Three workers, X, Y, and Z, can complete a certain job in 10 days, 12 days, and 15 days, respectively. Determine the number of days required for them to complete the job when they work together.
4 days
To determine the number of days required for workers X, Y, and Z to complete the job together, we use the concept of work and time, specifically the formula for combined work rate.
Step 1: Determine the work rate of each worker.
Step 2: Calculate the combined work rate.
The combined work rate when all workers work together is the sum of their individual work rates:
\(\frac{1}{10} + \frac{1}{12} + \frac{1}{15}\)
To add these fractions, we need a common denominator. The least common multiple of 10, 12, and 15 is 60.
Convert each work rate to have a denominator of 60:
Add these together:
\(\frac{6}{60} + \frac{5}{60} + \frac{4}{60} = \frac{15}{60} = \frac{1}{4}\)
Step 3: Calculate the time to complete the job together.
Since their combined work rate is \(\frac{1}{4}\), they can complete \(\frac{1}{4}\) of the job in one day. Therefore, they will complete 1 whole job in:
\(4 \text{ days}\)
Thus, the correct answer is 4 days.
Reena runs at a speed of 8 km/hr. How long will she take to cover 200 m?
A is thrice as good a workman as B and together they can finish a piece of work in 12 days. In how many days can A alone finish the work?
A can complete a piece of work in 18 days. B can complete it in 14 days. With the assistance of C, they completed the work in 7 days. C alone can complete it in_____________ days.
P is 30% more efficient than Q. How much time will they, working together, take to complete a job that P alone could have done in 23 days?
A can lay railway track between two given stations in 17 days and B can do the same job in 16 days. With the help of C, they did the job in 4 days only. Then, C alone can do the job in __________