All Exams Test series for 1 year @ ₹349 only
Question

A, B, C, D can complete a work in 3, 6, 9, 12 hours respectively. Further, only one person can work at a time in each hour and nobody can work for two consecutive hours. It is not necessary to engage all. What is the minimum number of hours that they will take to finish the work?

This question was previously asked in
CDS 2 2024 Maths Question Paper (01-Sep-2024)
The correct answer is
4

Understanding the Work and Time Problem

This problem asks for the minimum time needed to complete a work by four individuals, A, B, C, and D, each having a different working speed. We must also consider the specific rules about how they work: only one person works per hour, and no one can work in two consecutive hours.

Calculating Individual Work Rates

First, we determine the rate at which each person works. The rate is the fraction of the work completed per hour. It's calculated as \(1 / (\text{time taken to complete the work})\).

  • Person A's rate: A completes the work in 3 hours, so A's rate is \( \frac{1}{3} \) work per hour.
  • Person B's rate: B completes the work in 6 hours, so B's rate is \( \frac{1}{6} \) work per hour.
  • Person C's rate: C completes the work in 9 hours, so C's rate is \( \frac{1}{9} \) work per hour.
  • Person D's rate: D completes the work in 12 hours, so D's rate is \( \frac{1}{12} \) work per hour.

Analyzing the Working Constraints

The constraints are crucial for finding the minimum time:

  • Single Worker Per Hour: Only one person can perform work during any single hour.
  • No Consecutive Work: An individual cannot work in one hour and then immediately work in the next hour. They must have at least one hour break between their working shifts.
  • Optional Engagement: It's not required for all four people (A, B, C, D) to work; we can use only those needed to finish fastest.

Our goal is to complete 1 unit of work in the shortest possible total time.

Strategy for Minimum Time Calculation

To minimize the total time, we should prioritize using the workers who are the most efficient (have the highest work rates). Person A is the fastest (\(1/3\) work/hour). However, due to the constraint that no one can work for two consecutive hours, A cannot work continuously.

The best strategy is to pair the most efficient worker (A) with the next most efficient worker available, ensuring the constraint is met. Let's consider pairing A with B, the second fastest worker.

We can analyze the work done in a 2-hour cycle:

  • Hour 1: Person A works. Work done = \( \frac{1}{3} \).
  • Hour 2: Person A cannot work again. The next best choice is Person B. Work done = \( \frac{1}{6} \).

The total work completed in these 2 hours (1 hour by A, 1 hour by B) is:

\( \text{Work done in 2 hours} = \text{A's rate} + \text{B's rate} = \frac{1}{3} + \frac{1}{6} \)

To add these fractions, we use a common denominator, which is 6:

\( \frac{1}{3} + \frac{1}{6} = \frac{2}{6} + \frac{1}{6} = \frac{3}{6} = \frac{1}{2} \)

This means that by alternating A and B, they complete \( \frac{1}{2} \) of the work every 2 hours.

Determining Total Minimum Hours

To complete the entire work (1 unit), we need to find out how many of these 2-hour cycles are needed.

Total work = 1 unit.

Work completed per 2-hour cycle = \( \frac{1}{2} \) unit.

Number of cycles required = \( \frac{\text{Total Work}}{\text{Work per cycle}} = \frac{1}{1/2} = 2 \) cycles.

Since each cycle takes 2 hours, the total minimum time is:

\( \text{Total Minimum Time} = \text{Number of cycles} \times \text{Hours per cycle} \) \( \text{Total Minimum Time} = 2 \times 2 \text{ hours} = 4 \text{ hours} \)

The sequence of work would be: A works (Hour 1), B works (Hour 2), A works (Hour 3), B works (Hour 4). This completes the work in exactly 4 hours and adheres to all the rules.

We can confirm this is the minimum by noting that any other pairing (like A with C, or B with C) would result in less work done per 2-hour cycle, leading to a longer total time.

For example:

  • A + C in 2 hours = \( \frac{1}{3} + \frac{1}{9} = \frac{4}{9} \) work. Total time = \( \frac{1}{4/9} \times 2 = \frac{9}{2} = 4.5 \) hours.
  • A + D in 2 hours = \( \frac{1}{3} + \frac{1}{12} = \frac{5}{12} \) work. Total time = \( \frac{1}{5/12} \times 2 = \frac{12}{5} \times 2 = 4.8 \) hours.

Therefore, the minimum number of hours required is 4.

Was this answer helpful?

Similar Questions

  1. 50 men can complete a work in 40 days. They begin the work together but a batch of 5 men left after each period of 10 days. What is the time to complete the work?
  2. If the work done by \(x\) men in \((x + 1)\) days is equal to the work done by \((x + 5)\) men in \((x - 2)\) days, then what is the value of \(x\)?
  3. \(p\) number of men can finish a piece of work in \(q\) days. If there are 50% more men, then the work will be finished 12 days earlier. What is the value of \(q\)?
  4. 12 men working 8 hours a day can completely build a wall of length 100 m, breadth 20 cm and height 5 m in 10 days. How many days will 16 men working 10 hours a day require to build a wall of length 200 m, breadth 60 cm and height 5 m ?
  5. Eight men and 24 women can finish a piece of work in one day while 12 men and 18 women can also finish it in one day. What is the time taken by 24 men and 72 women to finish the work ?
  6. X can do a piece of work in 4 days and Y can do the same piece of work in 6 days. Which of the following statements is/are correct ?
    I. If X and Y work alternately starting with X, then the piece of work will be finished on the fifth day.
    II. If X and Y work alternately starting with Y, then the piece of work will be finished in less than 5 days.
    Select the answer using the code given below :

Important Questions from Time and work

  1. 5 men can complete a piece of work in 18 days, while 9 women can do it in 5 days. In how many days can 3 women and 3 men complete this work?
  2. A can lay railway track between two given stations in 16 days and B can do the same job in 11 days. With the help of C, they did the job in 3 days only. Then, C alone can do the job in
  3. A can lay railway track between two given stations in 17 days and B can do the same job in 16 days. With the help of C, they did the job in 4 days only. Then, C alone can do the job in __________

  4. A can do a work in 10 days and B can do the same work in 20 days. If they work on it together for 6 days, then what fraction of the work is left?
  5. Jaya can do a certain piece of work in 30 days. Jaya and Sushma can together do the same work in 21 days, and Jaya, Sushma and Hina can do the same work together in 14 days. In how many days can Jaya and Hina do the same work together?
Need Expert Advice?
Test Series
CDS img
Defence
UPSC CDS 2026 Mock Test Series
559 Tests 4 Tests Free
1833 Attempts
4.3(195)
English, Hindi
More Questions from CDS

Start Your Preparation with Prepp Mobile App

Download the app from Google Play & App Store
Download the app from Google Play & App Store
Prepp Mobile App