This question is about calculating the time required to complete a piece of work when the number of workers changes. We are given that a certain number of men (\(p\)) can finish a work in \(q\) days. The scenario changes when the number of men increases, and the work gets completed faster. We need to find the original number of days (\(q\)) required.
Let's break down the information:
Now, consider the change:
Since the amount of work remains the same, the total work done initially must equal the total work done with the increased number of men.
We can set up an equation based on the principle that Work = Number of Men × Number of Days:
Initial Work = New Work
\(p \times q = (1.5p) \times (q - 12)\)
Now, we solve this equation for \(q\). Since \(p\) represents the number of men, we know \(p\) cannot be zero. Therefore, we can divide both sides of the equation by \(p\):
\(q = 1.5 \times (q - 12)\)
Let's simplify the equation:
\(q = 1.5q - (1.5 \times 12)\)
\(q = 1.5q - 18\)
\(0 = 1.5q - q - 18\)
\(0 = 0.5q - 18\)
\(18 = 0.5q\)
\(q = \frac{18}{0.5}\)
\(q = 18 \times 2\)
\(q = 36\)
The initial number of days (\(q\)) required for \(p\) men to finish the work is 36 days.
Therefore, the value of \(q\) is 36.
A person can complete 20% of work in 8 days and another person y can complete 25% of the same work in 6 days. If they work together, in how many days will 40% of the work be completed?
P works thrice as fast as Q, whereas P and Q together can work four times as fast as R. If P, Q and R together work on a job, in what ratio should they share the earnings?
There are three pillars X, Y and Z of different heights. Three spiders A, B and C start to climb on these pillars simultaneously. In one chance, A climbs on X by 6 cm but slips down 1 cm. B climbs on Y by 7 cm but slips down 3 cm. C climbs on Z by 6.5 cm but slips down 2 cm. If each of them requires 40 chances to reach the top of the pillars, what is the height of the shortest pillar?
There is an order of 19000 quantity of a particular product from a customer. The firm produces 1000 quantity of that product per out of which 5% are unfit for sale. In how many days will the order be completed?
Ram and Shyam work on a job together for four days and complete 60% of it. Ram takes leave then and Shyam works for eight more days to complete the job. How long would Ram take to complete the entire job alone?