All Exams Test series for 1 year @ ₹349 only
Question

If A and B can finish a work in 10 days, B and C can finish the same work in 12 days, C and A can finish the same work in 15 days; then in how many days can A, B and C together finish half of the work?

The correct answer is

4 days

Solving Work and Time Problems with Multiple Workers

This problem involves calculating the time taken by A, B, and C to complete a certain amount of work, given the time it takes for them to complete the same work in pairs. These types of problems can be solved by determining the work rate of each individual or group per day.

Understanding Work Rate

Work rate is the amount of work done per unit of time. If someone can finish a whole work in 'd' days, their work rate per day is $\frac{1}{d}$ of the work.

Step-by-Step Solution

1. Calculate the Work Rate of Each Pair

We are given the time taken by pairs to finish the full work:

  • A and B together finish the work in 10 days.
  • B and C together finish the work in 12 days.
  • C and A together finish the work in 15 days.

From this, we can find their combined work rate per day:

  • Work done by (A + B) in 1 day = $\frac{1}{10}$ of the work.
  • Work done by (B + C) in 1 day = $\frac{1}{12}$ of the work.
  • Work done by (C + A) in 1 day = $\frac{1}{15}$ of the work.

2. Calculate the Combined Work Rate of A, B, and C Together

If we add the daily work rates of the three pairs, we get the combined rate of (A+B) + (B+C) + (C+A). Notice that each person's work rate (A, B, and C) is included twice in this sum:

Combined rate of (A+B) + (B+C) + (C+A) per day = $\frac{1}{10} + \frac{1}{12} + \frac{1}{15}$

To add these fractions, we find a common denominator. The least common multiple (LCM) of 10, 12, and 15 is 60.

Sum of daily rates = $\frac{6}{60} + \frac{5}{60} + \frac{4}{60} = \frac{6+5+4}{60} = \frac{15}{60}$

Simplifying the fraction: $\frac{15}{60} = \frac{1}{4}$

So, the combined work rate of (A + B + B + C + C + A), which is 2 times the work rate of (A + B + C), is $\frac{1}{4}$ of the work per day.

This means 2 $\times$ (Combined work rate of A, B, C) = $\frac{1}{4}$ of the work per day.

To find the combined work rate of A, B, and C together, we divide this sum by 2:

Combined work rate of (A + B + C) per day = $\frac{1}{4} \div 2 = \frac{1}{4} \times \frac{1}{2} = \frac{1}{8}$ of the work per day.

3. Calculate the Time Taken for A, B, and C to Finish the Full Work

If A, B, and C together can finish $\frac{1}{8}$ of the work in 1 day, they can finish the full work (which is 1) in the reciprocal of this rate.

Time taken by (A + B + C) to finish the full work = $\frac{1}{\text{Combined daily rate}}$

Time taken = $\frac{1}{1/8} = 1 \times 8 = 8$ days.

So, A, B, and C working together can finish the entire work in 8 days.

4. Calculate the Time Taken for A, B, and C to Finish Half of the Work

The question asks for the time taken to finish half of the work. Since they can finish the full work in 8 days, they will take half the time to finish half the work.

Time taken to finish half work = $\frac{1}{2} \times$ (Time taken for full work)

Time taken to finish half work = $\frac{1}{2} \times 8$ days = 4 days.

Thus, A, B, and C together can finish half of the work in 4 days.

Summary of Calculations

Group Time for Full Work Daily Work Rate (per day)
A + B 10 days $\frac{1}{10}$
B + C 12 days $\frac{1}{12}$
C + A 15 days $\frac{1}{15}$
(A+B) + (B+C) + (C+A) = 2(A+B+C) Not Applicable $\frac{1}{10} + \frac{1}{12} + \frac{1}{15} = \frac{15}{60} = \frac{1}{4}$
A + B + C 8 days $\frac{1}{4} \div 2 = \frac{1}{8}$

Time for A, B, C together to finish half work = Time for full work $\times \frac{1}{2} = 8 \times \frac{1}{2} = 4$ days.

The final answer is 4 days.

Revision Table: Work and Time Concepts

Concept Explanation Formula/Relation
Work Rate Amount of work done per unit of time (e.g., per day). Work Rate = $\frac{1}{\text{Time taken}}$
Time Taken Total time required to complete the work. Time Taken = $\frac{1}{\text{Work Rate}}$
Combined Work Rate Sum of individual work rates when people work together. Rate$_{\text{total}}$ = Rate$_1$ + Rate$_2$ + ...
Work Done Total amount of work completed. Can be fraction or a whole unit (1 for full work). Work Done = Work Rate $\times$ Time

Additional Information: Solving Paired Work Problems

Problems where people work in pairs (like A+B, B+C, C+A) are common in work and time topics. The key to solving these is to:

  • Calculate the daily work rate for each given pair.
  • Summing these rates gives you twice the combined rate of all individuals working together.
  • Divide the sum by two to get the combined daily rate of everyone together.
  • From the combined rate, you can find the time taken for everyone to finish the full work.
  • Adjust the time based on the fraction of work requested (e.g., half work, double work).
  • The LCM method for adding fractions representing work rates simplifies calculations significantly.

This approach helps break down complex problems into simpler, manageable steps based on daily work rates.

Was this answer helpful?

Important Questions from Time and Work

  1. A and B can do a piece of work in 18 days. B and C together can do it in 30 days. If A is twice as good a workman as C, find in how many days B alone can do the work?

  2. Two men and 7 women can complete a work in 28 days, whereas 6 men and 16 women can do the same work in 11 days. In how many days will 5 men and 4 women, working together, complete the same work?

  3. A man and a woman, working together can do a work in 66 days. The ratio of their working efficiencies is 3 ∶ 2. In how many days 6 men and 2 women together can do the same work?

  4. Each one of five men independently can complete a work in 20 days. The work is started by one person. Next day one more person joins and every next day one more person joins. From the fifth day, five persons continued working as a team. In how many days, will the work be completed?

  5. Numan does half the work as Gagan in 4/5 of the time. If together they take 16 days to complete a piece of work, then how long will it take Gagan to complete the work?

Need Expert Advice?

Start Your Preparation with Prepp Mobile App

Download the app from Google Play & App Store
Download the app from Google Play & App Store
Prepp Mobile App