If 5 workers, working at the same rate, complete a job in 12 days, how many days will 10 workers take to complete the same job?
6 days
The job is fixed in size, so more workers finish sooner: the number of workers and the days taken are inversely proportional.
Measure the fixed job as total effort in worker-days: \(5\ \text{workers}\times12\ \text{days}=60\ \text{worker-days}\).
The same 60 worker-days must now be shared among 10 workers.
So the days required are \(\dfrac{60}{10}=6\ \text{days}\).
The logic is confirmed by proportion: doubling the workforce from 5 to 10 halves the time from 12 to 6 days.
Answers like 5 or 10 days ignore the inverse relationship, and 12 days would mean the extra workers did nothing.
Hence, the answer is 6 days.
Reena runs at a speed of 8 km/hr. How long will she take to cover 200 m?
A is thrice as good a workman as B and together they can finish a piece of work in 12 days. In how many days can A alone finish the work?
A can complete a piece of work in 18 days. B can complete it in 14 days. With the assistance of C, they completed the work in 7 days. C alone can complete it in_____________ days.
P is 30% more efficient than Q. How much time will they, working together, take to complete a job that P alone could have done in 23 days?
A can lay railway track between two given stations in 17 days and B can do the same job in 16 days. With the help of C, they did the job in 4 days only. Then, C alone can do the job in __________