I. If X and Y work alternately starting with X, then the piece of work will be finished on the fifth day.
II. If X and Y work alternately starting with Y, then the piece of work will be finished in less than 5 days.
Select the answer using the code given below :
I only
To solve this question, we need to evaluate each statement based on the given conditions. Let's assess each statement step-by-step:
Given:
Calculations:
Let's calculate the work done when they work alternately:
Final Conclusion: The correct answer is "
I only
A person can complete 20% of work in 8 days and another person y can complete 25% of the same work in 6 days. If they work together, in how many days will 40% of the work be completed?
P works thrice as fast as Q, whereas P and Q together can work four times as fast as R. If P, Q and R together work on a job, in what ratio should they share the earnings?
There are three pillars X, Y and Z of different heights. Three spiders A, B and C start to climb on these pillars simultaneously. In one chance, A climbs on X by 6 cm but slips down 1 cm. B climbs on Y by 7 cm but slips down 3 cm. C climbs on Z by 6.5 cm but slips down 2 cm. If each of them requires 40 chances to reach the top of the pillars, what is the height of the shortest pillar?
There is an order of 19000 quantity of a particular product from a customer. The firm produces 1000 quantity of that product per out of which 5% are unfit for sale. In how many days will the order be completed?
Ram and Shyam work on a job together for four days and complete 60% of it. Ram takes leave then and Shyam works for eight more days to complete the job. How long would Ram take to complete the entire job alone?