Certainty-Equivalent Approach Discounting
The certainty-equivalent (CE) approach is a method used in finance to evaluate investment projects by adjusting for risk.
Risk Adjustment in CE Method
- First, the expected future cash flows are adjusted to reflect their risk. This adjustment converts the uncertain, expected cash flows into a certainty-equivalent cash flow amount, representing the value of the risky cash flow if it were certain.
- This conversion effectively incorporates the project's risk into the cash flow figure itself.
Discounting Rate
Because the risk has already been removed and accounted for in the cash flow adjustment step, the adjusted (certainty-equivalent) cash flows are discounted using a rate that reflects only the time value of money, without any additional risk premium.
- This rate is the risk-free rate. It represents the return on an investment with virtually no risk, typically approximated by government bond yields.
Conclusion
Therefore, in the certainty-equivalent approach, risk-adjusted cash flows are discounted at the Risk-free Rate.