This problem involves calculating the time it takes for person C to complete a job (laying railway track) alone, given the times taken by A, B, and A, B, C together.
We are given:
The core idea is to work with the 'rate' at which each person completes the job. The rate is the fraction of the job done per day. If someone takes 'x' days to complete a job, their rate is $\frac{1}{x}$ of the job per day.
First, let's determine the work rate for A and B:
When A, B, and C work together, they complete the job in 3 days. So, their combined work rate is:
To find C's contribution, we first need the combined rate of A and B working together.
Rate (A+B) = Rate of A + Rate of B
Rate (A+B) = $\frac{1}{16} + \frac{1}{11}$
To add these fractions, we find a common denominator, which is $16 \times 11 = 176$.
Rate (A+B) = $\frac{11}{176} + \frac{16}{176}$
Rate (A+B) = $\frac{11 + 16}{176} = \frac{27}{176}$ of the job per day.
Now, we can find C's individual work rate. The combined rate of A, B, and C is equal to the sum of their individual rates:
Rate (A+B+C) = Rate (A+B) + Rate (C)
We can rearrange this to find Rate (C):
Rate (C) = Rate (A+B+C) - Rate (A+B)
Rate (C) = $\frac{1}{3} - \frac{27}{176}$
To subtract these fractions, we find a common denominator, which is $3 \times 176 = 528$.
Rate (C) = $\frac{1 \times 176}{3 \times 176} - \frac{27 \times 3}{176 \times 3}$
Rate (C) = $\frac{176}{528} - \frac{81}{528}$
Rate (C) = $\frac{176 - 81}{528} = \frac{95}{528}$ of the job per day.
If C's work rate is $\frac{95}{528}$ of the job per day, then the total time C takes to complete the job alone is the reciprocal of this rate.
Time for C = $\frac{1}{\text{Rate of C}}$
Time for C = $\frac{1}{95/528}$
Time for C = $\frac{528}{95}$ days.
To express this as a mixed number:
Divide 528 by 95: $528 \div 95 = 5$ with a remainder of $53$ (since $95 \times 5 = 475$, and $528 - 475 = 53$).
Therefore, Time for C = $5\frac{53}{95}$ days.
A can lay railway track between two given stations in 17 days and B can do the same job in 16 days. With the help of C, they did the job in 4 days only. Then, C alone can do the job in __________