A and B can do a work in 15 days. B and C can do the work in 20 days and A and C can do the work in 10 days. In how many days will they together completed the work?
9.23 days
This question deals with the concept of time and work, specifically when the work rates of pairs of individuals are given, and we need to find the time taken by all three together.
Let's denote the amount of work A can do in one day as \(a\), the amount of work B can do in one day as \(b\), and the amount of work C can do in one day as \(c\). We can consider the total work to be completed as 1 unit.
We are given the time taken by pairs of individuals to complete the work:
To find the combined work rate of A, B, and C together (\(a+b+c\)), we can add the three equations we formulated:
\({(a + b) + (b + c) + (a + c) = \frac{1}{15} + \frac{1}{20} + \frac{1}{10}}\)
This simplifies to:
\({2a + 2b + 2c = \frac{1}{15} + \frac{1}{20} + \frac{1}{10}}\)
We can factor out 2 on the left side:
\({2(a + b + c) = \frac{1}{15} + \frac{1}{20} + \frac{1}{10}}\)
Now, we need to add the fractions on the right side. The least common multiple (LCM) of 15, 20, and 10 is 60.
\({2(a + b + c) = \frac{1 \times 4}{15 \times 4} + \frac{1 \times 3}{20 \times 3} + \frac{1 \times 6}{10 \times 6}}\)
\({2(a + b + c) = \frac{4}{60} + \frac{3}{60} + \frac{6}{60}}\)
\({2(a + b + c) = \frac{4 + 3 + 6}{60}}\)
\({2(a + b + c) = \frac{13}{60}}\)
Now, divide by 2 to find the combined work rate of A, B, and C:
\({a + b + c = \frac{13}{60 \times 2}}\)
\({a + b + c = \frac{13}{120}}\)
This means that A, B, and C together complete \(\frac{13}{120}\) of the total work in one day.
If A, B, and C together complete \(\frac{13}{120}\) of the work in one day, the total time taken to complete the entire work (1 unit) is the reciprocal of their combined work rate.
Time taken by A, B, and C together = \(\frac{1}{\text{Combined work rate}} = \frac{1}{\frac{13}{120}}\)
Time taken = \(\frac{120}{13}\) days.
Let's calculate the decimal value of \(\frac{120}{13}\):
\({120 \div 13 \approx 9.2307...}\)
Rounding to two decimal places, the time taken is approximately 9.23 days.
Let's look at the given options:
Our calculated time of approximately 9.23 days matches option 4.
| Pair | Time Taken (days) | Combined Work Rate (Work/day) |
|---|---|---|
| A & B | 15 | \(\frac{1}{15}\) |
| B & C | 20 | \(\frac{1}{20}\) |
| A & C | 10 | \(\frac{1}{10}\) |
| A, B & C (Together) | \(\frac{120}{13} \approx 9.23\) | \(\frac{13}{120}\) |
| Concept | Explanation | Formula/Relation |
|---|---|---|
| Work Rate | The amount of work done per unit of time (e.g., per day). | Work Rate = \(\frac{\text{Total Work}}{\text{Time Taken}}\) |
| Time Taken | The total time required to complete the work. | Time Taken = \(\frac{\text{Total Work}}{\text{Work Rate}}\) |
| Total Work | Often considered as 1 unit for calculation purposes. | Total Work = Work Rate \(\times\) Time Taken |
| Combined Work Rate | Sum of individual work rates when people work together. | Rate\(_{A+B}\) = Rate\(_A\) + Rate\(_B\) |
In this problem, we used a method of adding equations to find the combined work rate. Another way to approach problems like this, especially if individual rates (a, b, c) are needed, is to solve the system of linear equations:
You could use substitution or elimination methods. For example, subtract Equation 2 from Equation 1:
\({(a+b) - (b+c) = \frac{1}{15} - \frac{1}{20}}\)
\({a - c = \frac{4-3}{60} = \frac{1}{60}}\) (Equation 4)
Now add Equation 3 and Equation 4:
\({(a+c) + (a-c) = \frac{1}{10} + \frac{1}{60}}\)
\({2a = \frac{6+1}{60} = \frac{7}{60}}\)
\({a = \frac{7}{120}}\)
Once you have 'a', you can substitute it back into Equation 1 and Equation 3 to find 'b' and 'c'. Then you can sum a+b+c. This method also works and might be useful if the question asked for individual times.
A pump can fill a tank in 4 hours, but due to a leak, the tank now gets filled in 5 hours. How long will it take the leakage to empty the tank when it is full?
Mugdha and Mayuri, working together, can complete a job in 18 days. However, Mayuri works alone and leaves after completing two-fifths of the job and then Mugdha takes over and completes the remaining work by herself. As a result, the duo could complete the job in 39 days. How many days would Mugdha alone have taken to do the job if Mayuri worked faster than Mugdha?
Pramod can paint a wall red in 12 hours while Brajen can paint the wall red completely in 16 hours. If Pramod and Brajen work alternately for an hour each stalling when the wall has just cement on it till when it is completely painted red, how many hours will it take to paint the entire wall red?
Five men or ten women can complete a job in 20 days. In how many days can 3 men and 4 women complete it?
A can finish 25% of a task in 3 days and B can finish half of the task in 18 days. If they work on it together, in how many days can they finish the task?
Working together, if A, B and C can finish a task in 4 days. However, after starting the task, B quits and A and C finish the remaining task in 6 days. How many days would B take to finish if he had to perform the task alone?
In a computer game, a builder can build a wall in ten hours while a destroyer can demolish such a wall completely in fourteen hours. Both the builder and the destroyer were initially set to work together on the ground level, but, after 7 hours, the destroyer was taken out. What was the total time (in hours) taken to build the wall?
Sharan and Mayukh, working together, can complete a task in 18 days. However, Mayukh works alone and leaves after completing one-third of the task. Then, Sharan takes over and completes the remaining work by himself. As a result, the duo could complete the task in 40 days. How many days would Sharan alone have taken to do the job if Mayukh had worked faster than Sharan?
Surya works 3 times as fast as Ramya and is able to complete a piece of work in 40 days less than the number of days taken by Ramya. Find the time in which they can complete the work together.
In a computer game, there are builders and destroyers. Together there are 20 of them. Some of them try to build a wall around a castle while the rest try to demolish it. Each of the builders can build the wall alone in 15 hours while any of the destroyers can demolish it in 10 hours. If all 20 builders and destroyers are made active when there is no wall and the wall get built in 3 hours, how many of them are destroyers?
Five men and 2 boys can do in 30 days as much work as 7 men and 10 boys can do in 15 days. How many boys should join 40 men to do the same work in 4 days?
A man completes 7/8 of a job in 21 days. How many more days will it take him to finish the job if quantum of work further increased by 50%?
24 men and 12 women can do a piece of work in 30 days. In how many days can 12 men and 24 women do the same piece of work?
A and B together can do a piece of work in 4 days, B and C can do it in 6 days, A and C can do it in 8 days. Then A, B and C together can do the same work in :-
A can complete 50% of a work in 9 days and B can do 25% of the work in 9 days, if they work alone. If they work together then how much work (in percentage) can be completed in 6 days?