This example demonstrates how to calculate the number of days needed to complete a job when factors like the number of people and their efficiency change.
The fundamental relationship in work problems is:
Work = Number of Persons $\times$ Number of Days $\times$ Efficiency
Let $W$ represent the total work, $P$ the number of persons, $D$ the number of days, and $E$ the efficiency. The total work ($W$) required for a specific job is constant.
Given information for the first case:
The total work ($W$) can be calculated as:
$W = P_1 \times D_1 \times E_1 = 15 \times 30 \times E_1 = 450 E_1$
Information for the second case:
Using the same work formula for the second scenario:
$W = P_2 \times D_2 \times E_2 = 30 \times D_2 \times (2 E_1) = 60 D_2 E_1$
Since the total work ($W$) is constant, we equate the work done in both scenarios:
$450 E_1 = 60 D_2 E_1$
Divide both sides by $E_1$ (assuming $E_1 \neq 0$):
$450 = 60 D_2$
Solve for $D_2$:
$D_2 = \frac{450}{60}$
$D_2 = \frac{45}{6}$
$D_2 = 7.5$
Thus, the job can be completed in 7.5 days.
Manoj is twice as efficient a fisherman as Anuraj, and together they complete a piece of work in 22 days. In how many days can Anuraj alone complete the same work?
A and B together can complete a certain work in 20 days whereas B and C together can complete it in 24 days. If A is twice as good a workman as C, then in what time will B alone do 40% of the same work?
14 men can complete a work in 15 days. If 21 men are employed, then in how many days will they complete the same work?
A can do a certain work in 15 days, while B can do the same work in 21 days. If they work together, then in how many days will the same work be completed?
To do a certain work, A and B work on alternate days with B beginning the work on the first day. A alone can complete the same work in 24 days. If the work gets completed in \(11 \frac{1}{3}\) days, then B alone can complete \(\rm \frac{7}{9}^{th}\) part of the original work in:
Two men and 7 women can complete a work in 28 days whereas 6 men and 16 women can do the same work in 11 days. In how many days can 7 men complete the same work?