Question

Select the correct statement/s from the following:

Statement I: The slope of the NPV profile reflects how sensitive the project is to discount rate changes.

Statement II: To find total NPV of more than one projects, their NPV cannot be added.

Statement III: The certainty equivalent coefficient applies adjustments to both, the cash flows (in the numerator) and the discount factor (in the denominator).

Statement IV: The risk-adjusted discount factor applies adjustment for risk only to the discount factor (denominator).

Codes:

This question was previously asked in
UGC NET 2015 Paper 1 Question Paper (27-Dec-2015)
The correct answer is

Statements IV and I are correct

Each statement about NPV and risk adjustment must be judged separately.

Statement I is correct: the steeper the NPV profile (the graph of NPV against the discount rate), the more sharply NPV changes as the discount rate changes, so the slope reflects sensitivity to discount-rate changes.

Statement IV is correct: the risk-adjusted discount rate method adds a risk premium only to the discount rate in the denominator, leaving the cash flows unchanged.

Statement II is wrong: NPV is additive, so the NPVs of independent projects can be added. Statement III is wrong: the certainty-equivalent method adjusts only the cash flows in the numerator (by a certainty-equivalent coefficient), not the discount factor.

Hence Statements IV and I are correct.

Was this answer helpful?

Similar Questions

  1. A public works project is proposed that has total present-worth benefits of ₹ 75 million and total present-worth cost of ₹ 55 million. In deliberating this proposal, some members of the Municipal Board have suggested that the project has a total present-worth disbenefits of ₹ 15 million; other members feel that ₹ 15 million should be treated as a cost. What will be the benefit cost ratio and net benefits value while considering the disbenefits as a cost?

  2. Select the correct statement/s from the following :

    Statement I : The slope of the NPV profile reflects how sensitive the project is to discount rate changes.

    Statement II : To find total NPV of more than one projects, their NPV cannot be added.

    Statement III : The certainty equivalent coefficient applies adjustments to both, the cash flows (in the numerator) and the discount factor (in the denominator).

    Statement IV : The risk - adjusted discount factor applies adjustment for risk only to the discount factor (denominator).

    Codes :

  3. Indicate the correct code for the combination from the following regarding the superiority of the wealth maximisation over the profit maximisation objective of the financial management :

    (a) It takes into account long term stability and survival of the firm.

    (b) It takes care of all other objectives of the firm like exploring and expanding markets, etc.

    (c) It is based on the assumption of perfect competition in the market.

    (d) It considers risk alongwith returns.

    Code :

  4. Capital budgeting is concerned with :

  5. Which combination of the following statements about the net present value method of the investment project appraisal is correct ?

    (a) It considers all the cash flows from the project

    (b) It gives more weightage to distant flows than near-term flows

    (c) It considers the time value of money

    Code :

  6. In which of the following appraisal criteria of capital budgeting, the use of varying opportunity cost of capital as a discount factor is possible ?

    (a) NPV

    (b) IRR

    (c) Pay-back Period

    (d) ARR

  7. Statement – I : In general, the NPV and IRR methods lead to the same acceptance or rejection decision when a single project is involved.

    Statement – II : The inconsistency in ranking of competing projects as per the NPV and IRR methods lies in the implicit assumptions with regard to different rates of returns on re-investment of intermediate cash flows.

    Code :

  8. Under the Modified Accelerated Cost Recovery System (MACRS) an asset in the “5 year property class” would typically be depreciated over how many years ?

  9. In case the firm makes varying investments on the different investment projects, the appropriate project evaluation technique would be, which one of the following?

  10. A company issues 11% debentures of ₹ 100 each for an amount aggregating ₹ 2,00,000 at 10% premium, redeemable at par after 5 years. The company tax rate is 40%. The cost of debt is:


Important Questions from Capital Budgeting

  1. A firm is currently earning Rs. 50,000 and its one share has a present market value of Rs. 175. It has 5,000 shares outstanding. The earnings of the firm is expected to remain stable and it has a payout ratio of 100%. The cost of equity is:

  2. With project cost of ₹300 lacs, profits after depreciation (straight line method) and tax for its lifetime of 5 years are estimated at ₹10 lacs, ₹10 lacs, ₹30 lacs, ₹40 lacs and ₹50 lacs respectively. The cost of capital is 12% and discount factors @ 12%, for the first five years are 0.89, 0.80, 0.71, 0.64 and 0.57 respectively. The Net present value of project is :

  3. Match List I with List II

    LIST I

    (Investment Decision rule)

    LIST II

    (Feature)

    A.NPVI.Insufficiently consistent
    B.PaybackII.Highly Inflexible
    C.Cash ReturnsIII.Balance between flexibility and consistency
    D.Accounting ReturnsIV.Relatively consistent

    Choose the correct answer from the options given below:

  4. Which of the following are assumption of Net Operating Income Approach of Capital Structure?

    (A) There is no Corporate Tax

    (B) Cost of debt remain constant at all level

    (C) The Business risk remain constant every level of debt and equity mix

    (D) The cost of Debt is less than cost of equity

    (E) Overall cost of Capital remain constant

    Choose the correct answer from the options given below:

  5. Fixing the zero date is important step in establishing a project-

Need Expert Advice?
Upcoming Exams
MH SET
October 25, 2026
JTET
November 01, 2026
CTET
December 12, 2026
Test Series
UGC NET img
Teaching
UGC NET (Paper 2) 2026 Mock Test Series
796 Tests 2 Tests Free
4.4(36)
English
More Questions from UGC NET

Start Your Preparation with Prepp Mobile App

Download the app from Google Play & App Store
Download the app from Google Play & App Store
Prepp Mobile App