A can lay a railway track between two given stations in 7 days and B can do the same job in 63 days. With the help of C, they do the job in 6 days only. Then, C alone can do the job in:
126 days
Work rate is the reciprocal of the days taken. A completes \(\frac{1}{7}\) of the job in a day and B completes \(\frac{1}{63}\) of it in a day. All three together finish in 6 days, so their combined rate is \(\frac{1}{6}\).
\(\frac{1}{C} = \frac{1}{6} - \frac{1}{7} - \frac{1}{63}\). Taking the common denominator 126 gives \(\frac{21}{126} - \frac{18}{126} - \frac{2}{126} = \frac{1}{126}\).
So C completes \(\frac{1}{126}\) of the job daily and needs 126 days alone.
Check: in one day the three together do \(\frac{18}{126} + \frac{2}{126} + \frac{1}{126} = \frac{21}{126} = \frac{1}{6}\), which matches 6 days.
Hence, 126 days.
Reena runs at a speed of 8 km/hr. How long will she take to cover 200 m?
A is thrice as good a workman as B and together they can finish a piece of work in 12 days. In how many days can A alone finish the work?
A can complete a piece of work in 18 days. B can complete it in 14 days. With the assistance of C, they completed the work in 7 days. C alone can complete it in_____________ days.
P is 30% more efficient than Q. How much time will they, working together, take to complete a job that P alone could have done in 23 days?
A can lay railway track between two given stations in 17 days and B can do the same job in 16 days. With the help of C, they did the job in 4 days only. Then, C alone can do the job in __________