj, and together they complete a piece of work in 22 days. In how many days can Anuraj alone complete the same work?
A and B together can complete a certain work in 20 days whereas B and C together can complete it in 24 days. If A is twice as good a workman as C, then in what time will B alone do 40% of the same work?
14 men can complete a work in 15 days. If 21 men are employed, then in how many days will they complete the same work?
A can do a certain work in 15 days, while B can do the same work in 21 days. If they work together, then in how many days will the same work be completed?
To do a certain work, A and B work on alternate days with B beginning the work on the first day. A alone can complete the same work in 24 days. If the work gets completed in \(11 \frac{1}{3}\) days, then B alone can complete \(\rm \frac{7}{9}^{th}\) part of the original work in:
Two men and 7 women can complete a work in 28 days whereas 6 men and 16 women can do the same work in 11 days. In how many days can 7 men complete the same work?