All Exams Test series for 1 year @ ₹349 only
Question

50 men can complete a work in 40 days. They begin the work together but a batch of 5 men left after each period of 10 days. What is the time to complete the work?

This question was previously asked in
CDS 2 2024 Maths Question Paper (01-Sep-2024)
The correct answer is
45 days

Work Problem: Calculating Time with Decreasing Workforce

This problem involves calculating the total time needed to complete a work when the number of workers changes over time. We are given the initial number of men, the time they would take if they all worked together throughout, and the condition that some men leave periodically.

Understanding Total Work Required

First, let's determine the total amount of work that needs to be done. This is often measured in 'man-days', which represents the total effort required.

Total Work = (Initial Number of Men) × (Initial Time)

Given:

  • Initial Number of Men = 50
  • Initial Time = 40 days

Using LaTeX for the formula:

Total Work = \(50 \text{ men} \times 40 \text{ days} = 2000 \text{ man-days}\)

So, the project requires a total of 2000 man-days of effort.

Step-by-Step Work Calculation with Workforce Reduction

The problem states that 5 men leave after *each period* of 10 days. We need to calculate the work done in each 10-day interval and track the remaining workforce and work.

Period 1: Days 1-10

  • Number of men working = 50
  • Work done in this period = \(50 \text{ men} \times 10 \text{ days} = 500 \text{ man-days}\)
  • Total work done so far = 500 man-days
  • Remaining work = \(2000 - 500 = 1500 \text{ man-days}\)
  • At the end of day 10, 5 men leave.
  • Number of men for the next period = \(50 - 5 = 45\)

Period 2: Days 11-20

  • Number of men working = 45
  • Work done in this period = \(45 \text{ men} \times 10 \text{ days} = 450 \text{ man-days}\)
  • Total work done so far = \(500 + 450 = 950 \text{ man-days}\)
  • Remaining work = \(2000 - 950 = 1050 \text{ man-days}\)
  • At the end of day 20, 5 men leave.
  • Number of men for the next period = \(45 - 5 = 40\)

Period 3: Days 21-30

  • Number of men working = 40
  • Work done in this period = \(40 \text{ men} \times 10 \text{ days} = 400 \text{ man-days}\)
  • Total work done so far = \(950 + 400 = 1350 \text{ man-days}\)
  • Remaining work = \(2000 - 1350 = 650 \text{ man-days}\)
  • At the end of day 30, 5 men leave.
  • Number of men for the next period = \(40 - 5 = 35\)

Period 4: Days 31-40

  • Number of men working = 35
  • Work done in this period = \(35 \text{ men} \times 10 \text{ days} = 350 \text{ man-days}\)
  • Total work done so far = \(1350 + 350 = 1700 \text{ man-days}\)
  • Remaining work = \(2000 - 1700 = 300 \text{ man-days}\)
  • At the end of day 40, 5 men leave.
  • Number of men for the next period = \(35 - 5 = 30\)

Period 5: Days 41 onwards

  • Number of men working = 30
  • Remaining work to be done = 300 man-days
  • Time needed to complete the remaining work = \(\frac{\text{Remaining Work}}{\text{Number of men}}\)
  • Time needed = \(\frac{300 \text{ man-days}}{30 \text{ men}} = 10 \text{ days}\)

Total Time Calculation

The total time to complete the work is the sum of the time taken in all periods until the work is finished.

Total Time = (Time for Period 1) + (Time for Period 2) + (Time for Period 3) + (Time for Period 4) + (Time needed for remaining work)

Total Time = 10 days + 10 days + 10 days + 10 days + 10 days

Total Time = 50 days

Based on the standard calculation method for work problems, the total time required to complete the work is 50 days. The calculation involves determining the total work required and then accounting for the decreasing number of workers over successive 10-day periods.

Was this answer helpful?

Similar Questions

  1. A, B, C, D can complete a work in 3, 6, 9, 12 hours respectively. Further, only one person can work at a time in each hour and nobody can work for two consecutive hours. It is not necessary to engage all. What is the minimum number of hours that they will take to finish the work?
  2. If the work done by \(x\) men in \((x + 1)\) days is equal to the work done by \((x + 5)\) men in \((x - 2)\) days, then what is the value of \(x\)?
  3. \(p\) number of men can finish a piece of work in \(q\) days. If there are 50% more men, then the work will be finished 12 days earlier. What is the value of \(q\)?
  4. 12 men working 8 hours a day can completely build a wall of length 100 m, breadth 20 cm and height 5 m in 10 days. How many days will 16 men working 10 hours a day require to build a wall of length 200 m, breadth 60 cm and height 5 m ?
  5. Eight men and 24 women can finish a piece of work in one day while 12 men and 18 women can also finish it in one day. What is the time taken by 24 men and 72 women to finish the work ?
  6. X can do a piece of work in 4 days and Y can do the same piece of work in 6 days. Which of the following statements is/are correct ?
    I. If X and Y work alternately starting with X, then the piece of work will be finished on the fifth day.
    II. If X and Y work alternately starting with Y, then the piece of work will be finished in less than 5 days.
    Select the answer using the code given below :

Important Questions from Time and work

  1. 5 men can complete a piece of work in 18 days, while 9 women can do it in 5 days. In how many days can 3 women and 3 men complete this work?
  2. A can lay railway track between two given stations in 16 days and B can do the same job in 11 days. With the help of C, they did the job in 3 days only. Then, C alone can do the job in
  3. A can lay railway track between two given stations in 17 days and B can do the same job in 16 days. With the help of C, they did the job in 4 days only. Then, C alone can do the job in __________

  4. A can do a work in 10 days and B can do the same work in 20 days. If they work on it together for 6 days, then what fraction of the work is left?
  5. Jaya can do a certain piece of work in 30 days. Jaya and Sushma can together do the same work in 21 days, and Jaya, Sushma and Hina can do the same work together in 14 days. In how many days can Jaya and Hina do the same work together?
Need Expert Advice?
Test Series
CDS img
Defence
UPSC CDS 2026 Mock Test Series
559 Tests 4 Tests Free
1833 Attempts
4.3(195)
English, Hindi
More Questions from CDS

Start Your Preparation with Prepp Mobile App

Download the app from Google Play & App Store
Download the app from Google Play & App Store
Prepp Mobile App