All Exams Test series for 1 year @ ₹349 only
Question

If 6 men and 8 boys can do a piece of work in 10 days, while 26 men and 48 boys can do the same work in 2 days, then the time taken by 10 men and 20 boys for doing the same piece of work will be:

This question was previously asked in
RRB NTPC 2024 Undergraduate CBT 1 Question Paper (29-Aug-2025) (Shift 1)
The correct answer is

5 days

Work and Time Problem Analysis

This question is about solving a classic work and time problem. It involves determining the time required for a specific group of workers (men and boys) to complete a task, given the time taken by different combinations of these workers. The core idea is to find the individual work rate of a man and a boy and then calculate their combined efficiency for the new group.

Mathematical Formulation of Work Rates

To solve this, we first assign variables to represent the work rate of each individual.

  • Let \(M\) denote the amount of work one man can complete in one day.
  • Let \(B\) denote the amount of work one boy can complete in one day.

We will assume the total piece of work to be completed is equivalent to 1 unit.

Deriving Equations from Given Information

Condition 1: 6 men and 8 boys can do the work in 10 days.

If 6 men and 8 boys complete the work in 10 days, their combined work rate per day is:

\( \text{Work Rate}_1 = \frac{\text{Total Work}}{\text{Time}} = \frac{1}{10} \)

This can be expressed in terms of \(M\) and \(B\) as:

\( 6M + 8B = \frac{1}{10} \quad (\text{Equation } 1) \)

Condition 2: 26 men and 48 boys can do the same work in 2 days.

Similarly, their combined work rate per day is:

\( \text{Work Rate}_2 = \frac{\text{Total Work}}{\text{Time}} = \frac{1}{2} \)

This gives us the second equation:

\( 26M + 48B = \frac{1}{2} \quad (\text{Equation } 2) \)

Solving the System of Equations for Individual Rates

We now have a system of two linear equations with two variables, \(M\) and \(B\):

  1. \(6M + 8B = \frac{1}{10}\)
  2. \(26M + 48B = \frac{1}{2}\)

We can use the method of elimination to solve for \(M\) and \(B\). Let's aim to eliminate \(B\). We can multiply Equation 1 by 6 to make the coefficient of \(B\) equal to 48, matching Equation 2.

Multiplying Equation 1 by 6:

\( 6 \times (6M + 8B) = 6 \times \frac{1}{10} \)

\( 36M + 48B = \frac{6}{10} = \frac{3}{5} \quad (\text{Equation } 3) \)

Now, subtract Equation 3 from Equation 2:

\( (26M + 48B) - (36M + 48B) = \frac{1}{2} - \frac{3}{5} \)

\( 26M - 36M = \frac{5}{10} - \frac{6}{10} \)

\( -10M = -\frac{1}{10} \)

Dividing both sides by -10:

\( M = \frac{-1/10}{-10} = \frac{1}{100} \)

So, one man completes \(\frac{1}{100}\) of the work in one day.

Now substitute the value of \(M\) back into Equation 1 to find the value of \(B\):

\( 6\left(\frac{1}{100}\right) + 8B = \frac{1}{10} \)

\( \frac{6}{100} + 8B = \frac{1}{10} \)

Isolate \(8B\):

\( 8B = \frac{1}{10} - \frac{6}{100} \)

Find a common denominator (100):

\( 8B = \frac{10}{100} - \frac{6}{100} \)

\( 8B = \frac{4}{100} \)

Solve for \(B\):

\( B = \frac{4}{100 \times 8} = \frac{4}{800} = \frac{1}{200} \)

Thus, one boy completes \(\frac{1}{200}\) of the work in one day.

Calculating the Combined Work Rate for the New Group

The question asks for the time taken by 10 men and 20 boys to complete the same work.

First, we calculate the combined work rate of this group in one day:

Work done by 10 men in 1 day = \(10 \times M = 10 \times \frac{1}{100} = \frac{10}{100} = \frac{1}{10}\)

Work done by 20 boys in 1 day = \(20 \times B = 20 \times \frac{1}{200} = \frac{20}{200} = \frac{1}{10}\)

The total work done by 10 men and 20 boys in one day is the sum of their individual contributions:

\( \text{Combined Rate} = (\text{Work by 10 men}) + (\text{Work by 20 boys}) \)

\( \text{Combined Rate} = \frac{1}{10} + \frac{1}{10} \)

\( \text{Combined Rate} = \frac{2}{10} = \frac{1}{5} \)

This signifies that 10 men and 20 boys together can complete \(\frac{1}{5}\) of the total work in a single day.

Final Time Calculation

The relationship between total work, work rate, and time is:

\( \text{Total Work} = \text{Combined Rate} \times \text{Time} \)

Since the total work is 1 unit, and the combined rate is \(\frac{1}{5}\) units per day, we can find the time:

\( 1 = \frac{1}{5} \times \text{Time} \)

To find the time, we rearrange the equation:

\( \text{Time} = \frac{1}{1/5} \)

\( \text{Time} = 5 \text{ days} \)

Therefore, it will take 10 men and 20 boys 5 days to complete the same piece of work.

Was this answer helpful?

Similar Questions

  1. P is 30% more efficient than Q. How much time will they, working together, take to complete a job that P alone could have done in 23 days?

  2. 8 men and 12 women can build a wall in 10 days. 6 men and 8 women can build the same wall in 14 days. How long will it take for 2 women and 1 man to build it together?

  3. 8 men and 12 women can build a wall in 10 days. 6 men and 8 women can build the same wall in 14 days. How long will it take for 1 woman to build it alone?

  4. Ravi and Kumar are working on an assignment. Ravi takes 6 hours to type 32 pages on a computer, while Kumar takes 5 hours to type 40 pages. How much time will they take, working together on two different computers to type an assignment of 110 pages?

  5. 8 men and 12 women can build a wall in 10 days. 6 men and 8 women can build the same wall in 14 days. How many more days will 1 woman take to build that wall alone compared to the number of days 1 man will take to build same wall alone?

  6. 48 men can do a work in 5 days while 40 women can do the same work in 9 days. In how many days can 4 men and 6 women together do the same work?

  7. If 6 men and 8 boys can do a piece of work in 10 days, while 26 men and 48 boys can do the same work in 2 days, then the time taken by 20 men to do the same piece of work is:

  8. A can complete a piece of work in 20 days and B can do the same work in 15 days. B worked alone for 6 days and left. In how many days can A complete the remaining work alone?

  9. A and B can together complete a piece of work in 5 days. They worked together for 4 days, and then B left. After another 2 days, A completed the remaining work. In how many days can A complete the entire work alone?

  10. 6 men or 5 women can complete a job in 7 days. 6 men work for 5 days and leave. The number of women required to complete the remaining work in 5 days is:


Important Questions from Time and work

  1. A person can complete 20% of work in 8 days and another person y can complete 25% of the same work in 6 days. If they work together, in how many days will 40% of the work be completed?

  2. P works thrice as fast as Q, whereas P and Q together can work four times as fast as R. If P, Q and R together work on a job, in what ratio should they share the earnings?

  3. There are three pillars X, Y and Z of different heights. Three spiders A, B and C start to climb on these pillars simultaneously. In one chance, A climbs on X by 6 cm but slips down 1 cm. B climbs on Y by 7 cm but slips down 3 cm. C climbs on Z by 6.5 cm but slips down 2 cm. If each of them requires 40 chances to reach the top of the pillars, what is the height of the shortest pillar?

  4. There is an order of 19000 quantity of a particular product from a customer. The firm produces 1000 quantity of that product per out of which 5% are unfit for sale. In how many days will the order be completed?

  5. Ram and Shyam work on a job together for four days and complete 60% of it. Ram takes leave then and Shyam works for eight more days to complete the job. How long would Ram take to complete the entire job alone?

Need Expert Advice?
Upcoming Exams
RRB Technician
October 06, 2026
RRB JE
October 27, 2026
RRB ALP
November 03, 2026
Test Series
RRB ALP img
Railways
RRB ALP 2026 Mock Test series
1035 Tests 1 Tests Free
1071 Attempts
4.3(238)
English, Hindi

Start Your Preparation with Prepp Mobile App

Download the app from Google Play & App Store
Download the app from Google Play & App Store
Prepp Mobile App