A and B can do a piece of work in 12 days and 39 days, respectively. Both work for 4 days and then A leaves. How long (in days) will B take to complete the remaining work?
22
A's one-day work \(= \frac{1}{12}\) and B's one-day work \(= \frac{1}{39}\).
Combined one-day work \(= \frac{1}{12} + \frac{1}{39} = \frac{13 + 4}{156} = \frac{17}{156}\).
Work done together in 4 days \(= 4 \times \frac{17}{156} = \frac{68}{156} = \frac{17}{39}\).
Remaining work \(= 1 - \frac{17}{39} = \frac{22}{39}\).
Time for B alone \(= \frac{22}{39} \div \frac{1}{39} = \frac{22}{39} \times 39 = 22\) days.
Hence, B takes 22 days to finish the remaining work.
Mohan can do a piece of work in 10 days and Sohan in 15 days. They started working together, but after 3 days Mohan left the work . What time will Sohan take to finish the work?
A tank is filled in 8 hours by three taps A, B and C. The tap C is thrice as fast as B and B is twice as fast as A. How much time will pipe B alone take to fill the tank?
Had been one menless, then the number of days required to do a piece of work would have been one more. If the number of Man. Days required to complete the work is 56, how many workers were there?
A can do a piece of work in 16 hours, B and C can do it in 8 hours while A and C can do it 12 hours. How long will B alone take to do it?