All Exams Test series for 1 year @ ₹349 only
Question

X can complete one-third of a certain work in 6 days, Y can complete one-third of the same work in 8 days and Z can complete three-fourth of the same work in 12 days. All of them work together for n days and then X and Z quit and Y alone finishes the remaining work in 82⁄3 days. What is n equal to?

The correct answer is

4

This problem involves calculating the time taken by individuals and a group to complete a certain amount of work. We are given the time taken by X, Y, and Z to complete a fraction of the work and the time taken by Y to complete the remaining work after X and Z leave. We need to find the number of days (n) all three worked together.

Calculating Individual Work Rates

First, let's determine the rate at which each person completes the total work per day. The rate is the reciprocal of the time taken to complete the entire work.

  • X's Work Rate: X completes $1/3$ of the work in 6 days. To complete the whole work (1 unit), X would take $6 \text{ days} \times 3 = 18$ days.

Therefore, X's daily work rate is $\frac{1}{18}$ of the total work.

  • Y's Work Rate: Y completes $1/3$ of the work in 8 days. To complete the whole work (1 unit), Y would take $8 \text{ days} \times 3 = 24$ days.

Therefore, Y's daily work rate is $\frac{1}{24}$ of the total work.

  • Z's Work Rate: Z completes $3/4$ of the work in 12 days. To complete the whole work (1 unit), Z would take $12 \text{ days} \times \frac{4}{3} = 4 \times 4 = 16$ days.

Therefore, Z's daily work rate is $\frac{1}{16}$ of the total work.

Combined Work Rate of X, Y, and Z

When X, Y, and Z work together, their daily work rates add up to find their combined daily work rate.

Combined rate = X's rate + Y's rate + Z's rate

Combined rate = $\frac{1}{18} + \frac{1}{24} + \frac{1}{16}$

To add these fractions, we find the least common multiple (LCM) of 18, 24, and 16.

  • 18 = $2 \times 3^2$
  • 24 = $2^3 \times 3$
  • 16 = $2^4$

LCM(18, 24, 16) = $2^4 \times 3^2 = 16 \times 9 = 144$.

Now, express each fraction with the denominator 144:

  • $\frac{1}{18} = \frac{1 \times 8}{18 \times 8} = \frac{8}{144}$
  • $\frac{1}{24} = \frac{1 \times 6}{24 \times 6} = \frac{6}{144}$
  • $\frac{1}{16} = \frac{1 \times 9}{16 \times 9} = \frac{9}{144}$

Combined rate = $\frac{8}{144} + \frac{6}{144} + \frac{9}{144} = \frac{8 + 6 + 9}{144} = \frac{23}{144}$ of the total work per day.

Work Done in Different Phases

The work is completed in two phases:

  1. X, Y, and Z work together for 'n' days.
  2. Y alone finishes the remaining work in $82/3$ days.

Work done by X, Y, and Z together:

In 'n' days, the work done by all three is their combined rate multiplied by the number of days.

Work done together = Combined rate $\times$ n

Work done together = $\frac{23}{144} \times n = \frac{23n}{144}$

Work done by Y alone:

Y works alone for $82/3$ days. Let's convert $82/3$ to an improper fraction: $82/3 = \frac{(8 \times 3) + 2}{3} = \frac{24 + 2}{3} = \frac{26}{3}$ days.

Work done by Y alone = Y's rate $\times$ time worked by Y alone

Work done by Y alone = $\frac{1}{24} \times \frac{26}{3} = \frac{26}{24 \times 3} = \frac{26}{72}$

This fraction can be simplified by dividing the numerator and denominator by 2:

Work done by Y alone = $\frac{13}{36}$

Setting Up and Solving the Equation

The total work done is the sum of the work done in the two phases, which must equal the total work (1 unit).

Work done together + Work done by Y alone = Total work

$\frac{23n}{144} + \frac{13}{36} = 1$

To solve for 'n', isolate the term with 'n':

$\frac{23n}{144} = 1 - \frac{13}{36}$

To subtract the fractions on the right side, find a common denominator, which is 36.

$1 = \frac{36}{36}$

$\frac{23n}{144} = \frac{36}{36} - \frac{13}{36} = \frac{36 - 13}{36} = \frac{23}{36}$

So, we have:

$\frac{23n}{144} = \frac{23}{36}$

To solve for 'n', we can multiply both sides by 144:

$23n = \frac{23}{36} \times 144$

$23n = 23 \times \frac{144}{36}$

Since $144 / 36 = 4$, the equation becomes:

$23n = 23 \times 4$

Divide both sides by 23:

$n = \frac{23 \times 4}{23}$

$n = 4$

Thus, X, Y, and Z worked together for 4 days.

Summary of Calculations

Person Fraction of work Time taken Time for whole work Daily Rate
X 1/3 6 days 18 days 1/18
Y 1/3 8 days 24 days 1/24
Z 3/4 12 days 16 days 1/16

Combined Daily Rate (X+Y+Z) = $\frac{1}{18} + \frac{1}{24} + \frac{1}{16} = \frac{8+6+9}{144} = \frac{23}{144}$

Let 'n' be the number of days X, Y, and Z worked together.

Work done by X, Y, Z in n days = $n \times \frac{23}{144} = \frac{23n}{144}$

Time Y worked alone = $82/3$ days = $26/3$ days

Work done by Y alone = $\frac{1}{24} \times \frac{26}{3} = \frac{13}{36}$

Total work = Work done together + Work done by Y alone = 1

$\frac{23n}{144} + \frac{13}{36} = 1$

$\frac{23n}{144} = 1 - \frac{13}{36} = \frac{36-13}{36} = \frac{23}{36}$

$23n = \frac{23}{36} \times 144$

$23n = 23 \times 4$

$n = 4$

Conclusion

Based on the calculations, the number of days 'n' that X, Y, and Z worked together is 4.

Revision Table: Work and Time Concepts

Concept Description Formula
Work Rate The amount of work done per unit of time. Rate = 1 / Time
Time Taken The total time required to complete the entire work. Time = 1 / Rate
Work Done Rate multiplied by the time worked. Work Done = Rate $\times$ Time
Combined Rate Sum of individual rates when multiple people work together. Rate$_{total}$ = Rate$_1$ + Rate$_2$ + ...
Total Work Usually considered as 1 unit when the entire work is completed. Sum of Work Done in all phases = 1

Additional Information on Work and Time Problems

Work and time problems often involve calculating how long it takes individuals or groups to complete tasks. The key is to convert the given information into daily (or hourly) work rates. If someone completes a fraction of work in a certain time, you can find the time taken for the whole work and thus their rate.

  • If a person can do a piece of work in 'd' days, their rate is $1/d$ work per day.
  • If multiple people work together, their rates are usually added.
  • The total work done is often treated as '1' unit. If only a fraction of the work is completed, that fraction is used.
  • Problems can involve phases where different people work or the group changes. Calculate the work done in each phase and sum them up to the total work.
  • Ensure units are consistent (e.g., days and work per day).

These problems are fundamentally about setting up equations based on the fraction of work done and the time taken, using the relationship: Work Done = Rate $\times$ Time.

Was this answer helpful?

Similar Questions

  1. Team X scored a total of N runs in 20 overs. Team Y tied the score in 10% less overs. Had Team Y’s average run rate (runs per over) been 50% higher, the scores would have been tied in 12 overs. How many runs were scored by Team X?

  2. P and Q walk along a circular track. They start at 5:00 a.m. from the same point in opposite directions. P walks at an average speed of 5 rounds per hour and Q walks at an average speed of 3 rounds per hour.
    How many times will they cross each other between 5:20 a.m. and 7:00 a.m.?

  3. A set (X) of 20 pipes can fill 70% of a tank in 14 minutes. Another set (Y) of 10 pipes fills 3/8 of the tank in 6 minutes. A third set (Z) of 16 pipes can empty half of the tank in 20 minutes. If half of the pipes of set X are closed and only half of the pipes of set Y are open, then how long will it take to fill 50% of the tank, if all pipes of set Z are open?

  4. The 5-digit number PQRST (all distinct digits) is such that T ≠ 0, P is thrice T. S is greater than Q by 4, while Q is greater than R by 3. How many such 5-digit numbers are possible?

  5. A question is given followed by two Statements I and II. Consider the Question and the Statements and mark the correct option.

    Question:
    What is the smallest 1-digit number having exactly 4 distinct factors?

    Statement I: 2 is one of the factors.
    Statement II: 3 is one of the factors.

    Which one of the following is correct in respect of the above Question and the Statements?

  6. Consider a set of 11 numbers:

    Value-I = Minimum value of the average of the numbers of the set when they are consecutive integers ≥ -5.
    Value-II = Minimum value of the product of the numbers of the set when they are consecutive non-negative integers.

    Which one of the following is correct?

  7. A 4-digit number N is such that when divided by 3, 5, 6, 9 leaves a remainder 1, 3, 4, 7 respectively. What is the smallest value of N?

  8. The average of three numbers p, q and r is k. p is as much more than the average as q is less than the average. What is the value of r?

  9. What is X in the sequence:
    24, X, 12, 18, 36, 90 ?

  10. If P = +, Q = −, R = ×, S = ÷, then insert the proper notations between the successive numbers in the equation:
    60_15_3_20_4 = 20


Important Questions from Miscellaneous Topics

  1. In communication the word 'Haptics' signifies :
  2. Which of the following statements best defines the scope of semiotics?
  3. The compound interest on Rs. 75,000 for three years, at successive interest rates of 4%, 6% and 9% for each year respectively is:

  4. The value of x in the following figures is :

  5. When a child reaches adolescence, there is apt to be a conflict between the parents and the child, since
    the latter considers himself to be by now quite capable of managing his own affairs, while the former
    are filled with parental solicitude, which is often a disguise for love of power. Parents consider, usually,
    that the various moral problems which arise in adolescence are peculiarly their province. The options
    they express, however, are so dogmatic that the young seldom confide in them, and usually go their
    own way in secret.

Need Expert Advice?
Upcoming Exams
UPSC IFoS
November 22, 2026
UPSC SO Steno
December 12, 2026
Test Series
IAS img
UPSC
UPSC CSE (IAS) 2027 Prelims Mock Test Series
666 Tests 3 Tests Free
2127 Attempts
4.8(218)
English, Hindi
More Questions from IAS

Start Your Preparation with Prepp Mobile App

Download the app from Google Play & App Store
Download the app from Google Play & App Store
Prepp Mobile App