A and B can do a piece of work in 12 days and 20 days, respectively. Both work for 3 days and then A leaves. How long (in days) will B take to complete the remaining work?
12
Combined rate of A and B: \(\tfrac1{12}+\tfrac1{20} = \tfrac{5+3}{60} = \tfrac{8}{60} = \tfrac{2}{15}\) per day.
Work done in 3 days: \(3\times\tfrac{2}{15} = \tfrac{6}{15} = \tfrac25\).
Remaining work: \(1-\tfrac25 = \tfrac35\).
Time for B alone to finish: \(\dfrac{3/5}{1/20} = 12\) days.
Hence, B will take 12 days to complete the remaining work.
Mohan can do a piece of work in 10 days and Sohan in 15 days. They started working together, but after 3 days Mohan left the work . What time will Sohan take to finish the work?
A tank is filled in 8 hours by three taps A, B and C. The tap C is thrice as fast as B and B is twice as fast as A. How much time will pipe B alone take to fill the tank?
Had been one menless, then the number of days required to do a piece of work would have been one more. If the number of Man. Days required to complete the work is 56, how many workers were there?
A can do a piece of work in 16 hours, B and C can do it in 8 hours while A and C can do it 12 hours. How long will B alone take to do it?