All Exams Test series for 1 year @ ₹349 only
Question

A works twice as fast as B, whereas A and B together can work three times as fast as C. They all work together on a job and get a sum of Rs 17,136 for the completion of the job. The share of A is:

This question was previously asked in
SSC Selection Post 2020 Graduation Level Question Paper (14 Dec, 2020) (Shift 3)
The correct answer is

Rs. 8,568

Understanding the Work and Wages Problem

This question involves calculating the share of an individual (A) from a total sum received for completing a job, based on the work efficiency of different individuals (A, B, and C).

In work and wages problems, the amount of wages received by each person is directly proportional to the amount of work done by them. When they work for the same duration, the work done is proportional to their efficiency or work rate.

The key information given is:

  • A works twice as fast as B.
  • A and B together work three times as fast as C.
  • Total earnings for the job are Rs 17,136.

Our goal is to find the ratio of their work rates (efficiency) because the wages will be distributed in that same ratio.

Calculating the Efficiency Ratios

Let's denote the work rate (efficiency) of A, B, and C as $r_A$, $r_B$, and $r_C$ respectively.

From the first statement:

A works twice as fast as B. This means $r_A = 2 \times r_B$.

From the second statement:

A and B together work three times as fast as C. This means the combined rate of A and B is three times the rate of C.

So, $r_A + r_B = 3 \times r_C$.

Now, we can substitute the first equation into the second equation to relate the rates of B and C:

$(2 \times r_B) + r_B = 3 \times r_C$

$3 \times r_B = 3 \times r_C$

Dividing both sides by 3, we get:

$r_B = r_C$

So, the efficiency of B is equal to the efficiency of C.

Now we can find the ratio of their efficiencies $r_A : r_B : r_C$.

  • We know $r_A = 2 \times r_B$.
  • We know $r_B = r_C$.

If we consider $r_B$ as 1 unit, then:

  • $r_B = 1$
  • $r_C = r_B = 1$
  • $r_A = 2 \times r_B = 2 \times 1 = 2$

Therefore, the ratio of their work rates is $r_A : r_B : r_C = 2 : 1 : 1$.

Distributing the Wages Based on Efficiency Ratio

Since the wages are distributed in proportion to the work done, and they work together for the same time, the wages will be distributed in the ratio of their efficiencies.

Ratio of shares of A, B, and C = $r_A : r_B : r_C = 2 : 1 : 1$.

The total ratio parts are $2 + 1 + 1 = 4$.

The total amount of wages received is Rs 17,136.

A's share is $\frac{\text{A's ratio part}}{\text{Total ratio parts}} \times \text{Total Wages}$.

A's share = $\frac{2}{4} \times 17136$

A's share = $\frac{1}{2} \times 17136$

A's share = $8568$

So, the share of A is Rs 8,568.

Summary of Share Calculation

Here is a breakdown of how the total wages are distributed:

Person Efficiency Ratio Fraction of Total Wage Calculated Share
A 2 $\frac{2}{4}$ $\frac{2}{4} \times 17136 = 8568$
B 1 $\frac{1}{4}$ $\frac{1}{4} \times 17136 = 4284$
C 1 $\frac{1}{4}$ $\frac{1}{4} \times 17136 = 4284$

Total Share = Rs 8568 (A) + Rs 4284 (B) + Rs 4284 (C) = Rs 17136.

This confirms that the shares are calculated correctly based on the efficiency ratio.

Revision Table: Work and Wages Concepts

Concept Explanation Relation to Problem
Work Rate (Efficiency) The amount of work done by a person or team in a unit of time. Used to establish the ratio A:B:C.
Total Work The entire job or task to be completed. Implicitly represented by the total wage sum.
Wage Distribution Wages are divided among workers in proportion to the work they complete. The basis for sharing the Rs 17,136.
Ratio and Proportion Mathematical tools used to compare quantities and distribute values proportionally. Applied to determine individual shares from the total wage based on efficiency ratios.

Additional Information: Work and Time Relation

While this problem focuses on wage distribution based on efficiency when working together for the same time, it's useful to remember the relationship between work, rate, and time:

Work = Rate $\times$ Time

If the work is constant (completing the same job), then Rate is inversely proportional to Time. A faster worker (higher rate) takes less time to complete the same work alone.

In this problem, because A, B, and C work together on the same job for the same duration, their individual contributions to the total work are directly proportional to their rates (efficiencies).

  • If A has rate $r_A$, B has $r_B$, C has $r_C$, and they work for time $T$.
  • Work done by A = $r_A \times T$
  • Work done by B = $r_B \times T$
  • Work done by C = $r_C \times T$
  • Ratio of work done = $(r_A \times T) : (r_B \times T) : (r_C \times T) = r_A : r_B : r_C$.

This confirms why the wage distribution is based directly on the ratio of their rates (efficiencies) when they work together on the same task for the same amount of time.

Was this answer helpful?

Similar Questions

  1. If 72 persons build a 220-m-long wall in 6 days, then how many persons will be required to build the same type of wall of 550-m length in 5 days?

  2. A and B can complete a work in 16 days and 12 days respectively. Both work for 4 days and then A leaves.  Find how much time will B take to complete the remaining work?

  3. A can do a piece of work in 66 days and B can do the same work in two-third of the time taken by A. Working together, what part of the same work can they complete in 12 days?

  4. A can do a work in 10 days. He worked for 6 days and left the work. The remaining work was done by B in 8 days. In how many days can B alone do 65% of the work?

  5. A and B together can do a certain work in 36 days, whereas B and C together can do it in 30 days. A, B and C together can complete the same work to 24 days. In how many days can A alone complete 33 \(\frac{1}{3}\) % of the same work?

  6. 18 men can complete a certain work in 15 days working 8 hours a day. How many men can complete the same work in 12 days working 9 hours a day?

  7. A and B can do a piece of work in 24 days and 48 days, respectively. working together, they completed the work in 12 days with the help of C. How long (in days) will C take of do five-sixth of the work all by himself?

  8. A and B can do a certain work in 25 and 20 days, respectively. They work together for 4 days. The remaining work is completed by C in 8 days. C alone can complete 40% of the original work in:

  9. In a press, there are three types of printing machines, P, Q and R. Machine P can print 10,000 pages in 8 hours, machine Q can finish the same task in 10 hours and machine R can finish the same task in 15 hours. All the three machines start the work at 9 : 00 a.m. Machine P breaks down at 11 : 00 a.m. and machines Q and R finish the task. The approximate time of completion of the job is

  10. A certain number of persons can complete a task in 28 days. If there were 150 persons more, it would have taken 7 days less for the task to be completed. How many persons are there in the beginning?


Important Questions from Time and Work

  1. Mohan can do a piece of work in 10 days and Sohan in 15 days. They started working together, but after 3 days Mohan left the work . What time will Sohan take to finish the work?

  2. A tank is filled in 8 hours by three taps A, B and C. The tap C is thrice as fast as B and B is twice as fast as A. How much time will pipe B alone take to fill the tank?

  3. Had been one menless, then the number of days required to do a piece of work would have been one more. If the number of Man. Days required to complete the work is 56, how many workers were there?

  4. A can do a piece of work in 16 hours, B and C can do it in 8 hours while A and C can do it 12 hours. How long will B alone take to do it?

  5. lf 12 men can do a work in 20 days, in how many days will the work be done by 15 men-
Need Expert Advice?
Upcoming Exams
UPSSSC PET
October 25, 2026
SSC JE
November 02, 2026
SSC CPO
November 20, 2026
SSC CHSL
November 30, 2026
Test Series
SSC Selection Post img
SSC
SSC Selection Post (Graduation) (Phase 12) 2025 Mock Test Series
489 Tests 5 Tests Free
5490 Attempts
4.8(317)
English, Hindi

Start Your Preparation with Prepp Mobile App

Download the app from Google Play & App Store
Download the app from Google Play & App Store
Prepp Mobile App