Two inlet pipes can fill the tank in 15 hours and 18 hours and one outlet pipe can empty the tank in 20 hours. If all the pipes are opened simultaneously, then in how much time the tank will be filled completely?
180/13 hours
This problem involves calculating the time taken to fill a tank when multiple pipes with different rates (inlet and outlet) are operating simultaneously. We need to find the combined rate of filling and then determine the total time.
First, we determine the rate at which each pipe works. The rate is the fraction of the tank that can be filled or emptied in one hour.
When all pipes are opened together, the net rate of filling is the sum of the rates of the inlet pipes minus the rate of the outlet pipe.
Combined Rate = (Rate of Pipe 1) + (Rate of Pipe 2) - (Rate of Pipe 3)
Combined Rate = $\frac{1}{15} + \frac{1}{18} - \frac{1}{20}$ tank per hour.
To add and subtract these fractions, we need a common denominator. We find the LCM of 15, 18, and 20.
The LCM is the product of the highest powers of all prime factors involved: $2^2 \times 3^2 \times 5 = 4 \times 9 \times 5 = 180$.
Now we convert each fraction to have the denominator 180:
Substitute these values back into the combined rate equation:
Combined Rate = $\frac{12}{180} + \frac{10}{180} - \frac{9}{180}$
Combined Rate = $\frac{12 + 10 - 9}{180} = \frac{22 - 9}{180} = \frac{13}{180}$ tank per hour.
The time required to fill the tank is the reciprocal of the combined filling rate. This is because Time = Total Work / Rate, and here the Total Work is filling 1 tank.
Time = $\frac{1}{\text{Combined Rate}}$
Time = $\frac{1}{\frac{13}{180}}$ hours
Time = $\frac{180}{13}$ hours.
Therefore, if all the pipes are opened simultaneously, the tank will be filled completely in $\frac{180}{13}$ hours.
If X can do 1/4 of a work in 3 days and Y can do 1/6 of the same work in 4 days, how much will X get if both work together and are paid Rs. 1800 in all?
Mohan can do a piece of work in 10 days and Sohan in 15 days. They started working together, but after 3 days Mohan left the work . What time will Sohan take to finish the work?
A tank is filled in 8 hours by three taps A, B and C. The tap C is thrice as fast as B and B is twice as fast as A. How much time will pipe B alone take to fill the tank?
Had been one menless, then the number of days required to do a piece of work would have been one more. If the number of Man. Days required to complete the work is 56, how many workers were there?
A can do a piece of work in 16 hours, B and C can do it in 8 hours while A and C can do it 12 hours. How long will B alone take to do it?