3 men, 4 women and 6 boys together can complete a work in 6 days. A woman does triple the work a man does and a boy does half the work a man does. How many women alone will be able to complete this work in 4 days?
9
Step 1 — Equivalent work units:
Take 1 man's daily work as \(M\). Then 1 woman = \(3M\) and 1 boy = \(\tfrac{M}{2}\).
Step 2 — Group rate per day:
\[3M+4(3M)+6\left(\tfrac{M}{2}\right)=3M+12M+3M=18M\]
Step 3 — Total work:
Total = \(18M\times 6=108M\) man-days.
Step 4 — Women needed in 4 days:
One woman does \(3M\) per day, so in 4 days she does \(12M\). Number of women = \(\dfrac{108M}{12M}=9\).
Therefore 9 women are required.
A can complete a certain piece of work in 40 days. B is 25% more efficient than A and C is 28% more efficient than B. They work together for 5 days. The remaining work will be complete by B alone, in:
45 men or 60 boys can do a piece of work in 20 days. How many days will 15 men and 20 boys take to complete the work?
A, B and C can finish a job working alone in 20, 30 and 60 days respectively. They all work together for 1 day, then A and B quit. How many days C working alone will take to finish the remaining part of the job?
A can do a piece of work in 6 days, B can do it in 9 days. With the assistance of C they completed the work in 3 days. In how many days can C alone do the work?
A piece of work was finished by A, B and C together. A and B together finished 60% of the work and B and C together finished 70% of the work. Who among the three is most efficient?
A, B and C can individually complete a task in 24 days, 20 days and 18 days, respectively. B and C start the task, and they work for 6 days and leave. The number of days required by A alone to finish the remaining task is:
Amar can complete a work in 30 days and Raman can complete the same work in 15 days. If both of them work together, then in 4 days what percent of the total work will be completed?
The ratio of the efficiencies of A, B and C is 7 ∶ 5 ∶ 4. Working together, they can finish a work in 35 days. A and B work together for 28 days. The remaining work will be completed (in days) by C alone∶
A can paint a house in 42 days and B can do it in 21 days. Along with C, they can finish the job in 7 days only. C alone can do the painting job in how many days?
One contractor had undertaken a construction work. To complete the given job, he sought labour comprising 24 men for 12 days for working 10 hours a day. But due to festival season, as the labour had gone to their respective hometowns, he could get only 15 men and they too were willing to work 8 hours a day. With this much labour, in how many days would he be able to complete the same job?