All Exams Test series for 1 year @ ₹349 only
Question

If the work done by \(x\) men in \((x + 1)\) days is equal to the work done by \((x + 5)\) men in \((x - 2)\) days, then what is the value of \(x\)?

This question was previously asked in
CDS 2 2024 Maths Question Paper (01-Sep-2024)
The correct answer is
5

Understanding the Work Done Relationship

This problem involves the concept of work done, which is typically calculated as the product of the number of workers, the time spent working, and the rate of work. Assuming the rate of work for each man is the same, the total work done is directly proportional to the number of men and the number of days they work.

We can express this relationship as:

Work = (Number of Men) × (Number of Days)

Men and Days Equation Setup

Let's denote the number of men and days for the two scenarios:

  • Scenario 1: \(x\) men working for \((x + 1)\) days.
  • Scenario 2: \((x + 5)\) men working for \((x - 2)\) days.

The problem states that the work done in both scenarios is equal. Therefore, we can set up the equation:

Work1 = Work2

\( x \times (x + 1) = (x + 5) \times (x - 2) \)

Solving the Work Equation Algebraically

Now, we need to solve this equation for \(x\).

  1. Expand both sides of the equation:
    • Left side: \( x \times (x + 1) = x^2 + x \)
    • Right side: \( (x + 5) \times (x - 2) = x(x - 2) + 5(x - 2) = x^2 - 2x + 5x - 10 = x^2 + 3x - 10 \)
  2. Set the expanded expressions equal:

    \( x^2 + x = x^2 + 3x - 10 \)

  3. Simplify the equation: Subtract \( x^2 \) from both sides:

    \( x = 3x - 10 \)

  4. Isolate \(x\): Rearrange the terms to solve for \(x\). Subtract \(x\) from both sides and add 10 to both sides:

    \( 10 = 3x - x \)

    \( 10 = 2x \)

  5. Calculate the value of \(x\): Divide by 2:

    \( x = \frac{10}{2} \)

    \( x = 5 \)

Validating the Solution

We must ensure that the values for men and days are physically possible (i.e., positive numbers).

If \( x = 5 \):

  • Number of men in scenario 1 = \( x = 5 \) (Positive)
  • Number of days in scenario 1 = \( x + 1 = 5 + 1 = 6 \) (Positive)
  • Number of men in scenario 2 = \( x + 5 = 5 + 5 = 10 \) (Positive)
  • Number of days in scenario 2 = \( x - 2 = 5 - 2 = 3 \) (Positive)

All values are positive, so \( x = 5 \) is a valid solution.

Let's check the work done:

  • Work1 = \( 5 \text{ men} \times 6 \text{ days} = 30 \) units of work.
  • Work2 = \( 10 \text{ men} \times 3 \text{ days} = 30 \) units of work.

The work done is indeed equal in both scenarios.

Conclusion

Based on the algebraic solution and validation, the value of \(x\) is 5.

Was this answer helpful?

Similar Questions

  1. A, B, C, D can complete a work in 3, 6, 9, 12 hours respectively. Further, only one person can work at a time in each hour and nobody can work for two consecutive hours. It is not necessary to engage all. What is the minimum number of hours that they will take to finish the work?
  2. 50 men can complete a work in 40 days. They begin the work together but a batch of 5 men left after each period of 10 days. What is the time to complete the work?
  3. \(p\) number of men can finish a piece of work in \(q\) days. If there are 50% more men, then the work will be finished 12 days earlier. What is the value of \(q\)?
  4. 12 men working 8 hours a day can completely build a wall of length 100 m, breadth 20 cm and height 5 m in 10 days. How many days will 16 men working 10 hours a day require to build a wall of length 200 m, breadth 60 cm and height 5 m ?
  5. Eight men and 24 women can finish a piece of work in one day while 12 men and 18 women can also finish it in one day. What is the time taken by 24 men and 72 women to finish the work ?
  6. X can do a piece of work in 4 days and Y can do the same piece of work in 6 days. Which of the following statements is/are correct ?
    I. If X and Y work alternately starting with X, then the piece of work will be finished on the fifth day.
    II. If X and Y work alternately starting with Y, then the piece of work will be finished in less than 5 days.
    Select the answer using the code given below :

Important Questions from Time and work

  1. 5 men can complete a piece of work in 18 days, while 9 women can do it in 5 days. In how many days can 3 women and 3 men complete this work?
  2. A can lay railway track between two given stations in 16 days and B can do the same job in 11 days. With the help of C, they did the job in 3 days only. Then, C alone can do the job in
  3. A can lay railway track between two given stations in 17 days and B can do the same job in 16 days. With the help of C, they did the job in 4 days only. Then, C alone can do the job in __________

  4. A can do a work in 10 days and B can do the same work in 20 days. If they work on it together for 6 days, then what fraction of the work is left?
  5. Jaya can do a certain piece of work in 30 days. Jaya and Sushma can together do the same work in 21 days, and Jaya, Sushma and Hina can do the same work together in 14 days. In how many days can Jaya and Hina do the same work together?
Need Expert Advice?
Test Series
CDS img
Defence
UPSC CDS 2026 Mock Test Series
559 Tests 4 Tests Free
1833 Attempts
4.3(195)
English, Hindi
More Questions from CDS

Start Your Preparation with Prepp Mobile App

Download the app from Google Play & App Store
Download the app from Google Play & App Store
Prepp Mobile App