All Exams Test series for 1 year @ ₹349 only
Question

A pump can fill a tank in 4 hours, but due to a leak, the tank now gets filled in 5 hours. How long will it take the leakage to empty the tank when it is full?

This question was previously asked in
RRB ALP/Technician 2018 CBT 2 Electronics Mechanic Question Paper (23-Jan-2019) (Shift 1)
The correct answer is

20 hours

Understanding Tank Filling and Emptying Problems

This problem involves calculating the time taken by a leak to empty a tank, given the time taken by a pump to fill it alone and the time taken by the pump to fill it when the leak is active. We can approach this by considering the rate at which work is done (filling or emptying the tank).

Calculating Individual Rates

Let the total capacity of the tank be 1 unit (representing a full tank). The rate of filling or emptying is the amount of tank filled or emptied per hour.

  • The pump can fill the tank in 4 hours. This means the pump fills $\frac{1}{4}$ of the tank per hour. We can call this the filling rate of the pump, $R_p$. So, $R_p = \frac{1}{4}$ tank/hour.
  • When the leak is present, the tank is filled in 5 hours. This means the net filling rate (pump filling minus leak emptying) is $\frac{1}{5}$ of the tank per hour. We can call the emptying rate of the leak $R_l$. The combined rate is $R_p - R_l$. So, $R_p - R_l = \frac{1}{5}$ tank/hour.

Finding the Leakage Rate

We know the pump's filling rate ($R_p = \frac{1}{4}$) and the combined rate ($R_p - R_l = \frac{1}{5}$). We can use these to find the leak's emptying rate ($R_l$).

Substitute the value of $R_p$ into the combined rate equation:

\( \frac{1}{4} - R_l = \frac{1}{5} \)

Now, we solve for $R_l$:

\( R_l = \frac{1}{4} - \frac{1}{5} \)

To subtract these fractions, we find a common denominator, which is 20:

\( R_l = \frac{1 \times 5}{4 \times 5} - \frac{1 \times 4}{5 \times 4} \)

\( R_l = \frac{5}{20} - \frac{4}{20} \)

\( R_l = \frac{5 - 4}{20} \)

\( R_l = \frac{1}{20} \)

The leak empties $\frac{1}{20}$ of the tank per hour. This is the emptying rate of the leak.

Calculating Time for Leak to Empty Tank

The time taken to empty the full tank by the leak alone is the reciprocal of its emptying rate.

Time = $\frac{\text{Total Capacity}}{\text{Rate}}$

Since the total capacity is 1 unit and the leak's rate is $R_l = \frac{1}{20}$, the time taken for the leak to empty the tank ($T_l$) is:

\( T_l = \frac{1}{R_l} = \frac{1}{\frac{1}{20}} \)

\( T_l = 1 \times 20 = 20 \)

So, it will take the leakage 20 hours to empty the tank when it is full.

Summary of Rates and Times

Entity Time to Fill/Empty Full Tank Rate (Fraction of Tank per Hour)
Pump (filling) 4 hours $\frac{1}{4}$
Pump + Leak (filling) 5 hours $\frac{1}{5}$ (Net Rate)
Leak (emptying) ? hours $\frac{1}{20}$

The leak alone empties the tank at a rate of $\frac{1}{20}$ tank per hour. Therefore, it will take 20 hours to empty the entire tank.

Revision Table: Tank and Leak Problems

Concept Formula/Idea Example
Rate Work Done / Time Taken If a pump fills a tank (1 unit of work) in 4 hours, its rate is $\frac{1}{4}$ tank/hour.
Time from Rate Work Done / Rate If a leak empties at $\frac{1}{20}$ tank/hour (rate), time to empty 1 tank is $1 / \frac{1}{20} = 20$ hours.
Combined Rate (Filling Pump & Emptying Leak) Rate of Pump - Rate of Leak Pump fills at $\frac{1}{4}$, leak empties at $\frac{1}{20}$. Net rate is $\frac{1}{4} - \frac{1}{20} = \frac{5}{20} - \frac{1}{20} = \frac{4}{20} = \frac{1}{5}$ tank/hour.

Additional Information: Working with Rates

Problems involving filling and emptying tanks (or pipes and cisterns) are often solved using the concept of work rates. The key idea is that if something completes a task (like filling a tank) in 'T' units of time, its rate of work is 1/T per unit of time.

  • If multiple agents (like pumps) work together to fill, their filling rates are added.
  • If some agents (like leaks) work to empty while others fill, the net rate is the sum of filling rates minus the sum of emptying rates.
  • If the net rate is positive, the tank fills. If it's negative, the tank empties.
  • The time taken to complete the task (filling or emptying the full tank) is 1 divided by the net rate.

Understanding rates helps simplify these types of problems by converting the time taken into work done per unit of time.

Was this answer helpful?

Similar Questions

  1. 4 workers working 6 hours per day can finish painting a wall in 21 days. If 7 workers work for 4 hours per day, in how many days will they be able to finish the same work?

  2. A and B can complete a task together in 35 days. If A works alone and completes \(\frac{5}{7}\) of the task and then leaves the rest for B to complete by herself, it will take a total of 90 days to complete the task. How many days would it take A, the more efficient among the duo, to complete the entire work by herself?

  3. A and B can complete a piece of work in 10 days and 15 days respectively. B starts the work and is joined by A after 5 days. If they earn a total of Rs. 60, what are their individual shares?

  4. A and B together can do a piece of work in 10 days. If A can do the work in 15 days, find in how many days that B alone can do the same work. Given below are the steps involved in solving the above problem. Arrange them in sequential order.

    (A) One day’s work of B is 1/10 - 1/15

    (B) One day’s work of A and B is 1/10 and one day’s work of A is 1/15

    (C) B alone can do the work in 30 days

    (D) One day’s work of B is 1/30
  5. Mugdha and Mayuri, working together, can complete a job in 18 days. However, Mayuri works alone and leaves after completing two-fifths of the job and then Mugdha takes over and completes the remaining work by herself. As a result, the duo could complete the job in 39 days. How many days would Mugdha alone have taken to do the job if Mayuri worked faster than Mugdha?

  6. Pramod can paint a wall red in 12 hours while Brajen can paint the wall red completely in 16 hours. If Pramod and Brajen work alternately for an hour each stalling when the wall has just cement on it till when it is completely painted red, how many hours will it take to paint the entire wall red?

  7. Arjun and Anurag complete a job in 5 days and 6 days respectively. They worked together and earned a total of Rs. 770. Find Arjun’s share in this amount (in Rs.).

  8. A and B can complete a task in 10 days, B and C can complete it in 15 days while C and A can do the same task together in 12 days. How many days will they together take to complete the task?

  9. 10 people could complete a task in 8 days. After 4 days, 2 of the workers left. How many days from then did it take to complete the remaining task?

  10. Sharan and Mayukh, working together, can complete a task in 18 days. However, Mayukh works alone and leaves after completing one-third of the task. Then, Sharan takes over and completes the remaining work by himself. As a result, the duo could complete the task in 40 days. How many days would Sharan alone have taken to do the job if Mayukh had worked faster than Sharan?


Important Questions from Work Efficiency

  1. M is thrice as efficient as workman as N and therefore is able to finish a job in 264 days less than N. Then in how many days can N finish the entire work?
  2. A can do a piece of work in $1455$ days. B is $25\%$ more efficient than A. Find the number of days taken by B to do the same piece of work.
  3. 45 people take 18 days to dig a pond. If the pond would have to be dug in 15 days, then the number of people to be employed will be
  4. A stock of food is enough for 240 men for 48 days. How long will the same stock last for 160 men?
  5. One contractor had undertaken a construction work. To complete the given job, he sought labour comprising 24 men for 12 days for working 10 hours a day. But due to festival season, as the labour had gone to their respective hometowns, he could get only 15 men and they too were willing to work 8 hours a day. With this much labour, in how many days would he be able to complete the same job?

Need Expert Advice?
Upcoming Exams
RRB Staff Nurse
November 23, 2026
RRB Paramedical
November 23, 2026
Test Series
RRB ALP img
Railways
RRB ALP 2026 Mock Test series
1035 Tests 1 Tests Free
1801 Attempts
4.3(259)
English, Hindi

Start Your Preparation with Prepp Mobile App

Download the app from Google Play & App Store
Download the app from Google Play & App Store
Prepp Mobile App