Three workers, X, Y, and Z, can complete a certain job in 10 days, 12 days, and 15 days, respectively. Determine the number of days required for them to complete the job when they work together.
4 days
To determine the number of days required for workers X, Y, and Z to complete the job together, we use the concept of work and time, specifically the formula for combined work rate.
Step 1: Determine the work rate of each worker.
Step 2: Calculate the combined work rate.
The combined work rate when all workers work together is the sum of their individual work rates:
\(\frac{1}{10} + \frac{1}{12} + \frac{1}{15}\)
To add these fractions, we need a common denominator. The least common multiple of 10, 12, and 15 is 60.
Convert each work rate to have a denominator of 60:
Add these together:
\(\frac{6}{60} + \frac{5}{60} + \frac{4}{60} = \frac{15}{60} = \frac{1}{4}\)
Step 3: Calculate the time to complete the job together.
Since their combined work rate is \(\frac{1}{4}\), they can complete \(\frac{1}{4}\) of the job in one day. Therefore, they will complete 1 whole job in:
\(4 \text{ days}\)
Thus, the correct answer is 4 days.
If 5 workers, working at the same rate, complete a job in 12 days, how many days will 10
workers take to complete the same job?
In a circular race on a track of length 2000 m, X and Y start from the same point at the same time in opposite directions at the speeds of 15 km/h and 33 km/h, respectively. After how much time will they meet next?
Which of the following option figures will complete the pattern in the figure given below?

A has completed two-third of a job in 8 days, and B completes the rest of the job in 20 days. In how many days can they together complete the job?
The smallest 4-digit prime number is:
If Anand can do a piece of work in 9 days and Vinod can complete the same work in 6 days, then in how many days will both of them complete it together?