The ratio of the efficiencies of A, B and C is 7 ∶ 5 ∶ 4. Working together, they can finish a work in 35 days. A and B work together for 28 days. The remaining work will be completed (in days) by C alone∶

This question was previously asked in
SSC CGL 2018 (Tier 2) Statistics Previous Year Paper (22-feb-2018)
The correct answer is

56

Understanding Work, Efficiency, and Time

This problem involves the concepts of work, efficiency, and time. Efficiency is the rate at which work is done. If we know the efficiency and the time taken, we can find the total work. Similarly, if we know the total work and efficiency, we can find the time taken.

Analyzing the Efficiency Ratio

The problem states that the ratio of the efficiencies of A, B, and C is 7 ∶ 5 ∶ 4. This means that for every 7 units of work A does in a day, B does 5 units, and C does 4 units in a day. We can represent their efficiencies as:

  • Efficiency of A = 7 units/day
  • Efficiency of B = 5 units/day
  • Efficiency of C = 4 units/day

The combined efficiency of A, B, and C working together is the sum of their individual efficiencies.

\(\text{Combined efficiency of A, B, and C} = \text{Efficiency of A} + \text{Efficiency of B} + \text{Efficiency of C}\)

\(\text{Combined efficiency of A, B, and C} = 7 + 5 + 4 = 16 \text{ units/day}\)

Calculating Total Work

We are told that A, B, and C working together can finish the entire work in 35 days. Using the combined efficiency and the total time, we can calculate the total amount of work.

\(\text{Total Work} = \text{Combined Efficiency} \times \text{Time taken together}\)

\(\text{Total Work} = 16 \text{ units/day} \times 35 \text{ days} = 560 \text{ units}\)

So, the total work required to complete the job is 560 units.

Work Done by A and B

A and B work together for 28 days. First, let's find their combined efficiency.

\(\text{Combined efficiency of A and B} = \text{Efficiency of A} + \text{Efficiency of B}\)

\(\text{Combined efficiency of A and B} = 7 + 5 = 12 \text{ units/day}\)

Now, we can calculate the work done by A and B in 28 days.

\(\text{Work done by A and B} = \text{Combined efficiency of A and B} \times \text{Time A and B worked}\)

\(\text{Work done by A and B} = 12 \text{ units/day} \times 28 \text{ days}\)

12 \(\times\) 28
96 (12 \(\times\) 8)
+ 240 (12 \(\times\) 20)
--- ---
336

So, A and B together completed 336 units of work in 28 days.

Calculating Remaining Work

The total work is 560 units. A and B completed 336 units. The remaining work is the difference between the total work and the work done by A and B.

\(\text{Remaining Work} = \text{Total Work} - \text{Work done by A and B}\)

\(\text{Remaining Work} = 560 \text{ units} - 336 \text{ units}\)

\(\text{Remaining Work} = 224 \text{ units}\)

This remaining 224 units of work needs to be completed by C alone.

Time Taken by C to Complete Remaining Work

The efficiency of C is 4 units/day. To find the time taken by C to complete the remaining 224 units of work, we divide the remaining work by C's efficiency.

\(\text{Time taken by C} = \frac{\text{Remaining Work}}{\text{Efficiency of C}}\)

\(\text{Time taken by C} = \frac{224 \text{ units}}{4 \text{ units/day}}\)

56
\(4\) \( \overline{) \ 224} \)
\( -20 \)
\( \overline{\ \ 24} \)
\( \ -24 \)
\( \overline{\ \ \ 0} \)

\(\text{Time taken by C} = 56 \text{ days}\)

Therefore, C alone will complete the remaining work in 56 days.

Step-by-Step Solution Summary

  1. Determine the combined efficiency of A, B, and C from the given ratio (7:5:4). Combined efficiency = 7 + 5 + 4 = 16 units/day.
  2. Calculate the total work using the combined efficiency and the time taken by all three working together (35 days). Total work = 16 * 35 = 560 units.
  3. Determine the combined efficiency of A and B. Combined efficiency of A and B = 7 + 5 = 12 units/day.
  4. Calculate the work done by A and B in 28 days. Work done by A and B = 12 * 28 = 336 units.
  5. Calculate the remaining work by subtracting the work done by A and B from the total work. Remaining work = 560 - 336 = 224 units.
  6. Calculate the time taken by C to complete the remaining work using C's efficiency (4 units/day). Time taken by C = Remaining work / Efficiency of C = 224 / 4 = 56 days.

Revision Table: Key Concepts

Concept Formula/Calculation
Efficiency Ratio A:B:C 7:5:4
Combined Efficiency (A+B+C) \(7+5+4 = 16\) units/day
Total Work \(16 \text{ units/day} \times 35 \text{ days} = 560\) units
Combined Efficiency (A+B) \(7+5 = 12\) units/day
Work done by A & B in 28 days \(12 \text{ units/day} \times 28 \text{ days} = 336\) units
Remaining Work \(560 - 336 = 224\) units
Time taken by C (Remaining Work) \(224 \text{ units} / 4 \text{ units/day} = 56\) days

Additional Information on Work and Time Problems

Work and time problems often involve calculating the rate of work (efficiency) and using it to determine the time taken to complete a task. Here are some key points:

  • If a person can do a piece of work in 'd' days, their one day's work (efficiency) is \(1/d\).
  • If a person's one day's work is \(1/d\), they can complete the work in 'd' days.
  • If multiple people work together, their combined one day's work (combined efficiency) is the sum of their individual one day's work.
  • Total Work = Efficiency \(\times\) Time. This fundamental relationship is used to solve most problems.
  • When efficiency is given as a ratio, it is convenient to assume the efficiency values directly from the ratio (or multiply them by a common factor 'x') to calculate total work and work done.

Understanding the relationship between work, efficiency, and time is crucial for solving such problems efficiently.

Was this answer helpful?

Similar Questions

  1. A and Btogether can do a piece of work in 12 days. Aalone can do it in 18 days. In how many days can Balone can do the work?
  2. A can complete a certain piece of work in 40 days. B is 25% more efficient than A and C is 28% more efficient than B. They work together for 5 days. The remaining work will be complete by B alone, in:

  3. 45 men or 60 boys can do a piece of work in 20 days. How many days will 15 men and 20 boys take to complete the work?

  4. A, B and C can finish a job working alone in 20, 30 and 60 days respectively. They all work together for 1 day, then A and B quit. How many days C working alone will take to finish the remaining part of the job?

  5. A can do a piece of work in 6 days, B can do it in 9 days. With the assistance of C they completed the work in 3 days. In how many days can C alone do the work?

  6. A piece of work was finished by A, B and C together. A and B together finished 60% of the work and B and C together finished 70% of the work. Who among the three is most efficient?

  7. A, B and C can individually complete a task in 24 days, 20 days and 18 days, respectively. B and C start the task, and they work for 6 days and leave. The number of days required by A alone to finish the remaining task is:

  8. Amar can complete a work in 30 days and Raman can complete the same work in 15 days. If both of them work together, then in 4 days what percent of the total work will be completed?

  9. 3 men, 4 women and 6 boys together can complete a work in 6 days. A woman does triple the work a man does and a boy does half the work a man does. How many women alone will be able to complete this work in 4 days?

  10. A can paint a house in 42 days and B can do it in 21 days. Along with C, they can finish the job in 7 days only. C alone can do the painting job in how many days?


Important Questions from Work Efficiency

  1. M is thrice as efficient as workman as N and therefore is able to finish a job in 264 days less than N. Then in how many days can N finish the entire work?
  2. A can do a piece of work in $1455$ days. B is $25\%$ more efficient than A. Find the number of days taken by B to do the same piece of work.
  3. 45 people take 18 days to dig a pond. If the pond would have to be dug in 15 days, then the number of people to be employed will be
  4. A stock of food is enough for 240 men for 48 days. How long will the same stock last for 160 men?
  5. One contractor had undertaken a construction work. To complete the given job, he sought labour comprising 24 men for 12 days for working 10 hours a day. But due to festival season, as the labour had gone to their respective hometowns, he could get only 15 men and they too were willing to work 8 hours a day. With this much labour, in how many days would he be able to complete the same job?

Need Expert Advice?
Upcoming Exams
SSC CPO
November 23, 2026
SSC CHSL
November 30, 2026
SSC JE
November 30, 2026
Test Series
SSC CGL img
SSC
SSC CGL (Tier I + Tier II) 2026 Mock Test Series - Latest Pattern
2509 Tests 6 Tests Free
9153 Attempts
4.2(953)
English, Hindi
More Questions from SSC CGL

Start Your Preparation with Prepp Mobile App

Download the app from Google Play & App Store
Download the app from Google Play & App Store
Prepp Mobile App