A can complete a certain piece of work in 40 days. B is 25% more efficient than A and C is 28% more efficient than B. They work together for 5 days. The remaining work will be complete by B alone, in:
This problem involves calculating the time taken to complete a piece of work based on individual efficiencies and combined work. We need to determine the work rate of each person (A, B, and C), calculate the work they complete together, find the remaining work, and finally calculate the time B takes to finish the rest alone.
Let's assume the total work is a specific amount. A completes the work in 40 days. A simple way to set up the problem is to consider the total work as 40 units. This makes A's daily work rate easy to calculate.
B is 25% more efficient than A. Efficiency is directly proportional to the work rate. So, B's daily work rate is 25% more than A's.
C is 28% more efficient than B. So, C's daily work rate is 28% more than B's.
Let's summarise the individual daily work rates:
| Person | Daily Work Rate (units/day) |
|---|---|
| A | 1.00 |
| B | 1.25 |
| C | 1.60 |
A, B, and C work together for 5 days. First, we find their combined daily work rate.
Now, calculate the total work done by them in 5 days:
The total work is 40 units. After A, B, and C work together for 5 days, 19.25 units of work are completed.
The remaining work needs to be completed by B alone. We know B's daily work rate is 1.25 units/day.
Let's perform the division:
\(\frac{20.75}{1.25} = \frac{2075}{125}\)
We can simplify this fraction:
\(\frac{2075}{125} = \frac{415}{25} \text{ (dividing numerator and denominator by 5)}\)
\(\frac{415}{25} = \frac{83}{5} \text{ (dividing numerator and denominator by 5)}\)
Now, convert the improper fraction \(\frac{83}{5}\) into a mixed number:
\(83 \div 5 = 16\) with a remainder of \(3\).
So, \(\frac{83}{5} = 16 \frac{3}{5}\) days.
Therefore, B alone will complete the remaining work in \(16\frac{3}{5}\) days.
| Step | Description | Calculation | Result |
|---|---|---|---|
| 1 | A's Daily Work Rate | \(40 \text{ units} / 40 \text{ days}\) | \(1 \text{ unit/day}\) |
| 2 | B's Daily Work Rate (25% more than A) | \(1 \times (1 + 0.25)\) | \(1.25 \text{ units/day}\) |
| 3 | C's Daily Work Rate (28% more than B) | \(1.25 \times (1 + 0.28)\) | \(1.60 \text{ units/day}\) |
| 4 | Combined Daily Work Rate (A+B+C) | \(1 + 1.25 + 1.60\) | \(3.85 \text{ units/day}\) |
| 5 | Work Done in 5 Days (A+B+C) | \(3.85 \times 5\) | \(19.25 \text{ units}\) |
| 6 | Remaining Work | \(40 - 19.25\) | \(20.75 \text{ units}\) |
| 7 | Time for B to finish Remaining Work | \(20.75 / 1.25\) | \(16 \frac{3}{5} \text{ days}\) |
Understanding the relationship between work, time, and efficiency is crucial for solving these types of problems. Here are some key concepts:
Problems often involve scenarios where people work together for a certain period, and then one or more leave, or new people join, requiring calculation of remaining work and time.
45 men or 60 boys can do a piece of work in 20 days. How many days will 15 men and 20 boys take to complete the work?
A, B and C can finish a job working alone in 20, 30 and 60 days respectively. They all work together for 1 day, then A and B quit. How many days C working alone will take to finish the remaining part of the job?
A can do a piece of work in 6 days, B can do it in 9 days. With the assistance of C they completed the work in 3 days. In how many days can C alone do the work?
A piece of work was finished by A, B and C together. A and B together finished 60% of the work and B and C together finished 70% of the work. Who among the three is most efficient?
A, B and C can individually complete a task in 24 days, 20 days and 18 days, respectively. B and C start the task, and they work for 6 days and leave. The number of days required by A alone to finish the remaining task is:
Amar can complete a work in 30 days and Raman can complete the same work in 15 days. If both of them work together, then in 4 days what percent of the total work will be completed?
The ratio of the efficiencies of A, B and C is 7 ∶ 5 ∶ 4. Working together, they can finish a work in 35 days. A and B work together for 28 days. The remaining work will be completed (in days) by C alone∶
3 men, 4 women and 6 boys together can complete a work in 6 days. A woman does triple the work a man does and a boy does half the work a man does. How many women alone will be able to complete this work in 4 days?
A can paint a house in 42 days and B can do it in 21 days. Along with C, they can finish the job in 7 days only. C alone can do the painting job in how many days?
One contractor had undertaken a construction work. To complete the given job, he sought labour comprising 24 men for 12 days for working 10 hours a day. But due to festival season, as the labour had gone to their respective hometowns, he could get only 15 men and they too were willing to work 8 hours a day. With this much labour, in how many days would he be able to complete the same job?