A and B can complete a piece of work in 10 days and 15 days respectively. B starts the work and is joined by A after 5 days. If they earn a total of Rs. 60, what are their individual shares?
Rs. 24, Rs. 36
This question asks us to determine the individual shares of earnings for two people, A and B, based on the amount of work they complete together. The key is to figure out how much work each person contributed and divide the total earnings in proportion to their contributions.
The work rate is the fraction of the total work that can be completed in one day.
B starts the work and works alone for the first 5 days.
Work done by B in 5 days = B's daily work rate $\times$ Number of days worked
Work done by B in 5 days = $\frac{1}{15} \times 5 = \frac{5}{15} = \frac{1}{3}$ of the total work.
After B works for 5 days, the remaining work is:
Remaining Work = Total Work $-$ Work done by B alone
Remaining Work = $1 - \frac{1}{3} = \frac{3}{3} - \frac{1}{3} = \frac{2}{3}$ of the total work.
After 5 days, A joins B. Now, they work together. Their combined daily work rate is the sum of their individual daily rates.
Combined daily work rate = A's daily rate + B's daily rate
Combined daily work rate = $\frac{1}{10} + \frac{1}{15}$
To add these fractions, we find a common denominator, which is 30.
Combined daily work rate = $\frac{1 \times 3}{10 \times 3} + \frac{1 \times 2}{15 \times 2} = \frac{3}{30} + \frac{2}{30} = \frac{5}{30} = \frac{1}{6}$ of the total work per day.
They work together to complete the remaining $\frac{2}{3}$ of the work.
Time taken together = Remaining Work $\div$ Combined daily work rate
Time taken together = $\frac{2}{3} \div \frac{1}{6} = \frac{2}{3} \times \frac{6}{1} = \frac{12}{3} = 4$ days.
So, A and B work together for 4 days.
Now we calculate the total amount of work each person did over the entire project duration they were involved.
Work done by A = A's daily rate $\times$ Days A worked
Work done by A = $\frac{1}{10} \times 4 = \frac{4}{10} = \frac{2}{5}$ of the total work.
Work done by B = B's daily rate $\times$ Days B worked
Work done by B = $\frac{1}{15} \times 9 = \frac{9}{15} = \frac{3}{5}$ of the total work.
Let's check: Total work done = Work by A + Work by B = $\frac{2}{5} + \frac{3}{5} = \frac{5}{5} = 1$. This confirms our calculations for the amount of work done are correct.
The earnings are shared in the ratio of the work done by each person.
Ratio of work done (A : B) = Work done by A : Work done by B
Ratio of work done (A : B) = $\frac{2}{5} : \frac{3}{5}$
We can multiply both sides by 5 to get a simpler ratio: $2 : 3$.
The ratio of earnings for A and B is $2 : 3$.
The total earnings are Rs. 60. The ratio of shares is $2 : 3$, with a total of $2 + 3 = 5$ parts.
A's share = $\frac{\text{A's ratio part}}{\text{Total ratio parts}} \times \text{Total Earnings}$
A's share = $\frac{2}{5} \times 60 = 2 \times 12 = 24$
A's share is Rs. 24.
B's share = $\frac{\text{B's ratio part}}{\text{Total ratio parts}} \times \text{Total Earnings}$
B's share = $\frac{3}{5} \times 60 = 3 \times 12 = 36$
B's share is Rs. 36.
The individual shares are Rs. 24 for A and Rs. 36 for B.
| Item | Value |
|---|---|
| A's Daily Rate | $\frac{1}{10}$ |
| B's Daily Rate | $\frac{1}{15}$ |
| Work by B in 5 days | $\frac{1}{3}$ |
| Remaining Work | $\frac{2}{3}$ |
| Combined Daily Rate (A+B) | $\frac{1}{6}$ |
| Days A & B work together | 4 days |
| Total Days B worked | 9 days |
| Total Days A worked | 4 days |
| Work done by A | $\frac{2}{5}$ |
| Work done by B | $\frac{3}{5}$ |
| Work Ratio (A : B) | 2 : 3 |
| Total Earnings | Rs. 60 |
| A's Share | Rs. 24 |
| B's Share | Rs. 36 |
| Concept | Explanation |
|---|---|
| Daily Work Rate | The amount of work done by a person in one day. If a person finishes work in 'n' days, their daily rate is $\frac{1}{n}$. |
| Work Done | Daily Rate $\times$ Number of Days Worked. |
| Combined Rate | Sum of individual daily rates when multiple people work together. |
| Sharing Earnings | When working together, earnings are typically shared in the ratio of the work completed by each individual. |
Work and Time problems often involve calculating how quickly individuals or groups can complete a task. Understanding individual work rates is fundamental. When people work together, their rates combine. If someone leaves or joins, you calculate the work done in phases. The principle of sharing wages in proportion to the work done is a common application of these concepts.
Other scenarios include:
Always ensure you calculate the exact fraction of work contributed by each person involved for the duration they worked.
4 workers working 6 hours per day can finish painting a wall in 21 days. If 7 workers work for 4 hours per day, in how many days will they be able to finish the same work?
A and B can complete a task together in 35 days. If A works alone and completes \(\frac{5}{7}\) of the task and then leaves the rest for B to complete by herself, it will take a total of 90 days to complete the task. How many days would it take A, the more efficient among the duo, to complete the entire work by herself?
A and B together can do a piece of work in 10 days. If A can do the work in 15 days, find in how many days that B alone can do the same work. Given below are the steps involved in solving the above problem. Arrange them in sequential order.
(A) One day’s work of B is 1/10 - 1/15
(B) One day’s work of A and B is 1/10 and one day’s work of A is 1/15
(C) B alone can do the work in 30 days
(D) One day’s work of B is 1/30A pump can fill a tank in 4 hours, but due to a leak, the tank now gets filled in 5 hours. How long will it take the leakage to empty the tank when it is full?
Mugdha and Mayuri, working together, can complete a job in 18 days. However, Mayuri works alone and leaves after completing two-fifths of the job and then Mugdha takes over and completes the remaining work by herself. As a result, the duo could complete the job in 39 days. How many days would Mugdha alone have taken to do the job if Mayuri worked faster than Mugdha?
Pramod can paint a wall red in 12 hours while Brajen can paint the wall red completely in 16 hours. If Pramod and Brajen work alternately for an hour each stalling when the wall has just cement on it till when it is completely painted red, how many hours will it take to paint the entire wall red?
Arjun and Anurag complete a job in 5 days and 6 days respectively. They worked together and earned a total of Rs. 770. Find Arjun’s share in this amount (in Rs.).
A and B can complete a task in 10 days, B and C can complete it in 15 days while C and A can do the same task together in 12 days. How many days will they together take to complete the task?
10 people could complete a task in 8 days. After 4 days, 2 of the workers left. How many days from then did it take to complete the remaining task?
Sharan and Mayukh, working together, can complete a task in 18 days. However, Mayukh works alone and leaves after completing one-third of the task. Then, Sharan takes over and completes the remaining work by himself. As a result, the duo could complete the task in 40 days. How many days would Sharan alone have taken to do the job if Mayukh had worked faster than Sharan?
One contractor had undertaken a construction work. To complete the given job, he sought labour comprising 24 men for 12 days for working 10 hours a day. But due to festival season, as the labour had gone to their respective hometowns, he could get only 15 men and they too were willing to work 8 hours a day. With this much labour, in how many days would he be able to complete the same job?