Pratima and Diksha can complete a typing work separately in 10 hours and 15 hours, respectively. After typing for 4 hours alone, Pratima leaves the work. In how many hours will Diksha complete the remaining typing work?
9
This problem involves understanding work and time concepts. We are given the time it takes two individuals, Pratima and Diksha, to complete a typing work separately. We need to calculate how long Diksha takes to finish the remaining work after Pratima has worked alone for a specific duration.
The work rate is the amount of work done per unit of time. If someone can complete a work in 'T' hours, their work rate is 1/T of the work per hour.
Pratima works alone for 4 hours. To find the amount of work she completes, we multiply her work rate by the time she worked:
Work done by Pratima = Pratima's rate $\times$ Time worked
Work done by Pratima = $\frac{1}{10} \times 4 = \frac{4}{10} = \frac{2}{5}$ of the typing work.
So, Pratima completed $\frac{2}{5}$ of the total typing work before leaving.
The total work is considered as 1 unit. After Pratima leaves, the remaining work is:
Remaining work = Total work - Work done by Pratima
Remaining work = $1 - \frac{2}{5} = \frac{5}{5} - \frac{2}{5} = \frac{3}{5}$ of the typing work.
Thus, $\frac{3}{5}$ of the typing work still needs to be completed.
Diksha will complete the remaining $\frac{3}{5}$ of the work at her own work rate, which is $\frac{1}{15}$ of the work per hour. The time taken by Diksha is the remaining work divided by Diksha's rate:
Time taken by Diksha = $\frac{\text{Remaining Work}}{\text{Diksha's Rate}}$
Time taken by Diksha = $\frac{\frac{3}{5}}{\frac{1}{15}}$
To divide by a fraction, we multiply by its reciprocal:
Time taken by Diksha = $\frac{3}{5} \times \frac{15}{1}$
Time taken by Diksha = $\frac{3 \times 15}{5 \times 1} = \frac{45}{5} = 9$ hours.
Therefore, Diksha will take 9 hours to complete the remaining typing work.
| Person | Time to Complete (hours) | Work Rate (work/hour) |
|---|---|---|
| Pratima | 10 | $\frac{1}{10}$ |
| Diksha | 15 | $\frac{1}{15}$ |
| Step | Calculation | Result |
|---|---|---|
| Work done by Pratima in 4 hours | $\frac{1}{10} \times 4$ | $\frac{2}{5}$ of the work |
| Remaining Work | $1 - \frac{2}{5}$ | $\frac{3}{5}$ of the work |
| Time taken by Diksha for remaining work | $\frac{3/5}{1/15} = \frac{3}{5} \times 15$ | 9 hours |
The remaining typing work will be completed by Diksha in 9 hours.
| Concept | Explanation |
|---|---|
| Work Rate | The fraction of work done per unit of time. If time taken is T, rate is $1/T$. |
| Work Done | Work Rate $\times$ Time Worked. |
| Total Work | Usually considered as 1 unit. |
| Remaining Work | Total Work - Work Done. |
| Time to Complete Remaining Work | Remaining Work / Person's Work Rate. |
Work and time problems are common in quantitative aptitude. They are based on the principle that the amount of work done is directly proportional to the time taken and the rate at which the work is done. A higher work rate means less time is needed to complete the same amount of work.
Key points to remember:
These problems often involve scenarios where individuals work alone for a time, leave, or join others, requiring calculation of work done in parts and the time taken for the remaining work.
Five men and 2 boys can do in 30 days as much work as 7 men and 10 boys can do in 15 days. How many boys should join 40 men to do the same work in 4 days?
To do a certain work, A and B work on alternate days with B beginning the work on the first day. A alone can complete the same work in 24 days. If the work gets completed in \(11 \frac{1}{3}\) days, then B alone can complete \(\rm \frac{7}{9}^{th}\) part of the original work in:
R, S and T can finish a work in 20, 15 and 10 days, respectively. R works on all days and S and T work on alternate days with T starting the work on the first day. In how many days is the work finished?
A can do \(1 \over 3\) of a piece of work in 32 days, B can do \(37{1 \over 2}\)% of the same work in 24 days, while C can do 60% of the same work in 48 days. B and C together started and worked for x days. After x days, B left the work and A joined C and both completed the remaining work in (x + 8) days. If the ratio of the work done by (B + C) together to the work done by (A + C) together is 9 ∶ 11, then what fraction of the same work can be completed by C alone in 3.5x days?
A group of college students had decided to complete a project in 10 days. As 2 students dropped out every day, the project got completed at the end of the 15th day. The number of students at the beginning of the project was:
A,B and C can do a piece of work in 30 days, 40 days and 50 days, respectively. Beginning with A, if A, B and C do the work alternatively then in how many days will the work be finished?
15 men can complete a work in 25 days, and 25 women can complete the same work in 40 days. If all 15 men and 25 women work together, in how many days will the work get completed?
Working 5 hours a day, A can complete a task in 8 days and working 6 hours a day, B can finish the same task in 10 days, working 8 hours a day, they can jointly complete the task in __________.
A can do 20% of a job in 7 days and B can do 25% of the job in 7 days if they worked alone. How much of the job (in percentage) can they complete in 7 days if they worked together?
A can complete a work in 18 days, while B can complete it in 12 days. B worked on it for 4 days. How long will A take to finish the remaining work?
Five men and 2 boys can do in 30 days as much work as 7 men and 10 boys can do in 15 days. How many boys should join 40 men to do the same work in 4 days?
A man completes 7/8 of a job in 21 days. How many more days will it take him to finish the job if quantum of work further increased by 50%?
24 men and 12 women can do a piece of work in 30 days. In how many days can 12 men and 24 women do the same piece of work?
A and B together can do a piece of work in 4 days, B and C can do it in 6 days, A and C can do it in 8 days. Then A, B and C together can do the same work in :-
A can complete 50% of a work in 9 days and B can do 25% of the work in 9 days, if they work alone. If they work together then how much work (in percentage) can be completed in 6 days?