All Exams Test series for 1 year @ ₹349 only
Question

12 men working 8 hours a day can completely build a wall of length 100 m, breadth 20 cm and height 5 m in 10 days. How many days will 16 men working 10 hours a day require to build a wall of length 200 m, breadth 60 cm and height 5 m ?

This question was previously asked in
CDS 2 2026 Maths Question Paper (13-Sep-2026)
The correct answer is

36

To solve this problem, we can use the concept of man-hours, a common technique in work and time problems. This approach calculates the total hours required to complete a job based on the number of workers and hours worked per day.

First, determine the volume of the wall that 12 men can build.

  1. Volume of original wall = Length × Breadth × Height 
    \(= 100 \, \text{m} \times 0.2 \, \text{m} \times 5 \, \text{m} = 100 \times 0.2 \times 5 = 100 \, \text{m}^3\)

Next, find out the total man-hours required to build the wall, given the current team configuration:

  1. Total man-hours = (Number of workers) × (Hours per day) × (Days) 
    \(= 12 \times 8 \times 10 = 960 \, \text{man-hours}\)

To build this wall, 960 man-hours are required. Now, calculate the volume of the new wall:

  1. Volume of new wall = Length × Breadth × Height 
    \(= 200 \, \text{m} \times 0.6 \, \text{m} \times 5 \, \text{m} = 600 \, \text{m}^3\)

The ratio of volumes gives us the ratio of man-hours needed:

  1. Volume Ratio = \(\frac{600}{100} = 6\)

Thus, the man-hours required for the new wall is:

  1. Total man-hours for new wall = 960 × 6 = 5760 man-hours

Now calculate how many days 16 men working 10 hours a day will take to complete this:

  1. Work done per day by 16 men = (Number of workers) × (Hours per day) 
    Work done per day = \(16 \times 10 = 160 \, \text{man-hours}\)
  2. Days required = \(\frac{5760}{160} = 36 \, \text{days}\)

Thus, the correct answer is: 36 days.

Was this answer helpful?

Similar Questions

  1. A, B, C, D can complete a work in 3, 6, 9, 12 hours respectively. Further, only one person can work at a time in each hour and nobody can work for two consecutive hours. It is not necessary to engage all. What is the minimum number of hours that they will take to finish the work?
  2. 50 men can complete a work in 40 days. They begin the work together but a batch of 5 men left after each period of 10 days. What is the time to complete the work?
  3. If the work done by \(x\) men in \((x + 1)\) days is equal to the work done by \((x + 5)\) men in \((x - 2)\) days, then what is the value of \(x\)?
  4. \(p\) number of men can finish a piece of work in \(q\) days. If there are 50% more men, then the work will be finished 12 days earlier. What is the value of \(q\)?
  5. Eight men and 24 women can finish a piece of work in one day while 12 men and 18 women can also finish it in one day. What is the time taken by 24 men and 72 women to finish the work ?
  6. X can do a piece of work in 4 days and Y can do the same piece of work in 6 days. Which of the following statements is/are correct ?
    I. If X and Y work alternately starting with X, then the piece of work will be finished on the fifth day.
    II. If X and Y work alternately starting with Y, then the piece of work will be finished in less than 5 days.
    Select the answer using the code given below :

Important Questions from Time and work

  1. 5 men can complete a piece of work in 18 days, while 9 women can do it in 5 days. In how many days can 3 women and 3 men complete this work?
  2. A can lay railway track between two given stations in 16 days and B can do the same job in 11 days. With the help of C, they did the job in 3 days only. Then, C alone can do the job in
  3. A can lay railway track between two given stations in 17 days and B can do the same job in 16 days. With the help of C, they did the job in 4 days only. Then, C alone can do the job in __________

  4. A can do a work in 10 days and B can do the same work in 20 days. If they work on it together for 6 days, then what fraction of the work is left?
  5. Jaya can do a certain piece of work in 30 days. Jaya and Sushma can together do the same work in 21 days, and Jaya, Sushma and Hina can do the same work together in 14 days. In how many days can Jaya and Hina do the same work together?
Need Expert Advice?
Test Series
CDS img
Defence
UPSC CDS 2026 Mock Test Series
559 Tests 4 Tests Free
1833 Attempts
4.3(195)
English, Hindi
More Questions from CDS

Start Your Preparation with Prepp Mobile App

Download the app from Google Play & App Store
Download the app from Google Play & App Store
Prepp Mobile App