All Exams Test series for 1 year @ ₹349 only
Question

A pump can fill a tank in 4 hours, but due to a leak, the tank now gets filled in 5 hours. How long will it take the leakage to empty the tank when it is full?

This question was previously asked in
RRB ALP 2018 CBT 2 Fitter Question Paper (21-Jan-2019) (Shift 3)
The correct answer is

20 hours

Understanding Tank Filling and Emptying Problems

This problem involves calculating the time taken by a leak to empty a tank, given the time taken by a pump to fill it alone and the time taken by the pump to fill it when the leak is active. We can approach this by considering the rate at which work is done (filling or emptying the tank).

Calculating Individual Rates

Let the total capacity of the tank be 1 unit (representing a full tank). The rate of filling or emptying is the amount of tank filled or emptied per hour.

  • The pump can fill the tank in 4 hours. This means the pump fills $\frac{1}{4}$ of the tank per hour. We can call this the filling rate of the pump, $R_p$. So, $R_p = \frac{1}{4}$ tank/hour.
  • When the leak is present, the tank is filled in 5 hours. This means the net filling rate (pump filling minus leak emptying) is $\frac{1}{5}$ of the tank per hour. We can call the emptying rate of the leak $R_l$. The combined rate is $R_p - R_l$. So, $R_p - R_l = \frac{1}{5}$ tank/hour.

Finding the Leakage Rate

We know the pump's filling rate ($R_p = \frac{1}{4}$) and the combined rate ($R_p - R_l = \frac{1}{5}$). We can use these to find the leak's emptying rate ($R_l$).

Substitute the value of $R_p$ into the combined rate equation:

\( \frac{1}{4} - R_l = \frac{1}{5} \)

Now, we solve for $R_l$:

\( R_l = \frac{1}{4} - \frac{1}{5} \)

To subtract these fractions, we find a common denominator, which is 20:

\( R_l = \frac{1 \times 5}{4 \times 5} - \frac{1 \times 4}{5 \times 4} \)

\( R_l = \frac{5}{20} - \frac{4}{20} \)

\( R_l = \frac{5 - 4}{20} \)

\( R_l = \frac{1}{20} \)

The leak empties $\frac{1}{20}$ of the tank per hour. This is the emptying rate of the leak.

Calculating Time for Leak to Empty Tank

The time taken to empty the full tank by the leak alone is the reciprocal of its emptying rate.

Time = $\frac{\text{Total Capacity}}{\text{Rate}}$

Since the total capacity is 1 unit and the leak's rate is $R_l = \frac{1}{20}$, the time taken for the leak to empty the tank ($T_l$) is:

\( T_l = \frac{1}{R_l} = \frac{1}{\frac{1}{20}} \)

\( T_l = 1 \times 20 = 20 \)

So, it will take the leakage 20 hours to empty the tank when it is full.

Summary of Rates and Times

Entity Time to Fill/Empty Full Tank Rate (Fraction of Tank per Hour)
Pump (filling) 4 hours $\frac{1}{4}$
Pump + Leak (filling) 5 hours $\frac{1}{5}$ (Net Rate)
Leak (emptying) ? hours $\frac{1}{20}$

The leak alone empties the tank at a rate of $\frac{1}{20}$ tank per hour. Therefore, it will take 20 hours to empty the entire tank.

Revision Table: Tank and Leak Problems

Concept Formula/Idea Example
Rate Work Done / Time Taken If a pump fills a tank (1 unit of work) in 4 hours, its rate is $\frac{1}{4}$ tank/hour.
Time from Rate Work Done / Rate If a leak empties at $\frac{1}{20}$ tank/hour (rate), time to empty 1 tank is $1 / \frac{1}{20} = 20$ hours.
Combined Rate (Filling Pump & Emptying Leak) Rate of Pump - Rate of Leak Pump fills at $\frac{1}{4}$, leak empties at $\frac{1}{20}$. Net rate is $\frac{1}{4} - \frac{1}{20} = \frac{5}{20} - \frac{1}{20} = \frac{4}{20} = \frac{1}{5}$ tank/hour.

Additional Information: Working with Rates

Problems involving filling and emptying tanks (or pipes and cisterns) are often solved using the concept of work rates. The key idea is that if something completes a task (like filling a tank) in 'T' units of time, its rate of work is 1/T per unit of time.

  • If multiple agents (like pumps) work together to fill, their filling rates are added.
  • If some agents (like leaks) work to empty while others fill, the net rate is the sum of filling rates minus the sum of emptying rates.
  • If the net rate is positive, the tank fills. If it's negative, the tank empties.
  • The time taken to complete the task (filling or emptying the full tank) is 1 divided by the net rate.

Understanding rates helps simplify these types of problems by converting the time taken into work done per unit of time.

Was this answer helpful?

Similar Questions

  1. Mugdha and Mayuri, working together, can complete a job in 18 days. However, Mayuri works alone and leaves after completing two-fifths of the job and then Mugdha takes over and completes the remaining work by herself. As a result, the duo could complete the job in 39 days. How many days would Mugdha alone have taken to do the job if Mayuri worked faster than Mugdha?

  2. Pramod can paint a wall red in 12 hours while Brajen can paint the wall red completely in 16 hours. If Pramod and Brajen work alternately for an hour each stalling when the wall has just cement on it till when it is completely painted red, how many hours will it take to paint the entire wall red?

  3. Five men or ten women can complete a job in 20 days. In how many days can 3 men and 4 women complete it?

  4. A and B can do a work in 15 days. B and C can do the work in 20 days and A and C can do the work in 10 days. In how many days will they together completed the work?

  5. A can finish 25% of a task in 3 days and B can finish half of the task in 18 days. If they work on it together, in how many days can they finish the task?

  6. Working together, if A, B and C can finish a task in 4 days. However, after starting the task, B quits and A and C finish the remaining task in 6 days. How many days would B take to finish if he had to perform the task alone?

  7. In a computer game, a builder can build a wall in ten hours while a destroyer can demolish such a wall completely in fourteen hours. Both the builder and the destroyer were initially set to work together on the ground level, but, after 7 hours, the destroyer was taken out. What was the total time (in hours) taken to build the wall?

  8. Sharan and Mayukh, working together, can complete a task in 18 days. However, Mayukh works alone and leaves after completing one-third of the task. Then, Sharan takes over and completes the remaining work by himself. As a result, the duo could complete the task in 40 days. How many days would Sharan alone have taken to do the job if Mayukh had worked faster than Sharan?

  9. Surya works 3 times as fast as Ramya and is able to complete a piece of work in 40 days less than the number of days taken by Ramya. Find the time in which they can complete the work together.

  10. In a computer game, there are builders and destroyers. Together there are 20 of them. Some of them try to build a wall around a castle while the rest try to demolish it. Each of the builders can build the wall alone in 15 hours while any of the destroyers can demolish it in 10 hours. If all 20 builders and destroyers are made active when there is no wall and the wall get built in 3 hours, how many of them are destroyers?


Important Questions from Work Efficiency

  1. Five men and 2 boys can do in 30 days as much work as 7 men and 10 boys can do in 15 days. How many boys should join 40 men to do the same work in 4 days?

  2. A man completes 7/8 of a job in 21 days. How many more days will it take him to finish the job if quantum of work further increased by 50%?

  3. 24 men and 12 women can do a piece of work in 30 days. In how many days can 12 men and 24 women do the same piece of work?

  4. A and B together can do a piece of work in 4 days, B and C can do it in 6 days, A and C can do it in 8 days. Then A, B and C together can do the same work in :-

  5. A can complete 50% of a work in 9 days and B can do 25% of the work in 9 days, if they work alone. If they work together then how much work (in percentage) can be completed in 6 days?

Need Expert Advice?
Upcoming Exams
RRB Technician
October 06, 2026
RRB JE
October 27, 2026
RRB ALP
November 03, 2026
Test Series
RRB ALP img
Railways
RRB ALP 2026 Mock Test series
1035 Tests 1 Tests Free
1088 Attempts
4.3(239)
English, Hindi

Start Your Preparation with Prepp Mobile App

Download the app from Google Play & App Store
Download the app from Google Play & App Store
Prepp Mobile App