All Exams Test series for 1 year @ ₹349 only
Question

A piece of work can be done by 16 men in 8 days working 12 hours a day. How many men are needed to complete another work, which is three times the first one, in 24 days working 8 hours a day?

This question was previously asked in
RRB ALP/Technician 2018 CBT 2 Electronics Mechanic Question Paper (23-Jan-2019) (Shift 1)
The correct answer is
24 men

This problem involves calculating the number of men required for a task based on given work rates (men, days, hours) and a change in the amount of work.

Men and Work Calculation

The total amount of work done is directly proportional to the number of men, the number of days they work, and the number of hours they work per day. This relationship can be expressed using the formula:

$ \frac{W_1}{M_1 \times D_1 \times H_1} = \frac{W_2}{M_2 \times D_2 \times H_2} $

Where:

  • $ W $ = Amount of Work
  • $ M $ = Number of Men
  • $ D $ = Number of Days
  • $ H $ = Hours worked per day
  • Subscript 1 refers to the initial scenario, and subscript 2 refers to the target scenario.

Initial Work Scenario

We are given the details for the first piece of work:

  • Number of men ($ M_1 $): 16
  • Number of days ($ D_1 $): 8
  • Hours per day ($ H_1 $): 12
  • Amount of work ($ W_1 $): Let's denote this as $ W_1 $.

Target Work Scenario

For the second, larger piece of work, we have:

  • Amount of work ($ W_2 $): Three times the first work, so $ W_2 = 3 \times W_1 $.
  • Number of days ($ D_2 $): 24
  • Hours per day ($ H_2 $): 8
  • Number of men ($ M_2 $): This is what we need to find.

Men Calculation for Target Work

Now, we substitute the known values into the formula:

$ \frac{W_1}{16 \times 8 \times 12} = \frac{3 \times W_1}{M_2 \times 24 \times 8} $

We can cancel out $ W_1 $ from both sides of the equation since it's non-zero:

$ \frac{1}{16 \times 8 \times 12} = \frac{3}{M_2 \times 24 \times 8} $

To solve for $ M_2 $, we rearrange the equation:

$ M_2 = \frac{3 \times (16 \times 8 \times 12)}{(24 \times 8)} $

Now, simplify the calculation:

  • Cancel out the 8 from the numerator and denominator:
  • $ M_2 = \frac{3 \times 16 \times 12}{24} $
  • Simplify $ \frac{12}{24} $ to $ \frac{1}{2} $:
  • $ M_2 = 3 \times 16 \times \frac{1}{2} $
  • Calculate the result:
  • $ M_2 = 3 \times 8 $ $ M_2 = 24 $

Therefore, 24 men are needed to complete the second work.

Was this answer helpful?

Similar Questions

  1. A and B can complete a task in 30 days, whereas A, B and C can complete the same task in 21 days. In how many days can C alone complete the task?
  2. A and C can do a work in 12 days while A, B and C can do the work in 4 days. In how many days can B do the work alone?
  3. Tap A can fill an empty swimming pool in 10 h. Tap B can fill it in 15 h. How much time will the two taps take to fill the empty pool together?
  4. A and B can complete a task in 30 days, whereas A, B and C can complete the same task in 21 days. In how many days can C alone complete the task?
  5. Reena runs at a speed of 8 km/hr. How long will she take to cover 200 m?

  6. A is thrice as good a workman as B and together they can finish a piece of work in 12 days. In how many days can A alone finish the work?

  7. A can complete a piece of work in 18 days. B can complete it in 14 days. With the assistance of C, they completed the work in 7 days. C alone can complete it in_____________ days.

  8. Ajay can do a painting in 12 days. Amit is 70% more efficient than Ajay. What is the number of days Amit would need to finish the same painting?
  9. P is 30% more efficient than Q. How much time will they, working together, take to complete a job that P alone could have done in 23 days?

  10. 8 men and 12 women can build a wall in 10 days. 6 men and 8 women can build the same wall in 14 days. How long will it take for 2 women and 1 man to build it together?


Important Questions from Time and work

  1. 5 men can complete a piece of work in 18 days, while 9 women can do it in 5 days. In how many days can 3 women and 3 men complete this work?
  2. A can lay railway track between two given stations in 16 days and B can do the same job in 11 days. With the help of C, they did the job in 3 days only. Then, C alone can do the job in
  3. A can lay railway track between two given stations in 17 days and B can do the same job in 16 days. With the help of C, they did the job in 4 days only. Then, C alone can do the job in __________

  4. A can do a work in 10 days and B can do the same work in 20 days. If they work on it together for 6 days, then what fraction of the work is left?
  5. Jaya can do a certain piece of work in 30 days. Jaya and Sushma can together do the same work in 21 days, and Jaya, Sushma and Hina can do the same work together in 14 days. In how many days can Jaya and Hina do the same work together?
Need Expert Advice?
Upcoming Exams
RRB Paramedical
November 23, 2026
RRB Staff Nurse
November 23, 2026
Test Series
RRB ALP img
Railways
RRB ALP 2026 Mock Test series
1035 Tests 1 Tests Free
1775 Attempts
4.3(258)
English, Hindi

Start Your Preparation with Prepp Mobile App

Download the app from Google Play & App Store
Download the app from Google Play & App Store
Prepp Mobile App