This example demonstrates how to calculate the number of days needed to complete a job when factors like the number of people and their efficiency change.
The fundamental relationship in work problems is:
Work = Number of Persons $\times$ Number of Days $\times$ Efficiency
Let $W$ represent the total work, $P$ the number of persons, $D$ the number of days, and $E$ the efficiency. The total work ($W$) required for a specific job is constant.
Given information for the first case:
The total work ($W$) can be calculated as:
$W = P_1 \times D_1 \times E_1 = 15 \times 30 \times E_1 = 450 E_1$
Information for the second case:
Using the same work formula for the second scenario:
$W = P_2 \times D_2 \times E_2 = 30 \times D_2 \times (2 E_1) = 60 D_2 E_1$
Since the total work ($W$) is constant, we equate the work done in both scenarios:
$450 E_1 = 60 D_2 E_1$
Divide both sides by $E_1$ (assuming $E_1 \neq 0$):
$450 = 60 D_2$
Solve for $D_2$:
$D_2 = \frac{450}{60}$
$D_2 = \frac{45}{6}$
$D_2 = 7.5$
Thus, the job can be completed in 7.5 days.
Manoj is twice as efficient a fisherman as Anuraj, and together they complete a piece of work in 22 days. In how many days can Anuraj alone complete the same work?
A man completes 7/8 of a job in 21 days. How many more days will it take him to finish the job if quantum of work further increased by 50%?
24 men and 12 women can do a piece of work in 30 days. In how many days can 12 men and 24 women do the same piece of work?
A and B together can do a piece of work in 4 days, B and C can do it in 6 days, A and C can do it in 8 days. Then A, B and C together can do the same work in :-
A can complete 50% of a work in 9 days and B can do 25% of the work in 9 days, if they work alone. If they work together then how much work (in percentage) can be completed in 6 days?
A is thrice as good a workman as B. C alone takes 48 days to paint a house. All three A, B and C working together take 16 days to paint the house. It will take how many days for A alone to paint the house?