5 men and 15 women can complete a task in 10 days, while 15 men and 5 women can complete it in 20 days. In how many days will 40 women complete the task?

This question was previously asked in
RRB Group D 2025 Question Paper (18-Aug-2026) (Shift 1)
The correct answer is

4 days

Let one man do m units and one woman w units of work per day.

Total work = 10(5m + 15w) = 20(15m + 5w), so 50m + 150w = 300m + 100w, giving 50w = 250m and w = 5m.

Total work = 10(5m + 15 × 5m) = 800m, which in terms of women is 800m = 160w.

40 women need 160w ÷ 40w = 4 days.

Hence, the answer is 4 days.

Was this answer helpful?

Similar Questions

  1. Mohan can complete a piece of work alone in 6 days by working 5 hours a day, and Rohan can do the same in 8 days. If they work together for 8 hours each day, how long will it take them to finish the work?

  2. 30 students can complete a task in 10 days working for 4 hours a day. In how many days will 80 students working 3 hours a day will complete the work?

  3. Anshu can complete a piece of work in 16 days and Bijeta can complete the same work in 24 days. They work together for 6 days, after which Anshu leaves the work. In how many days will Bijeta complete the remaining work?

  4. If 8 painters can paint 18 rooms in 9 days, then how many rooms can 4 painters paint in 12 days?

  5. A can do a work in 10 days and B in 15 days. They work together for 3 days. How much work is left?

  6. If 8 workers can complete a task in 12 days, how many days will 6 workers take to complete the same task?

  7. In a class, Bhanu can do a piece of homework in 4 days, Jaya can do this work in 12 days, and Mounica can do the same work in 8 days. Working together, how many days will they take to complete the work?

  8. 16 typists working 8 hours a day can type 172 pages in 6 days. How many typists will be required to type 215 pages in 4 days if they work 6 hours a day?

  9. A can complete a piece of work alone in 10 days, and B can complete it alone in 30 days. They work together for 6 days. Then A leaves, and B works alone for 4 more days. What fraction of the work still remains unfinished?

  10. Riya can complete a piece of work in 15 days, while Neha can complete the same work in 20 days. If both of them work together, how many days will they take to complete the work?


Important Questions from Time and Work

  1. Mohan can do a piece of work in 10 days and Sohan in 15 days. They started working together, but after 3 days Mohan left the work . What time will Sohan take to finish the work?

  2. A tank is filled in 8 hours by three taps A, B and C. The tap C is thrice as fast as B and B is twice as fast as A. How much time will pipe B alone take to fill the tank?

  3. Had been one menless, then the number of days required to do a piece of work would have been one more. If the number of Man. Days required to complete the work is 56, how many workers were there?

  4. A can do a piece of work in 16 hours, B and C can do it in 8 hours while A and C can do it 12 hours. How long will B alone take to do it?

  5. lf 12 men can do a work in 20 days, in how many days will the work be done by 15 men-
Need Expert Advice?
Upcoming Exams
RRB Technician
October 06, 2026
RRB JE
October 27, 2026
RRB ALP
November 03, 2026
Test Series
RRB Group D img
Railways
RRB Group D Mock Test Series 2026 (Latest Pattern)
1198 Tests 1 Tests Free
1751 Attempts
4.1(103)
English, Hindi
More Questions from RRB Group D

Start Your Preparation with Prepp Mobile App

Download the app from Google Play & App Store
Download the app from Google Play & App Store
Prepp Mobile App