X can complete one-third of a certain work in 6 days, Y can complete one-third of the same work in 8 days and Z can complete three-fourth of the same work in 12 days. All of them work together for n days and then X and Z quit and Y alone finishes the remaining work in 82⁄3 days. What is n equal to?
4
This problem involves calculating the time taken by individuals and a group to complete a certain amount of work. We are given the time taken by X, Y, and Z to complete a fraction of the work and the time taken by Y to complete the remaining work after X and Z leave. We need to find the number of days (n) all three worked together.
First, let's determine the rate at which each person completes the total work per day. The rate is the reciprocal of the time taken to complete the entire work.
Therefore, X's daily work rate is $\frac{1}{18}$ of the total work.
Therefore, Y's daily work rate is $\frac{1}{24}$ of the total work.
Therefore, Z's daily work rate is $\frac{1}{16}$ of the total work.
When X, Y, and Z work together, their daily work rates add up to find their combined daily work rate.
Combined rate = X's rate + Y's rate + Z's rate
Combined rate = $\frac{1}{18} + \frac{1}{24} + \frac{1}{16}$
To add these fractions, we find the least common multiple (LCM) of 18, 24, and 16.
LCM(18, 24, 16) = $2^4 \times 3^2 = 16 \times 9 = 144$.
Now, express each fraction with the denominator 144:
Combined rate = $\frac{8}{144} + \frac{6}{144} + \frac{9}{144} = \frac{8 + 6 + 9}{144} = \frac{23}{144}$ of the total work per day.
The work is completed in two phases:
In 'n' days, the work done by all three is their combined rate multiplied by the number of days.
Work done together = Combined rate $\times$ n
Work done together = $\frac{23}{144} \times n = \frac{23n}{144}$
Y works alone for $82/3$ days. Let's convert $82/3$ to an improper fraction: $82/3 = \frac{(8 \times 3) + 2}{3} = \frac{24 + 2}{3} = \frac{26}{3}$ days.
Work done by Y alone = Y's rate $\times$ time worked by Y alone
Work done by Y alone = $\frac{1}{24} \times \frac{26}{3} = \frac{26}{24 \times 3} = \frac{26}{72}$
This fraction can be simplified by dividing the numerator and denominator by 2:
Work done by Y alone = $\frac{13}{36}$
The total work done is the sum of the work done in the two phases, which must equal the total work (1 unit).
Work done together + Work done by Y alone = Total work
$\frac{23n}{144} + \frac{13}{36} = 1$
To solve for 'n', isolate the term with 'n':
$\frac{23n}{144} = 1 - \frac{13}{36}$
To subtract the fractions on the right side, find a common denominator, which is 36.
$1 = \frac{36}{36}$
$\frac{23n}{144} = \frac{36}{36} - \frac{13}{36} = \frac{36 - 13}{36} = \frac{23}{36}$
So, we have:
$\frac{23n}{144} = \frac{23}{36}$
To solve for 'n', we can multiply both sides by 144:
$23n = \frac{23}{36} \times 144$
$23n = 23 \times \frac{144}{36}$
Since $144 / 36 = 4$, the equation becomes:
$23n = 23 \times 4$
Divide both sides by 23:
$n = \frac{23 \times 4}{23}$
$n = 4$
Thus, X, Y, and Z worked together for 4 days.
| Person | Fraction of work | Time taken | Time for whole work | Daily Rate |
|---|---|---|---|---|
| X | 1/3 | 6 days | 18 days | 1/18 |
| Y | 1/3 | 8 days | 24 days | 1/24 |
| Z | 3/4 | 12 days | 16 days | 1/16 |
Combined Daily Rate (X+Y+Z) = $\frac{1}{18} + \frac{1}{24} + \frac{1}{16} = \frac{8+6+9}{144} = \frac{23}{144}$
Let 'n' be the number of days X, Y, and Z worked together.
Work done by X, Y, Z in n days = $n \times \frac{23}{144} = \frac{23n}{144}$
Time Y worked alone = $82/3$ days = $26/3$ days
Work done by Y alone = $\frac{1}{24} \times \frac{26}{3} = \frac{13}{36}$
Total work = Work done together + Work done by Y alone = 1
$\frac{23n}{144} + \frac{13}{36} = 1$
$\frac{23n}{144} = 1 - \frac{13}{36} = \frac{36-13}{36} = \frac{23}{36}$
$23n = \frac{23}{36} \times 144$
$23n = 23 \times 4$
$n = 4$
Based on the calculations, the number of days 'n' that X, Y, and Z worked together is 4.
| Concept | Description | Formula |
|---|---|---|
| Work Rate | The amount of work done per unit of time. | Rate = 1 / Time |
| Time Taken | The total time required to complete the entire work. | Time = 1 / Rate |
| Work Done | Rate multiplied by the time worked. | Work Done = Rate $\times$ Time |
| Combined Rate | Sum of individual rates when multiple people work together. | Rate$_{total}$ = Rate$_1$ + Rate$_2$ + ... |
| Total Work | Usually considered as 1 unit when the entire work is completed. | Sum of Work Done in all phases = 1 |
Work and time problems often involve calculating how long it takes individuals or groups to complete tasks. The key is to convert the given information into daily (or hourly) work rates. If someone completes a fraction of work in a certain time, you can find the time taken for the whole work and thus their rate.
These problems are fundamentally about setting up equations based on the fraction of work done and the time taken, using the relationship: Work Done = Rate $\times$ Time.
P and Q walk along a circular track. They start at 5:00 a.m. from the same point in opposite directions. P walks at an average speed of 5 rounds per hour and Q walks at an average speed of 3 rounds per hour.
How many times will they cross each other between 5:20 a.m. and 7:00 a.m.?
A set (X) of 20 pipes can fill 70% of a tank in 14 minutes. Another set (Y) of 10 pipes fills 3/8 of the tank in 6 minutes. A third set (Z) of 16 pipes can empty half of the tank in 20 minutes. If half of the pipes of set X are closed and only half of the pipes of set Y are open, then how long will it take to fill 50% of the tank, if all pipes of set Z are open?
The 5-digit number PQRST (all distinct digits) is such that T ≠ 0, P is thrice T. S is greater than Q by 4, while Q is greater than R by 3. How many such 5-digit numbers are possible?
Consider a set of 11 numbers:
Value-I = Minimum value of the average of the numbers of the set when they are consecutive integers ≥ -5.
Value-II = Minimum value of the product of the numbers of the set when they are consecutive non-negative integers.
Which one of the following is correct?
The average of three numbers p, q and r is k. p is as much more than the average as q is less than the average. What is the value of r?
What is X in the sequence:
24, X, 12, 18, 36, 90 ?
If P = +, Q = −, R = ×, S = ÷, then insert the proper notations between the successive numbers in the equation:
60_15_3_20_4 = 20
What is the remainder when 93 + 94 + 95 + 96 + ⋯ + 9100 is divided by 6?
Let x be a real number between 0 and 1.
Which of the following statements is/are correct?
I. x² > x³
II. x > √x
select the correct answer using the code given below:
With reference to the above passage, the following assumptions have been made:
I. There is no need for the State to be involved in any manner in the handloom sector.
II. Handloom products are no longer appealing and attractive in the rapidly changing modern world.
Which of the above assumptions is/are valid?
Consider the following figures :

Which of the following group(s) of figures fit/fits into the same class?
1. (1,7,8)
2. (4, 5, 6)
3. (2, 3, 9)
Select the correct answer using the code given below :