3 people can do a job in 12 days. How many people are needed to finish it in 4 days?
9
For the same job, the total work in man-days stays constant: M1 × D1 = M2 × D2.
Total work = 3 × 12 = 36 man-days
People needed = 36 ÷ 4 = 9
Check: 9 × 4 = 36 man-days, the same as 3 × 12. Fewer days need proportionally more people, so 6 or 8 are too few and 12 is more than required.
Hence, 9.
A and B can complete a task together in 12 days, while B and C can finish it in 16 days. After A works on it for 5 days and B for 7 days, C takes the remaining 13 days to finish the work. How many days would it take for C to complete the work alone?
A is three times more efficient as a worker than B, which allows A to complete a job in 60 days less than B. If they work together, they can finish the job in:
If 6 machines complete a task in 10 days, how many days for 15 machines at the same rate?
A can do a work in 8 days and B in 12 days. They work together for 3 days. What part of the work is left?
A and B together can complete a work in 12 days. B and C together can complete the same work in 15 days. C and A together can do it in 20 days. In how many days can A alone complete the job?
A, B, and C are capable of completing a job in 30, 45, and 90 days, respectively. A works every day, while B and C join A every fifth day. How long will it take to finish the task?