A and B can do a piece of work in 12 days and 36 days, respectively. Both work for 4 days and then A leaves. How long (in days) will B take to complete the remaining work?
20
A's one-day work is \(\dfrac{1}{12}\) and B's one-day work is \(\dfrac{1}{36}\).
Their combined one-day work is \(\dfrac{1}{12} + \dfrac{1}{36} = \dfrac{3 + 1}{36} = \dfrac{4}{36} = \dfrac{1}{9}\).
In 4 days together they complete \(4 \times \dfrac{1}{9} = \dfrac{4}{9}\) of the work.
The remaining work is \(1 - \dfrac{4}{9} = \dfrac{5}{9}\).
B alone completes this in \(\dfrac{5}{9} \div \dfrac{1}{36} = \dfrac{5}{9} \times 36 = 20\) days.
Hence, B takes 20 days to complete the remaining work.
Mohan can do a piece of work in 10 days and Sohan in 15 days. They started working together, but after 3 days Mohan left the work . What time will Sohan take to finish the work?
A tank is filled in 8 hours by three taps A, B and C. The tap C is thrice as fast as B and B is twice as fast as A. How much time will pipe B alone take to fill the tank?
Had been one menless, then the number of days required to do a piece of work would have been one more. If the number of Man. Days required to complete the work is 56, how many workers were there?
A can do a piece of work in 16 hours, B and C can do it in 8 hours while A and C can do it 12 hours. How long will B alone take to do it?