I. If X and Y work alternately starting with X, then the piece of work will be finished on the fifth day.
II. If X and Y work alternately starting with Y, then the piece of work will be finished in less than 5 days.
Select the answer using the code given below :
I only
To solve this question, we need to evaluate each statement based on the given conditions. Let's assess each statement step-by-step:
Given:
Calculations:
Let's calculate the work done when they work alternately:
Final Conclusion: The correct answer is "
I only
A can lay railway track between two given stations in 17 days and B can do the same job in 16 days. With the help of C, they did the job in 4 days only. Then, C alone can do the job in __________