10 persons begin to work together on a job but after some days 4 persons leave. As a result, the job which could have been completed in 40 days is completed in 50 days. How many days after the commencement of the work did the 4 persons leave?
25 days
Total work = 10 persons × 40 days = 400 person-days.
Let the 4 persons leave after x days. Then 10 persons work for x days and the remaining 6 persons work for (50 - x) days.
10x + 6(50 - x) = 400
10x + 300 - 6x = 400
4x = 100
x = 25
Check: 10 × 25 + 6 × 25 = 250 + 150 = 400 person-days.
Hence, 25 days.