4 workers working 6 hours per day can finish painting a wall in 21 days. If 7 workers work for 4 hours per day, in how many days will they be able to finish the same work?
18
This question involves a classic work and time scenario where the total amount of work is constant. The work done is directly proportional to the number of workers, the hours they work per day, and the number of days they work.
We can establish a relationship based on the fact that the total work (painting the wall) is the same in both cases. The total work can be represented as the product of the number of workers, the hours worked per day, and the number of days. Let:
Since the total work (\(W\)) is constant, we can write: \(W = M \times H \times D \times \text{constant work rate per worker per hour}\). If we assume the constant work rate per worker per hour is uniform, we can simplify this relationship for the same amount of work (\(W_1 = W_2\)):
\(M_1 \times H_1 \times D_1 = M_2 \times H_2 \times D_2\)
We are given two scenarios:
Using the relationship \(M_1 \times H_1 \times D_1 = M_2 \times H_2 \times D_2\), we can substitute the given values:
\(4 \times 6 \times 21 = 7 \times 4 \times D_2\)
First, calculate the product on the left side:
\(4 \times 6 = 24\)
\(24 \times 21 = 504\)
So, the equation becomes:
\(504 = 7 \times 4 \times D_2\)
\(504 = 28 \times D_2\)
Now, to find \(D_2\), divide 504 by 28:
\(D_2 = \frac{504}{28}\)
Let's perform the division:
\(504 \div 28\)
We can simplify the fraction by dividing both numerator and denominator by common factors. For example, both are divisible by 4:
\(504 \div 4 = 126\)
\(28 \div 4 = 7\)
So, \(D_2 = \frac{126}{7}\)
Now divide 126 by 7:
\(126 \div 7 = 18\)
Thus, \(D_2 = 18\) days.
If 7 workers work for 4 hours per day, they will be able to finish the same work in 18 days.
| Scenario | Workers (\(M\)) | Hours/Day (\(H\)) | Days (\(D\)) | \(M \times H \times D\) |
|---|---|---|---|---|
| 1 | 4 | 6 | 21 | \(4 \times 6 \times 21 = 504\) |
| 2 | 7 | 4 | ? | \(7 \times 4 \times D_2 = 28 \times D_2\) |
Since the total work is constant:
\(504 = 28 \times D_2\)
\(D_2 = \frac{504}{28} = 18\)
| Concept | Description | Relationship |
|---|---|---|
| Work Done | The total task completed. | Proportional to (Workers) \(\times\) (Time) |
| Inverse Variation | When one quantity increases, another decreases proportionally, keeping their product constant (e.g., more workers, less time for the same work). | \(Q_1 \times Q_2 = \text{Constant}\) |
| Combined Variation | Work problems often involve multiple factors (workers, hours, days). | Work \(\propto\) Workers \(\times\) Hours/Day \(\times\) Days |
In work problems, the relationship between the number of workers and the time taken to complete a fixed amount of work is typically an inverse variation. This means if you increase the number of workers, the time required to finish the same job decreases, assuming each worker works at the same rate. Similarly, if workers work more hours per day, the total days needed to complete the job will decrease.
The formula \(M \times H \times D = \text{Constant}\) holds true when the total work is fixed and the efficiency of each worker is the same. This constant represents the total "worker-hours" or "worker-days" required to finish the job.
For instance, doubling the number of workers should theoretically halve the time required, assuming other factors like hours per day remain constant and there's no loss of efficiency due to coordination.
These types of problems are common in quantitative aptitude tests and require careful identification of the directly and inversely varying quantities.
A and B can complete a task together in 35 days. If A works alone and completes \(\frac{5}{7}\) of the task and then leaves the rest for B to complete by herself, it will take a total of 90 days to complete the task. How many days would it take A, the more efficient among the duo, to complete the entire work by herself?
A and B can complete a piece of work in 10 days and 15 days respectively. B starts the work and is joined by A after 5 days. If they earn a total of Rs. 60, what are their individual shares?
A and B together can do a piece of work in 10 days. If A can do the work in 15 days, find in how many days that B alone can do the same work. Given below are the steps involved in solving the above problem. Arrange them in sequential order.
(A) One day’s work of B is 1/10 - 1/15
(B) One day’s work of A and B is 1/10 and one day’s work of A is 1/15
(C) B alone can do the work in 30 days
(D) One day’s work of B is 1/30A pump can fill a tank in 4 hours, but due to a leak, the tank now gets filled in 5 hours. How long will it take the leakage to empty the tank when it is full?
Mugdha and Mayuri, working together, can complete a job in 18 days. However, Mayuri works alone and leaves after completing two-fifths of the job and then Mugdha takes over and completes the remaining work by herself. As a result, the duo could complete the job in 39 days. How many days would Mugdha alone have taken to do the job if Mayuri worked faster than Mugdha?
Pramod can paint a wall red in 12 hours while Brajen can paint the wall red completely in 16 hours. If Pramod and Brajen work alternately for an hour each stalling when the wall has just cement on it till when it is completely painted red, how many hours will it take to paint the entire wall red?
Arjun and Anurag complete a job in 5 days and 6 days respectively. They worked together and earned a total of Rs. 770. Find Arjun’s share in this amount (in Rs.).
A and B can complete a task in 10 days, B and C can complete it in 15 days while C and A can do the same task together in 12 days. How many days will they together take to complete the task?
10 people could complete a task in 8 days. After 4 days, 2 of the workers left. How many days from then did it take to complete the remaining task?
Sharan and Mayukh, working together, can complete a task in 18 days. However, Mayukh works alone and leaves after completing one-third of the task. Then, Sharan takes over and completes the remaining work by himself. As a result, the duo could complete the task in 40 days. How many days would Sharan alone have taken to do the job if Mayukh had worked faster than Sharan?
One contractor had undertaken a construction work. To complete the given job, he sought labour comprising 24 men for 12 days for working 10 hours a day. But due to festival season, as the labour had gone to their respective hometowns, he could get only 15 men and they too were willing to work 8 hours a day. With this much labour, in how many days would he be able to complete the same job?