Pramod can paint a wall red in 12 hours while Brajen can paint the wall red completely in 16 hours. If Pramod and Brajen work alternately for an hour each stalling when the wall has just cement on it till when it is completely painted red, how many hours will it take to paint the entire wall red?
13 hours 40 minutes
This question asks us to determine the total time taken for two people, Pramod and Brajen, to paint a wall completely red when they work alternately for one hour each. We are given their individual times to paint the entire wall alone.
Problems involving alternate working require calculating the work done in a cycle (usually two turns, one for each person) and then figuring out how many cycles are needed to complete most of the work. The remaining work is then handled by the person whose turn it is.
First, let's find out how much of the wall each person can paint in one hour. This is their work rate.
Pramod and Brajen work alternately for one hour each. A complete cycle consists of Pramod working for 1 hour and then Brajen working for 1 hour, totaling 2 hours.
In the first hour (Pramod's turn), work done is $\(\frac{1}{12}\)$.
In the second hour (Brajen's turn), work done is $\(\frac{1}{16}\)$.
Total work done in one 2-hour cycle = Work by Pramod + Work by Brajen
Total work in 2 hours = $\(\frac{1}{12} + \frac{1}{16}\)$
To add these fractions, we find a common denominator, which is the least common multiple (LCM) of 12 and 16. The LCM of 12 and 16 is 48.
$\(\frac{1}{12} = \frac{1 \times 4}{12 \times 4} = \frac{4}{48}\)$
$\(\frac{1}{16} = \frac{1 \times 3}{16 \times 3} = \frac{3}{48}\)$
Total work in 2 hours = $\(\frac{4}{48} + \frac{3}{48} = \frac{7}{48}\)$
So, in every 2-hour cycle of alternate work, $\(\frac{7}{48}\)$ of the wall is painted.
The total work to be done is painting the entire wall, which we represent as 1 unit of work.
In each 2-hour cycle, $\(\frac{7}{48}\)$ of the work is done.
We need to find out how many cycles can be completed before the work is finished or almost finished. Let $N$ be the number of cycles.
Total work after $N$ cycles = $N \times \(\frac{7}{48}\)$
We want to find the largest whole number $N$ such that $N \times \(\frac{7}{48}\)$ is less than or equal to 1. More specifically, we want to see how many full $\(\frac{7}{48}\)$ units fit into 1.
Divide total work (1) by work per cycle ($\(\frac{7}{48}\)$): $\(\frac{1}{7/48} = \frac{48}{7} \approx 6.857\)$
This means they can complete 6 full cycles before the work is finished. After 6 cycles (which take $6 \times 2 = 12$ hours), the work done is:
Work done after 6 cycles = $6 \times \(\frac{7}{48}\) = \(\frac{42}{48} = \frac{7}{8}\)$ of the wall.
After 12 hours (6 cycles), $\(\frac{7}{8}\)$ of the wall is painted. The remaining work is:
Remaining work = Total work - Work done = $\(1 - \frac{7}{8} = \frac{1}{8}\)$ of the wall.
After 6 complete cycles, it is the beginning of the 13th hour, and it is Pramod's turn to paint.
Pramod's rate is $\(\frac{1}{12}\)$ of the wall per hour.
In the 13th hour, Pramod works for 1 full hour and paints $\(\frac{1}{12}\)$ of the wall.
Work done after 13 hours (12 hours in cycles + 1 hour by Pramod) = Work done after 6 cycles + Work done by Pramod
Work done after 13 hours = $\(\frac{7}{8} + \frac{1}{12}\)$
Again, find a common denominator for 8 and 12, which is 24.
$\(\frac{7}{8} = \frac{7 \times 3}{8 \times 3} = \frac{21}{24}\)$
$\(\frac{1}{12} = \frac{1 \times 2}{12 \times 2} = \frac{2}{24}\)$
Work done after 13 hours = $\(\frac{21}{24} + \frac{2}{24} = \frac{23}{24}\)$ of the wall.
The wall is not yet completely painted (it's $\(\frac{23}{24}\)$ done, less than 1). The remaining work is:
Remaining work = Total work - Work done = $\(1 - \frac{23}{24} = \frac{1}{24}\)$ of the wall.
It is now the beginning of the 14th hour, and it is Brajen's turn to paint the remaining $\(\frac{1}{24}\)$ of the wall.
Brajen's rate is $\(\frac{1}{16}\)$ of the wall per hour.
Time taken by Brajen to paint the remaining $\(\frac{1}{24}\)$ of the wall = $\(\frac{\text{Remaining Work}}{\text{Brajen's Rate}}\)$
Time taken by Brajen = $\(\frac{1/24}{1/16}\) = \(\frac{1}{24} \times \frac{16}{1}\) = \(\frac{16}{24}\)$ hours.
Simplify the fraction: $\(\frac{16}{24} = \frac{2 \times 8}{3 \times 8} = \frac{2}{3}\)$ hours.
The total time taken is the sum of the time for the full cycles, Pramod's hour, and Brajen's final time.
Total time = 12 hours (for 6 cycles) + 1 hour (Pramod's turn) + $\(\frac{2}{3}\)$ hours (Brajen's turn)
Total time = 13 hours + $\(\frac{2}{3}\)$ hours.
Convert the fraction of an hour into minutes: $\(\frac{2}{3}\)$ hours = $\(\frac{2}{3} \times 60\)$ minutes = $\(2 \times 20\)$ minutes = 40 minutes.
So, the total time taken to paint the entire wall red is 13 hours and 40 minutes.
| Step | Description | Calculation |
|---|---|---|
| 1 | Pramod's Rate (per hour) | $\(\frac{1}{12}\)$ |
| 2 | Brajen's Rate (per hour) | $\(\frac{1}{16}\)$ |
| 3 | Work in 1 Cycle (2 hours) | $\(\frac{1}{12} + \frac{1}{16} = \frac{7}{48}\)$ |
| 4 | Number of Full Cycles | $\(\lfloor \frac{1}{7/48} \rfloor = \lfloor \frac{48}{7} \rfloor = 6\)$ cycles |
| 5 | Time for Full Cycles | $\(6 \times 2 = 12\)$ hours |
| 6 | Work Done After 12 Hours | $\(6 \times \frac{7}{48} = \frac{42}{48} = \frac{7}{8}\)$ |
| 7 | Remaining Work | $\(1 - \frac{7}{8} = \frac{1}{8}\)$ |
| 8 | Work by Pramod (13th hour) | $\(\frac{1}{12}\)$ |
| 9 | Total Work After 13 Hours | $\(\frac{7}{8} + \frac{1}{12} = \frac{21}{24} + \frac{2}{24} = \frac{23}{24}\)$ |
| 10 | Remaining Work (After 13 hours) | $\(1 - \frac{23}{24} = \frac{1}{24}\)$ |
| 11 | Time for Brajen to finish ($\(\frac{1}{24}\)$ work) | $\(\frac{1/24}{1/16} = \frac{16}{24} = \frac{2}{3}\)$ hours |
| 12 | Convert to Minutes | $\(\frac{2}{3} \times 60 = 40\)$ minutes |
| 13 | Total Time | $\(12 \text{ hours} + 1 \text{ hour} + 40 \text{ minutes} = 13 \text{ hours } 40 \text{ minutes}\)$ |
Alternate work problems are common in time and work topics. The key is to calculate the work done in one full cycle involving all individuals working alternately. Then, determine how many full cycles are needed without exceeding the total work (1 unit).
A pump can fill a tank in 4 hours, but due to a leak, the tank now gets filled in 5 hours. How long will it take the leakage to empty the tank when it is full?
Mugdha and Mayuri, working together, can complete a job in 18 days. However, Mayuri works alone and leaves after completing two-fifths of the job and then Mugdha takes over and completes the remaining work by herself. As a result, the duo could complete the job in 39 days. How many days would Mugdha alone have taken to do the job if Mayuri worked faster than Mugdha?
Five men or ten women can complete a job in 20 days. In how many days can 3 men and 4 women complete it?
A and B can do a work in 15 days. B and C can do the work in 20 days and A and C can do the work in 10 days. In how many days will they together completed the work?
A can finish 25% of a task in 3 days and B can finish half of the task in 18 days. If they work on it together, in how many days can they finish the task?
Working together, if A, B and C can finish a task in 4 days. However, after starting the task, B quits and A and C finish the remaining task in 6 days. How many days would B take to finish if he had to perform the task alone?
In a computer game, a builder can build a wall in ten hours while a destroyer can demolish such a wall completely in fourteen hours. Both the builder and the destroyer were initially set to work together on the ground level, but, after 7 hours, the destroyer was taken out. What was the total time (in hours) taken to build the wall?
Sharan and Mayukh, working together, can complete a task in 18 days. However, Mayukh works alone and leaves after completing one-third of the task. Then, Sharan takes over and completes the remaining work by himself. As a result, the duo could complete the task in 40 days. How many days would Sharan alone have taken to do the job if Mayukh had worked faster than Sharan?
Surya works 3 times as fast as Ramya and is able to complete a piece of work in 40 days less than the number of days taken by Ramya. Find the time in which they can complete the work together.
In a computer game, there are builders and destroyers. Together there are 20 of them. Some of them try to build a wall around a castle while the rest try to demolish it. Each of the builders can build the wall alone in 15 hours while any of the destroyers can demolish it in 10 hours. If all 20 builders and destroyers are made active when there is no wall and the wall get built in 3 hours, how many of them are destroyers?
Five men and 2 boys can do in 30 days as much work as 7 men and 10 boys can do in 15 days. How many boys should join 40 men to do the same work in 4 days?
A man completes 7/8 of a job in 21 days. How many more days will it take him to finish the job if quantum of work further increased by 50%?
24 men and 12 women can do a piece of work in 30 days. In how many days can 12 men and 24 women do the same piece of work?
A and B together can do a piece of work in 4 days, B and C can do it in 6 days, A and C can do it in 8 days. Then A, B and C together can do the same work in :-
A can complete 50% of a work in 9 days and B can do 25% of the work in 9 days, if they work alone. If they work together then how much work (in percentage) can be completed in 6 days?