A can complete a piece of work in 18 days. B can complete it in 14 days. With the assistance of C, they completed the work in 7 days. C alone can complete it in_____________ days.
63
To find how many days C alone can complete the work, we begin by finding the work rates of A and B. A can complete the work in 18 days, so A's rate is 1/18 work per day. B can complete the work in 14 days, so B's rate is 1/14 work per day. Working together, A, B, and C complete the work in 7 days, meaning their combined rate is 1/7 work per day.
Let C's work rate be 1/x work per day. The combined work rate of A, B, and C is the sum of their individual work rates:
To find 1/x, subtract the work rates of A and B from the combined rate:
Calculate each fraction to have a common denominator:
Substitute these values back into the equation and simplify:
Simplify the fraction:
Solve for x:
Thus, C alone can complete the work in 63 days.
Reena runs at a speed of 8 km/hr. How long will she take to cover 200 m?
A is thrice as good a workman as B and together they can finish a piece of work in 12 days. In how many days can A alone finish the work?
P is 30% more efficient than Q. How much time will they, working together, take to complete a job that P alone could have done in 23 days?
8 men and 12 women can build a wall in 10 days. 6 men and 8 women can build the same wall in 14 days. How long will it take for 2 women and 1 man to build it together?
A can lay railway track between two given stations in 17 days and B can do the same job in 16 days. With the help of C, they did the job in 4 days only. Then, C alone can do the job in __________