A and B can complete a task in 20 days and 25 days, respectively. They started working together, but B left after 5 days. How many more days will A take to finish the remaining work?
11 days
A completes the task in 20 days, so A's one-day work is \(\frac{1}{20}\); B completes it in 25 days, so B's one-day work is \(\frac{1}{25}\).
Together in one day they do \(\frac{1}{20} + \frac{1}{25} = \frac{5 + 4}{100} = \frac{9}{100}\).
In 5 days together they finish \(5 \times \frac{9}{100} = \frac{45}{100} = \frac{9}{20}\) of the work.
The remaining work is \(1 - \frac{9}{20} = \frac{11}{20}\).
A alone finishes this in \(\frac{11}{20} \div \frac{1}{20} = \frac{11}{20} \times 20 = 11\) days.
Hence, A takes 11 more days to finish the remaining work.
Mohan can do a piece of work in 10 days and Sohan in 15 days. They started working together, but after 3 days Mohan left the work . What time will Sohan take to finish the work?
A tank is filled in 8 hours by three taps A, B and C. The tap C is thrice as fast as B and B is twice as fast as A. How much time will pipe B alone take to fill the tank?
Had been one menless, then the number of days required to do a piece of work would have been one more. If the number of Man. Days required to complete the work is 56, how many workers were there?
A can do a piece of work in 16 hours, B and C can do it in 8 hours while A and C can do it 12 hours. How long will B alone take to do it?