All Exams Test series for 1 year @ ₹349 only
Question

A can finish 25% of a task in 3 days and B can finish half of the task in 18 days. If they work on it together, in how many days can they finish the task?

This question was previously asked in
RRB ALP 2018 CBT 2 Fitter Question Paper (21-Jan-2019) (Shift 3)
The correct answer is

9

Solving Work and Time Problems: A Step-by-Step Guide

This problem asks us to find the time it takes for two individuals, A and B, to complete a task when working together, given their individual rates of work. Work and time problems require us to first determine the efficiency or rate at which each person works individually.

Understanding Individual Work Rates

First, let's figure out how long each person takes to complete the entire task on their own.

  • A finishes 25% of the task in 3 days. Since 25% is equivalent to \(\frac{1}{4}\) of the task, A takes 4 times as long to complete the whole task.
  • Time taken by A to complete the whole task = \(3 \text{ days} \times 4 = 12 \text{ days}\).
  • B finishes half of the task in 18 days. Since half is 50% or \(\frac{1}{2}\) of the task, B takes 2 times as long to complete the whole task.
  • Time taken by B to complete the whole task = \(18 \text{ days} \times 2 = 36 \text{ days}\).

Calculating Daily Work Efficiency

Now that we know the total time each person takes, we can calculate the fraction of the task they complete in one day. This is their daily work rate or efficiency.

  • A's daily work rate = \(\frac{1}{\text{Time taken by A}} = \frac{1}{12}\) of the task per day.
  • B's daily work rate = \(\frac{1}{\text{Time taken by B}} = \frac{1}{36}\) of the task per day.

Calculating Combined Work Rate

When A and B work together, their work rates add up. To find their combined daily work rate, we sum their individual daily rates.

Combined daily work rate of A and B = A's daily rate + B's daily rate

Combined daily work rate = \(\frac{1}{12} + \frac{1}{36}\)

To add these fractions, we find a common denominator, which is 36.

\(\frac{1}{12} = \frac{1 \times 3}{12 \times 3} = \frac{3}{36}\)

Combined daily work rate = \(\frac{3}{36} + \frac{1}{36} = \frac{3 + 1}{36} = \frac{4}{36}\)

Simplifying the fraction:

Combined daily work rate = \(\frac{4}{36} = \frac{1}{9}\) of the task per day.

Time Taken to Finish the Task Together

If A and B together complete \(\frac{1}{9}\) of the task in one day, the total time taken to complete the entire task (which is 1 whole task) is the reciprocal of their combined daily work rate.

Time taken together = \(\frac{1}{\text{Combined daily work rate}}\)

Time taken together = \(\frac{1}{\frac{1}{9}} = 1 \times 9 = 9\) days.

Therefore, if A and B work on the task together, they can finish it in 9 days.

Individual Fraction of Task Done Time Taken Time for Full Task Daily Work Rate
A 25% or \(\frac{1}{4}\) 3 days \(3 \times 4 = 12\) days \(\frac{1}{12}\)
B 50% or \(\frac{1}{2}\) 18 days \(18 \times 2 = 36\) days \(\frac{1}{36}\)
A & B Together 1 (whole task) ? ? \(\frac{1}{12} + \frac{1}{36} = \frac{4}{36} = \frac{1}{9}\)

Revision Table: Key Concepts in Work and Time

Concept Explanation Formula
Work Rate The amount of work done per unit of time. Work Rate = \(\frac{\text{Work Done}}{\text{Time Taken}}\)
Time Taken The total duration to complete a specific amount of work. Time Taken = \(\frac{\text{Total Work}}{\text{Work Rate}}\)
Individual Time for Full Task If a fraction of work is done in 'x' days, the time for the full task is 'x' divided by the fraction. Time (Full Task) = \(\frac{\text{Time Taken for Fraction}}{\text{Fraction of Work Done}}\)
Combined Work Rate When multiple people work together, their individual work rates add up. Combined Rate = Rate\(_1\) + Rate\(_2\) + ...

Additional Information on Solving Work Problems

Work and time problems often involve calculating efficiency and combining efforts. A key idea is to consider the total work as '1 unit' or equivalent to the Least Common Multiple (LCM) of the individual times if dealing with discrete units.

  • Efficiency Method: Consider the total work as the LCM of the days taken by individuals. This helps avoid fractions. For example, LCM of 12 and 36 is 36. Assume total work is 36 units. A does 36/12 = 3 units/day. B does 36/36 = 1 unit/day. Together they do 3+1 = 4 units/day. Time taken together = Total work / Combined rate = 36 / 4 = 9 days. This method is useful for more complex problems.
  • Understanding Proportionality: Work is directly proportional to time and number of workers (assuming constant efficiency). If more people work, less time is needed. If efficiency increases, less time is needed.
  • Consistent Units: Always ensure the units of time (days, hours, minutes) are consistent throughout the problem calculation.
Was this answer helpful?

Similar Questions

  1. A pump can fill a tank in 4 hours, but due to a leak, the tank now gets filled in 5 hours. How long will it take the leakage to empty the tank when it is full?

  2. Mugdha and Mayuri, working together, can complete a job in 18 days. However, Mayuri works alone and leaves after completing two-fifths of the job and then Mugdha takes over and completes the remaining work by herself. As a result, the duo could complete the job in 39 days. How many days would Mugdha alone have taken to do the job if Mayuri worked faster than Mugdha?

  3. Pramod can paint a wall red in 12 hours while Brajen can paint the wall red completely in 16 hours. If Pramod and Brajen work alternately for an hour each stalling when the wall has just cement on it till when it is completely painted red, how many hours will it take to paint the entire wall red?

  4. Five men or ten women can complete a job in 20 days. In how many days can 3 men and 4 women complete it?

  5. A and B can do a work in 15 days. B and C can do the work in 20 days and A and C can do the work in 10 days. In how many days will they together completed the work?

  6. Working together, if A, B and C can finish a task in 4 days. However, after starting the task, B quits and A and C finish the remaining task in 6 days. How many days would B take to finish if he had to perform the task alone?

  7. In a computer game, a builder can build a wall in ten hours while a destroyer can demolish such a wall completely in fourteen hours. Both the builder and the destroyer were initially set to work together on the ground level, but, after 7 hours, the destroyer was taken out. What was the total time (in hours) taken to build the wall?

  8. Sharan and Mayukh, working together, can complete a task in 18 days. However, Mayukh works alone and leaves after completing one-third of the task. Then, Sharan takes over and completes the remaining work by himself. As a result, the duo could complete the task in 40 days. How many days would Sharan alone have taken to do the job if Mayukh had worked faster than Sharan?

  9. Surya works 3 times as fast as Ramya and is able to complete a piece of work in 40 days less than the number of days taken by Ramya. Find the time in which they can complete the work together.

  10. In a computer game, there are builders and destroyers. Together there are 20 of them. Some of them try to build a wall around a castle while the rest try to demolish it. Each of the builders can build the wall alone in 15 hours while any of the destroyers can demolish it in 10 hours. If all 20 builders and destroyers are made active when there is no wall and the wall get built in 3 hours, how many of them are destroyers?


Important Questions from Work Efficiency

  1. Five men and 2 boys can do in 30 days as much work as 7 men and 10 boys can do in 15 days. How many boys should join 40 men to do the same work in 4 days?

  2. A man completes 7/8 of a job in 21 days. How many more days will it take him to finish the job if quantum of work further increased by 50%?

  3. 24 men and 12 women can do a piece of work in 30 days. In how many days can 12 men and 24 women do the same piece of work?

  4. A and B together can do a piece of work in 4 days, B and C can do it in 6 days, A and C can do it in 8 days. Then A, B and C together can do the same work in :-

  5. A can complete 50% of a work in 9 days and B can do 25% of the work in 9 days, if they work alone. If they work together then how much work (in percentage) can be completed in 6 days?

Need Expert Advice?
Upcoming Exams
RRB Technician
October 06, 2026
RRB JE
October 27, 2026
RRB ALP
November 03, 2026
Test Series
RRB ALP img
Railways
RRB ALP 2026 Mock Test series
1035 Tests 1 Tests Free
1088 Attempts
4.3(239)
English, Hindi

Start Your Preparation with Prepp Mobile App

Download the app from Google Play & App Store
Download the app from Google Play & App Store
Prepp Mobile App