5 men and 15 women can complete a task in 10 days, while 15 men and 5 women can complete it in 20 days. In how many days will 40 women complete the task?
4 days
Let one man do m units and one woman w units of work per day.
Total work = 10(5m + 15w) = 20(15m + 5w), so 50m + 150w = 300m + 100w, giving 50w = 250m and w = 5m.
Total work = 10(5m + 15 × 5m) = 800m, which in terms of women is 800m = 160w.
40 women need 160w ÷ 40w = 4 days.
Hence, the answer is 4 days.
Mohan can complete a piece of work alone in 6 days by working 5 hours a day, and Rohan can do the same in 8 days. If they work together for 8 hours each day, how long will it take them to finish the work?
Anshu can complete a piece of work in 16 days and Bijeta can complete the same work in 24 days. They work together for 6 days, after which Anshu leaves the work. In how many days will Bijeta complete the remaining work?
If 8 painters can paint 18 rooms in 9 days, then how many rooms can 4 painters paint in 12 days?
A can do a work in 10 days and B in 15 days. They work together for 3 days. How much work is left?
If 8 workers can complete a task in 12 days, how many days will 6 workers take to complete the same task?
In a class, Bhanu can do a piece of homework in 4 days, Jaya can do this work in 12 days, and Mounica can do the same work in 8 days. Working together, how many days will they take to complete the work?
16 typists working 8 hours a day can type 172 pages in 6 days. How many typists will be required to type 215 pages in 4 days if they work 6 hours a day?
Riya can complete a piece of work in 15 days, while Neha can complete the same work in 20 days. If both of them work together, how many days will they take to complete the work?
12 men can finish a task in 20 days. How many days will 30 men take to complete the same task?
Anshu can do a piece of work in 24 days, and Kajal can do it in 28 days. They work together for 6 days after which Anshu leaves the work, and the remaining work is completed by Kajal alone. In how many days will the entire work be completed?