The problem involves calculating the time required for a group of men to complete a work, given information about women completing the same work and the relative work capacities of men and women.
First, determine the total amount of work. The total work is the product of the number of workers, their individual rate, and the time taken.
Given: 5 women can do the work in 36 days.
Let $R_w$ represent the work rate of one woman.
Total Work = (Number of Women) $\times$ (Days) $\times$ (Rate of one Woman)
Total Work $= 5 \times 36 \times R_w = 180 R_w$ units of work.
The ratio between the capacity (work rate) of a man ($R_m$) and a woman ($R_w$) is given as 3:1.
This means $\frac{R_m}{R_w} = \frac{3}{1}$, which implies $R_m = 3 R_w$. A man works three times as fast as a woman.
Now, calculate the time it takes for 5 men to complete the same total work.
Let $D$ be the number of days it takes for 5 men to complete the work.
Total Work = (Number of Men) $\times$ (Days) $\times$ (Rate of one Man)
Using the total work calculated earlier:
$180 R_w = 5 \times D \times R_m$
Substitute the relationship $R_m = 3 R_w$ into the equation:
$180 R_w = 5 \times D \times (3 R_w)$
$180 R_w = 15 D R_w$
To find $D$, divide both sides by $15 R_w$ (assuming $R_w \neq 0$):
$D = \frac{180}{15}$
$D = 12$
Therefore, it will take 5 men 12 days to complete the same work.
Manoj is twice as efficient a fisherman as Anuraj, and together they complete a piece of work in 22 days. In how many days can Anuraj alone complete the same work?
A man completes 7/8 of a job in 21 days. How many more days will it take him to finish the job if quantum of work further increased by 50%?
24 men and 12 women can do a piece of work in 30 days. In how many days can 12 men and 24 women do the same piece of work?
A and B together can do a piece of work in 4 days, B and C can do it in 6 days, A and C can do it in 8 days. Then A, B and C together can do the same work in :-
A can complete 50% of a work in 9 days and B can do 25% of the work in 9 days, if they work alone. If they work together then how much work (in percentage) can be completed in 6 days?
A is thrice as good a workman as B. C alone takes 48 days to paint a house. All three A, B and C working together take 16 days to paint the house. It will take how many days for A alone to paint the house?