Question

In certainty-equivalent approach, risk adjusted cash flows are discounted at

The correct answer is
Risk-free Rate

Certainty-Equivalent Approach Discounting

The certainty-equivalent (CE) approach is a method used in finance to evaluate investment projects by adjusting for risk.

Risk Adjustment in CE Method

  • First, the expected future cash flows are adjusted to reflect their risk. This adjustment converts the uncertain, expected cash flows into a certainty-equivalent cash flow amount, representing the value of the risky cash flow if it were certain.
  • This conversion effectively incorporates the project's risk into the cash flow figure itself.

Discounting Rate

Because the risk has already been removed and accounted for in the cash flow adjustment step, the adjusted (certainty-equivalent) cash flows are discounted using a rate that reflects only the time value of money, without any additional risk premium.

  • This rate is the risk-free rate. It represents the return on an investment with virtually no risk, typically approximated by government bond yields.

Conclusion

Therefore, in the certainty-equivalent approach, risk-adjusted cash flows are discounted at the Risk-free Rate.

Was this answer helpful?

Important Questions from Capital Budgeting

  1. Assume B is social benefits, C is social costs, r is the social discount rate, t is the time and T is the life of the investment project. The Net Present Value (NPV) of a project is
  2. Statement - I : In payback period method, the risk of the project is adjusted by lessening the target payback period.
    Statement - II : Sensitivity Analysis helps in calculation of net present value of the proposal.
    Code :
  3. Which one of the following equates the present value of cash out flows and the present value of expected cash inflows from a project ?
  4. A public works project is proposed that has total present-worth benefits of ₹ 75 million and total present-worth cost of ₹ 55 million. In deliberating this proposal, some members of the Municipal Board have suggested that the project has a total present-worth disbenefits of ₹ 15 million; other members feel that ₹ 15 million should be treated as a cost. What will be the benefit cost ratio and net benefits value while considering the disbenefits as a cost?

  5. Select the correct statement/s from the following :

    Statement I : The slope of the NPV profile reflects how sensitive the project is to discount rate changes.

    Statement II : To find total NPV of more than one projects, their NPV cannot be added.

    Statement III : The certainty equivalent coefficient applies adjustments to both, the cash flows (in the numerator) and the discount factor (in the denominator).

    Statement IV : The risk - adjusted discount factor applies adjustment for risk only to the discount factor (denominator).

    Codes :