10 people could complete a task in 8 days. After 4 days, 2 of the workers left. How many days from then did it take to complete the remaining task?
5
10 people could complete a task in 8 days,
⇒ Total work = 80 units
After 4 days, 2 of the workers left,
⇒ Work done by 10 people in 4 days = 40
⇒ Remaining work = 40 and remaining people = 8
⇒ Days required = 40/8 = 5
∴ 5 days from then it takes to complete the task.4 workers working 6 hours per day can finish painting a wall in 21 days. If 7 workers work for 4 hours per day, in how many days will they be able to finish the same work?
A and B can complete a task together in 35 days. If A works alone and completes \(\frac{5}{7}\) of the task and then leaves the rest for B to complete by herself, it will take a total of 90 days to complete the task. How many days would it take A, the more efficient among the duo, to complete the entire work by herself?
A and B can complete a piece of work in 10 days and 15 days respectively. B starts the work and is joined by A after 5 days. If they earn a total of Rs. 60, what are their individual shares?
A and B together can do a piece of work in 10 days. If A can do the work in 15 days, find in how many days that B alone can do the same work. Given below are the steps involved in solving the above problem. Arrange them in sequential order.
(A) One day’s work of B is 1/10 - 1/15
(B) One day’s work of A and B is 1/10 and one day’s work of A is 1/15
(C) B alone can do the work in 30 days
(D) One day’s work of B is 1/30A pump can fill a tank in 4 hours, but due to a leak, the tank now gets filled in 5 hours. How long will it take the leakage to empty the tank when it is full?
Mugdha and Mayuri, working together, can complete a job in 18 days. However, Mayuri works alone and leaves after completing two-fifths of the job and then Mugdha takes over and completes the remaining work by herself. As a result, the duo could complete the job in 39 days. How many days would Mugdha alone have taken to do the job if Mayuri worked faster than Mugdha?
Pramod can paint a wall red in 12 hours while Brajen can paint the wall red completely in 16 hours. If Pramod and Brajen work alternately for an hour each stalling when the wall has just cement on it till when it is completely painted red, how many hours will it take to paint the entire wall red?
Arjun and Anurag complete a job in 5 days and 6 days respectively. They worked together and earned a total of Rs. 770. Find Arjun’s share in this amount (in Rs.).
A and B can complete a task in 10 days, B and C can complete it in 15 days while C and A can do the same task together in 12 days. How many days will they together take to complete the task?
Sharan and Mayukh, working together, can complete a task in 18 days. However, Mayukh works alone and leaves after completing one-third of the task. Then, Sharan takes over and completes the remaining work by himself. As a result, the duo could complete the task in 40 days. How many days would Sharan alone have taken to do the job if Mayukh had worked faster than Sharan?
One contractor had undertaken a construction work. To complete the given job, he sought labour comprising 24 men for 12 days for working 10 hours a day. But due to festival season, as the labour had gone to their respective hometowns, he could get only 15 men and they too were willing to work 8 hours a day. With this much labour, in how many days would he be able to complete the same job?