Question

18 men can complete a certain work in 15 days working 8 hours a day. How many men can complete the same work in 12 days working 9 hours a day?

This question was previously asked in
SSC Selection Post 2021 Question Paper (09-Feb-2022) (Shift-1)
The correct answer is

20

Understanding Work and Time Problems

This question deals with the concept of work and time, specifically how the number of workers, the time spent working (days and hours per day), and the amount of work are related. A common principle in these problems is that the total amount of 'work' done is proportional to the number of workers, the number of days they work, and the hours they work each day, assuming constant efficiency.

The Man-Days-Hours Formula

For a fixed amount of work, the product of the number of men ($M$), the number of days ($D$), and the number of hours per day ($H$) is constant. We can write this as:

$\text{Total Work} = M \times D \times H$

If the work is the same in two different scenarios, we can equate the products:

$M_1 \times D_1 \times H_1 = M_2 \times D_2 \times H_2$

Where the subscript '1' refers to the first scenario and '2' refers to the second scenario.

Applying the Formula to the Problem

In the given problem, we have two scenarios:

  • Scenario 1: 18 men complete the work in 15 days working 8 hours a day.
  • Scenario 2: A certain number of men ($M_2$) complete the same work in 12 days working 9 hours a day.

Let's list the values:

  • $M_1 = 18$ men
  • $D_1 = 15$ days
  • $H_1 = 8$ hours/day
  • $M_2 = ?$ (unknown number of men)
  • $D_2 = 12$ days
  • $H_2 = 9$ hours/day

Step-by-Step Calculation

Using the formula $M_1 \times D_1 \times H_1 = M_2 \times D_2 \times H_2$, we substitute the known values:

$18 \times 15 \times 8 = M_2 \times 12 \times 9$

Now, we calculate the product on the left side:

$18 \times 15 = 270$

$270 \times 8 = 2160$

So, the equation becomes:

$2160 = M_2 \times 12 \times 9$

Next, calculate the product of days and hours in the second scenario:

$12 \times 9 = 108$

The equation is now:

$2160 = M_2 \times 108$

To find $M_2$, we need to isolate it by dividing both sides of the equation by 108:

$M_2 = \frac{2160}{108}$

Performing the division:

$M_2 = 20$

So, 20 men can complete the same work in 12 days working 9 hours a day.

Conclusion

The number of men required in the second scenario is 20. This corresponds to option 3.

Scenario Men (M) Days (D) Hours/Day (H) M × D × H
1 18 15 8 $18 \times 15 \times 8 = 2160$
2 $M_2$ 12 9 $M_2 \times 12 \times 9 = M_2 \times 108$

Equating the M × D × H products for both scenarios:

$2160 = M_2 \times 108$

$M_2 = \frac{2160}{108} = 20$

Revision Table: Work and Time Concepts

Concept Description Formula (Constant Work)
Man-Days If work is constant, Men × Days is constant. (Assuming constant hours/day). $M_1 D_1 = M_2 D_2$
Man-Hours If work is constant, Men × Hours is constant. (Total hours worked = Days × Hours/Day). $M_1 H_{total,1} = M_2 H_{total,2}$
Man-Days-Hours If work is constant, Men × Days × Hours/Day is constant. $M_1 D_1 H_1 = M_2 D_2 H_2$
Efficiency Efficiency is inversely proportional to time taken to complete work. If A is twice as efficient as B, A takes half the time B takes for the same work. Work = Efficiency × Time

Additional Information: Inverse Proportionality in Work Problems

In work and time problems, variables are often inversely proportional when the total work is fixed. For example:

  • If the number of men increases, the number of days required to complete the same work decreases (inverse proportionality).
  • If the hours worked per day increases, the number of days required decreases (inverse proportionality).
  • If the number of men decreases, the number of hours per day they need to work might increase to finish in the same number of days (inverse proportionality).

The formula $M \times D \times H = \text{Constant Work}$ shows this relationship clearly. If Work is constant, any increase in one variable (like M) must be balanced by a decrease in one or both of the other variables (D or H).

In this problem, both the number of days (from 15 to 12) and the hours per day (from 8 to 9) changed, requiring a calculation involving all three factors.

Was this answer helpful?

Similar Questions

  1. If 72 persons build a 220-m-long wall in 6 days, then how many persons will be required to build the same type of wall of 550-m length in 5 days?

  2. A and B can complete a work in 16 days and 12 days respectively. Both work for 4 days and then A leaves.  Find how much time will B take to complete the remaining work?

  3. A can do a piece of work in 66 days and B can do the same work in two-third of the time taken by A. Working together, what part of the same work can they complete in 12 days?

  4. A can do a work in 10 days. He worked for 6 days and left the work. The remaining work was done by B in 8 days. In how many days can B alone do 65% of the work?

  5. A and B together can do a certain work in 36 days, whereas B and C together can do it in 30 days. A, B and C together can complete the same work to 24 days. In how many days can A alone complete 33 \(\frac{1}{3}\) % of the same work?

  6. A and B can do a piece of work in 24 days and 48 days, respectively. working together, they completed the work in 12 days with the help of C. How long (in days) will C take of do five-sixth of the work all by himself?

  7. A and B can do a certain work in 25 and 20 days, respectively. They work together for 4 days. The remaining work is completed by C in 8 days. C alone can complete 40% of the original work in:

  8. In a press, there are three types of printing machines, P, Q and R. Machine P can print 10,000 pages in 8 hours, machine Q can finish the same task in 10 hours and machine R can finish the same task in 15 hours. All the three machines start the work at 9 : 00 a.m. Machine P breaks down at 11 : 00 a.m. and machines Q and R finish the task. The approximate time of completion of the job is

  9. A certain number of persons can complete a task in 28 days. If there were 150 persons more, it would have taken 7 days less for the task to be completed. How many persons are there in the beginning?

  10. A works twice as fast as B, whereas A and B together can work three times as fast as C. They all work together on a job and get a sum of Rs 17,136 for the completion of the job. The share of A is:


Important Questions from Time and Work

  1. Mohan can do a piece of work in 10 days and Sohan in 15 days. They started working together, but after 3 days Mohan left the work . What time will Sohan take to finish the work?

  2. A tank is filled in 8 hours by three taps A, B and C. The tap C is thrice as fast as B and B is twice as fast as A. How much time will pipe B alone take to fill the tank?

  3. Had been one menless, then the number of days required to do a piece of work would have been one more. If the number of Man. Days required to complete the work is 56, how many workers were there?

  4. A can do a piece of work in 16 hours, B and C can do it in 8 hours while A and C can do it 12 hours. How long will B alone take to do it?

  5. lf 12 men can do a work in 20 days, in how many days will the work be done by 15 men-
Need Expert Advice?
Upcoming Exams
UPSSSC PET
October 25, 2026
SSC JE
November 02, 2026
SSC CPO
November 20, 2026
SSC CHSL
November 30, 2026
Test Series
SSC Selection Post img
SSC
SSC Selection Post (Graduation) (Phase 12) 2025 Mock Test Series
489 Tests 5 Tests Free
5493 Attempts
4.8(317)
English, Hindi