Question

16 typists working 8 hours a day can type 172 pages in 6 days. How many typists will be required to type 215 pages in 4 days if they work 6 hours a day?

This question was previously asked in
RRB Group D 2025 Question Paper (9-Aug-2026) (Shift 1)
The correct answer is

40

Use the work formula \(\frac{M_{1}D_{1}H_{1}}{W_{1}}=\frac{M_{2}D_{2}H_{2}}{W_{2}}\).

Here M1 = 16, D1 = 6, H1 = 8, W1 = 172 and D2 = 4, H2 = 6, W2 = 215.

M2 = (16 × 6 × 8 × 215) ÷ (172 × 4 × 6) = 1,65,120 ÷ 4,128.

M2 = 40.

Hence, the answer is 40.

Was this answer helpful?

Similar Questions

  1. Mohan can complete a piece of work alone in 6 days by working 5 hours a day, and Rohan can do the same in 8 days. If they work together for 8 hours each day, how long will it take them to finish the work?

  2. Anshu can complete a piece of work in 16 days and Bijeta can complete the same work in 24 days. They work together for 6 days, after which Anshu leaves the work. In how many days will Bijeta complete the remaining work?

  3. If 8 painters can paint 18 rooms in 9 days, then how many rooms can 4 painters paint in 12 days?

  4. A can do a work in 10 days and B in 15 days. They work together for 3 days. How much work is left?

  5. If 8 workers can complete a task in 12 days, how many days will 6 workers take to complete the same task?

  6. In a class, Bhanu can do a piece of homework in 4 days, Jaya can do this work in 12 days, and Mounica can do the same work in 8 days. Working together, how many days will they take to complete the work?

  7. 5 men and 15 women can complete a task in 10 days, while 15 men and 5 women can complete it in 20 days. In how many days will 40 women complete the task?

  8. Riya can complete a piece of work in 15 days, while Neha can complete the same work in 20 days. If both of them work together, how many days will they take to complete the work?

  9. 12 men can finish a task in 20 days. How many days will 30 men take to complete the same task?

  10. Anshu can do a piece of work in 24 days, and Kajal can do it in 28 days. They work together for 6 days after which Anshu leaves the work, and the remaining work is completed by Kajal alone. In how many days will the entire work be completed?


Important Questions from Time and Work

  1. A works thrice as fast as B. If B can complete a work in 256 days independently, then find the number of days in which A and B can together
    finish the work.
  2. A can finish a job in 146 days, B can finish the same job in 219 days and C can finish the same job in 292 days. If all three are working together, how many days will they require to complete the same job?
  3. X can finish a work in 153 days, Y can finish a work in 255 and Z can finish the same piece of work 340 days. How many days will they require to complete the work, if X, Y and Z are working together?
  4. A finish a work in 1170 days and B can do the same work in 2340 days. Working together, they will complete the same work in how many days?
  5. A can finish a job in 102 days, B can finish the same job in 153 days and C can finish the same job in 204 days. If all three are working together, how many days will they require to complete the same job?
Need Expert Advice?
Upcoming Exams
RRB Staff Nurse
November 23, 2026
RRB Paramedical
November 23, 2026
Test Series
RRB Group D img
Railways
RRB Group D Mock Test Series 2026 (Latest Pattern)
1198 Tests 1 Tests Free
2016 Attempts
4.2(111)
English, Hindi
More Questions from RRB Group D

Start Your Preparation with Prepp Mobile App

Download the app from Google Play & App Store
Download the app from Google Play & App Store
Prepp Mobile App