If A and B can finish a work in 10 days, B and C can finish the same work in 12 days, C and A can finish the same work in 15 days; then in how many days can A, B and C together finish half of the work?
4 days
This problem involves calculating the time taken by A, B, and C to complete a certain amount of work, given the time it takes for them to complete the same work in pairs. These types of problems can be solved by determining the work rate of each individual or group per day.
Work rate is the amount of work done per unit of time. If someone can finish a whole work in 'd' days, their work rate per day is \(\frac{1}{d}\) of the work.
We are given the time taken by pairs to finish the full work:
From this, we can find their combined work rate per day:
If we add the daily work rates of the three pairs, we get the combined rate of (A+B) + (B+C) + (C+A). Notice that each person's work rate (A, B, and C) is included twice in this sum:
Combined rate of (A+B) + (B+C) + (C+A) per day = \(\frac{1}{10} + \frac{1}{12} + \frac{1}{15}\)
To add these fractions, we find a common denominator. The least common multiple (LCM) of 10, 12, and 15 is 60.
Sum of daily rates = \(\frac{6}{60} + \frac{5}{60} + \frac{4}{60} = \frac{6+5+4}{60} = \frac{15}{60}\)
Simplifying the fraction: \(\frac{15}{60} = \frac{1}{4}\)
So, the combined work rate of (A + B + B + C + C + A), which is 2 times the work rate of (A + B + C), is \(\frac{1}{4}\) of the work per day.
This means 2 \(\times\) (Combined work rate of A, B, C) = \(\frac{1}{4}\) of the work per day.
To find the combined work rate of A, B, and C together, we divide this sum by 2:
Combined work rate of (A + B + C) per day = \(\frac{1}{4} \div 2 = \frac{1}{4} \times \frac{1}{2} = \frac{1}{8}\) of the work per day.
If A, B, and C together can finish \(\frac{1}{8}\) of the work in 1 day, they can finish the full work (which is 1) in the reciprocal of this rate.
Time taken by (A + B + C) to finish the full work = \(\frac{1}{\text{Combined daily rate}}\)
Time taken = \(\frac{1}{1/8} = 1 \times 8 = 8\) days.
So, A, B, and C working together can finish the entire work in 8 days.
The question asks for the time taken to finish half of the work. Since they can finish the full work in 8 days, they will take half the time to finish half the work.
Time taken to finish half work = \(\frac{1}{2} \times\) (Time taken for full work)
Time taken to finish half work = \(\frac{1}{2} \times 8\) days = 4 days.
Thus, A, B, and C together can finish half of the work in 4 days.
| Group | Time for Full Work | Daily Work Rate (per day) |
|---|---|---|
| A + B | 10 days | \(\frac{1}{10}\) |
| B + C | 12 days | \(\frac{1}{12}\) |
| C + A | 15 days | \(\frac{1}{15}\) |
| (A+B) + (B+C) + (C+A) = 2(A+B+C) | Not Applicable | \(\frac{1}{10} + \frac{1}{12} + \frac{1}{15} = \frac{15}{60} = \frac{1}{4}\) |
| A + B + C | 8 days | \(\frac{1}{4} \div 2 = \frac{1}{8}\) |
Time for A, B, C together to finish half work = Time for full work \(\times \frac{1}{2} = 8 \times \frac{1}{2} = 4\) days.
The final answer is 4 days.
| Concept | Explanation | Formula/Relation |
|---|---|---|
| Work Rate | Amount of work done per unit of time (e.g., per day). | Work Rate = \(\frac{1}{\text{Time taken}}\) |
| Time Taken | Total time required to complete the work. | Time Taken = \(\frac{1}{\text{Work Rate}}\) |
| Combined Work Rate | Sum of individual work rates when people work together. | Rate\(_{\text{total}}\) = Rate\(_1\) + Rate\(_2\) + ... |
| Work Done | Total amount of work completed. Can be fraction or a whole unit (1 for full work). | Work Done = Work Rate \(\times\) Time |
Problems where people work in pairs (like A+B, B+C, C+A) are common in work and time topics. The key to solving these is to:
This approach helps break down complex problems into simpler, manageable steps based on daily work rates.
If x men working x hours per day can do x units of work in x days, then y men working y hours per day in y days would be able to do k units of work. What is the value of k?
A, B and C can complete a work in x, 1.5x and 2x days respectively. If they complete the work together, in what ratio should they be paid ?
X and Y can do a piece of work in 45 days and 40 days respectively. They begin to work together, but X leaves after n days and then Y completes the remaining work in 23 days. What is n equal to ?
Mohan can do a piece of work in 10 days and Sohan in 15 days. They started working together, but after 3 days Mohan left the work . What time will Sohan take to finish the work?
A tank is filled in 8 hours by three taps A, B and C. The tap C is thrice as fast as B and B is twice as fast as A. How much time will pipe B alone take to fill the tank?
Had been one menless, then the number of days required to do a piece of work would have been one more. If the number of Man. Days required to complete the work is 56, how many workers were there?
A can do a piece of work in 16 hours, B and C can do it in 8 hours while A and C can do it 12 hours. How long will B alone take to do it?