A can do a piece of work in 6 days, B can do it in 9 days. With the assistance of C they completed the work in 3 days. In how many days can C alone do the work?
18
This question is about understanding how the work rate of individuals combines when they work together. We are given the time it takes for A and B to complete a task individually and the time it takes for A, B, and C to complete the task together. We need to find the time C takes to complete the task alone.
The key concept in solving work and time problems is the 'one day's work' or the work rate. If a person can complete a whole work in 'n' days, then in one day, they complete $\frac{1}{n}$ of the work.
Let's assume C takes $x$ days to complete the work alone. Therefore, C's one day's work is $\frac{1}{x}$ of the total work.
When A, B, and C work together, their combined one day's work is the sum of their individual one day's work. We can write this as an equation:
$$ \text{(A's one day's work)} + \text{(B's one day's work)} + \text{(C's one day's work)} = \text{(A, B, C's combined one day's work)} $$
Substituting the values we know:
$$ \frac{1}{6} + \frac{1}{9} + \frac{1}{x} = \frac{1}{3} $$
Now, we need to solve this equation for $x$. To do this, we first find a common denominator for the fractions. The least common multiple (LCM) of 6, 9, and 3 is 18.
Convert each fraction to have a denominator of 18:
Substitute these equivalent fractions back into the equation:
$$ \frac{3}{18} + \frac{2}{18} + \frac{1}{x} = \frac{6}{18} $$
Combine the fractions on the left side:
$$ \frac{3+2}{18} + \frac{1}{x} = \frac{6}{18} $$
$$ \frac{5}{18} + \frac{1}{x} = \frac{6}{18} $$
To isolate $\frac{1}{x}$, subtract $\frac{5}{18}$ from both sides of the equation:
$$ \frac{1}{x} = \frac{6}{18} - \frac{5}{18} $$
$$ \frac{1}{x} = \frac{6-5}{18} $$
$$ \frac{1}{x} = \frac{1}{18} $$
Since $\frac{1}{x}$ represents C's one day's work and it equals $\frac{1}{18}$, it means C takes 18 days to complete the entire work alone.
C alone can do the work in 18 days.
| Worker | Time to complete work (days) | One day's work (fraction) |
|---|---|---|
| A | 6 | $\frac{1}{6}$ |
| B | 9 | $\frac{1}{9}$ |
| A + B + C | 3 | $\frac{1}{3}$ |
| C | $x$ | $\frac{1}{x}$ |
| Concept | Explanation | Formula/Relation |
|---|---|---|
| Work Rate | The amount of work done per unit of time (e.g., per day). | Work Rate = $\frac{1}{\text{Time to complete work}}$ |
| Total Work | Usually considered as 1 unit or represented by the LCM of individual times. | Total Work = Work Rate $\times$ Time |
| Combined Work Rate | Sum of individual work rates when people work together. | $(\text{Rate}_1 + \text{Rate}_2 + ... + \text{Rate}_n) = \frac{1}{\text{Combined Time}}$ |
| Individual Time | Time taken by one person to complete the work alone. | Individual Time = $\frac{1}{\text{Individual Work Rate}}$ |
Work and time problems can also be approached using the concept of efficiency. Efficiency is often inversely proportional to the time taken to complete a task. If A is more efficient than B, A will take less time than B to complete the same task.
In this problem:
We can think of the total work as a certain number of units, for example, the LCM of the days taken by A, B, and (A+B+C), which is LCM(6, 9, 3) = 18 units of work.
Both the fractional method and the efficiency method give the same result, confirming our answer.
A can complete a certain piece of work in 40 days. B is 25% more efficient than A and C is 28% more efficient than B. They work together for 5 days. The remaining work will be complete by B alone, in:
45 men or 60 boys can do a piece of work in 20 days. How many days will 15 men and 20 boys take to complete the work?
A, B and C can finish a job working alone in 20, 30 and 60 days respectively. They all work together for 1 day, then A and B quit. How many days C working alone will take to finish the remaining part of the job?
A piece of work was finished by A, B and C together. A and B together finished 60% of the work and B and C together finished 70% of the work. Who among the three is most efficient?
A, B and C can individually complete a task in 24 days, 20 days and 18 days, respectively. B and C start the task, and they work for 6 days and leave. The number of days required by A alone to finish the remaining task is:
Amar can complete a work in 30 days and Raman can complete the same work in 15 days. If both of them work together, then in 4 days what percent of the total work will be completed?
The ratio of the efficiencies of A, B and C is 7 ∶ 5 ∶ 4. Working together, they can finish a work in 35 days. A and B work together for 28 days. The remaining work will be completed (in days) by C alone∶
3 men, 4 women and 6 boys together can complete a work in 6 days. A woman does triple the work a man does and a boy does half the work a man does. How many women alone will be able to complete this work in 4 days?
A can paint a house in 42 days and B can do it in 21 days. Along with C, they can finish the job in 7 days only. C alone can do the painting job in how many days?
One contractor had undertaken a construction work. To complete the given job, he sought labour comprising 24 men for 12 days for working 10 hours a day. But due to festival season, as the labour had gone to their respective hometowns, he could get only 15 men and they too were willing to work 8 hours a day. With this much labour, in how many days would he be able to complete the same job?