All Exams Test series for 1 year @ ₹349 only
Question

Assume B is social benefits, C is social costs, r is the social discount rate, t is the time and T is the life of the investment project. The Net Present Value (NPV) of a project is

The correct answer is
$NPV = \sum_{t=0}^{T} \frac{B_t - C_t}{(1 + r)^t}$

Net Present Value (NPV) Formula Explanation

The Net Present Value (NPV) is a fundamental concept in finance used to determine the profitability of an investment. It calculates the present value of future cash flows, considering the time value of money.

Understanding the Variables

  • Bt: Social Benefits at time t
  • Ct: Social Costs at time t
  • r: Social Discount Rate (reflects the opportunity cost of capital and risk)
  • t: Time period (usually in years)
  • T: Total life of the investment project

NPV Calculation

The NPV is the sum of the discounted net cash flows over the project's life. Net cash flow at time t is the difference between benefits and costs (Bt - Ct). Each period's net cash flow is discounted back to its present value using the formula PV = CashFlow / (1 + r)t.

Therefore, the formula for NPV is:

$NPV = \sum_{t=0}^{T} \frac{B_t - C_t}{(1 + r)^t}$

Analysis of Options

Based on the standard financial formula for NPV:

  • Option 1 correctly represents the NPV as the sum of discounted net benefits (Bt - Ct) over the project's lifetime (T), using the social discount rate (r).
  • Option 2 reverses the benefit and cost terms.
  • Option 3 incorrectly places the discount factor in the numerator and inverts the net benefit term.
  • Option 4 uses an incorrect discounting factor involving Ct.

Thus, the correct formula is the one presented in Option 1.

Was this answer helpful?

Important Questions from Capital Budgeting

  1. In certainty-equivalent approach, risk adjusted cash flows are discounted at
  2. Statement - I : In payback period method, the risk of the project is adjusted by lessening the target payback period.
    Statement - II : Sensitivity Analysis helps in calculation of net present value of the proposal.
    Code :
  3. Which one of the following equates the present value of cash out flows and the present value of expected cash inflows from a project ?
  4. A public works project is proposed that has total present-worth benefits of ₹ 75 million and total present-worth cost of ₹ 55 million. In deliberating this proposal, some members of the Municipal Board have suggested that the project has a total present-worth disbenefits of ₹ 15 million; other members feel that ₹ 15 million should be treated as a cost. What will be the benefit cost ratio and net benefits value while considering the disbenefits as a cost?

  5. Select the correct statement/s from the following :

    Statement I : The slope of the NPV profile reflects how sensitive the project is to discount rate changes.

    Statement II : To find total NPV of more than one projects, their NPV cannot be added.

    Statement III : The certainty equivalent coefficient applies adjustments to both, the cash flows (in the numerator) and the discount factor (in the denominator).

    Statement IV : The risk - adjusted discount factor applies adjustment for risk only to the discount factor (denominator).

    Codes :

Need Expert Advice?

Start Your Preparation with Prepp Mobile App

Download the app from Google Play & App Store
Download the app from Google Play & App Store
Prepp Mobile App