This example demonstrates how to calculate the number of days needed to complete a job when factors like the number of people and their efficiency change.
The fundamental relationship in work problems is:
Work = Number of Persons $\times$ Number of Days $\times$ Efficiency
Let $W$ represent the total work, $P$ the number of persons, $D$ the number of days, and $E$ the efficiency. The total work ($W$) required for a specific job is constant.
Given information for the first case:
The total work ($W$) can be calculated as:
$W = P_1 \times D_1 \times E_1 = 15 \times 30 \times E_1 = 450 E_1$
Information for the second case:
Using the same work formula for the second scenario:
$W = P_2 \times D_2 \times E_2 = 30 \times D_2 \times (2 E_1) = 60 D_2 E_1$
Since the total work ($W$) is constant, we equate the work done in both scenarios:
$450 E_1 = 60 D_2 E_1$
Divide both sides by $E_1$ (assuming $E_1 \neq 0$):
$450 = 60 D_2$
Solve for $D_2$:
$D_2 = \frac{450}{60}$
$D_2 = \frac{45}{6}$
$D_2 = 7.5$
Thus, the job can be completed in 7.5 days.
Manoj is twice as efficient a fisherman as Anuraj, and together they complete a piece of work in 22 days. In how many days can Anuraj alone complete the same work?
Sumi can complete a job working 5 hours per day in 2 days. If she doubles her working hours per day, then in how many days will she complete the work?
Five men and 2 boys can do in 30 days as much work as 7 men and 10 boys can do in 15 days. How many boys should join 40 men to do the same work in 4 days?
A man completes 7/8 of a job in 21 days. How many more days will it take him to finish the job if quantum of work further increased by 50%?
24 men and 12 women can do a piece of work in 30 days. In how many days can 12 men and 24 women do the same piece of work?
3 men working 7 hours a day can complete a piece of work in 45 days. In how many days will 9 men working 6 hours a day complete the same work?